Professional Documents
Culture Documents
Translation
Translation
The building that is being served by Bole Summit Mekanselim Medehanialem Church is narrow in terms
of the congregation used by the church. Therefore, it has been a long time since the church leaders as well
as the believers believed in the construction of a larger building that can serve the believers in a better
way than the existing church. According to this, when it is God's will, a contractor will be selected to
design the church, and after the design is completed, a contractor will be selected from among the
candidates and the construction work will begin. The technical committee has been working on the
construction of this church building since the design until now. The construction project is briefly
described as follows;
The owner of the work: E/O/T/B/K Bola Summit Mkaneselim Be/Kristian
The contractor taken by Wulen: Tesfaye Mekonon Building Contractor
The consulting firm: Sey Consultants Pvt. Ltd
Name of the project: Construction of Bola Summit Christian Church
Date of signing: 24/05/2012
Project start date: 29/05/2012
Time allotted to complete the work: 1460 consecutive days
Project completion date: 28/05/2016
Elapsed time since the start of the project: 560 days
Elapsed time from the start of the work to now in terms of the time given to complete the work:
38.36%
The work done in terms of the total work: around 11%
The price given by the contractor during the tender before the tender, without including the raw
materials needed for the work before VAT 27,066,527.31 Birr including VAT 31,126,506.41 Birr
Since the contractor is the only company that meets the technical standards, if the price is agreed upon
based on the current market, excluding the raw materials needed for the work, 21,958,998.24 Birr
before VAT 25,252,847.97 Birr including VAT
Advance payment paid: 500,000 Birr
Other type: Paid according to the receipt made outside the supply of raw materials
2) The condition of the job
The project is currently 38.36% of the time that has elapsed since the start of the work, and the completed
work is about 11% of the total work. This clearly shows the delay in the work. Reasons that cause the
contractor to take responsibility for the delay in the work;
1) Not assigning qualified and necessary professionals on a foreign basis; As a result, when a job is
stopped due to raw materials, it is possible to find alternative jobs and make a solution to stop the job.
2) Having to do the work on the work list according to the existing procedures and quality standards,
while doing it arbitrarily, there is wasted time when correcting the work.
3) Since the construction is out of date and the contractor's attention to quality is weak, the supervisor
must be present to start the work, and time is wasted due to his absence.
4) The contractor does not receive professional work orders and implement them in time
5) The lack of commitment of the contractor and the consultant to work and perform the work according
to the work plan; Not this, but because of his absence, the work will be damaged when he can afford it.
6) The contractor failed to present the updated work schedule to the consultant for approval. When work
is not being carried out according to the schedule, instead of working on other tasks, the contractor should
inform the consultant that work was not completed due to supply issues.
5) Summary
The structural work of the above-ground church building requires more professional supervision.
However, the contractor has the problem of maintaining professional working methods for each job, as
well as accepting the professional opinions given by talking to the consulting organization and the
technical committees.
For the issues listed above, the technical committee put pressure on both the consultant and the contractor
to ensure that the documents, especially the advance payment and performance guarantees, are submitted
in a legal manner; We were able to understand that the first payment as well as the advance payment were
made without the submission of the said guarantees;
Submitted by the consultant in a letter dated November 10/2 ዏ 13 A.D. with number SAY/147/2012 to
contractor number two payment document proving that the remaining advance payment refund amount
should be fully refunded as well as a performance guarantee from Africa Insurance Bola/Yeka branch
with Bond Number: P/12/1702/21-22/1/00001 prepared by Mile Telekwale.
However, the consultant did not confirm the legality of the performance guarantee; when the technical
committee and the colleagues of the district went to the main and branch offices of the insurance
company and asked the officials concerned, serious doubts were raised about the legality of the document.
Therefore, in order to know the matter correctly and to confirm it in writing, on the date of 20/12/2013, in
the number of S/M/S/D/A/2589/13, the district administration requested an explanation to the insurance
branch office, and in response, on the date "August 26, 2021" in the number "AIC/0032/BY" /21" Work
Performance Guarantee We have explained that the work performance guarantee mentioned in Bond
Number: P/12/1702/21-22/1/00001 from Africa Insurance Bola/Yeka branch is not legal.
Therefore, when the contractor was asked to make operational adjustments at different times, he did not
show commitment to the implementation; Since this contractor's work above ground can cause serious
problems for the work; What's more, the consultants who are participating in this project beyond
themselves by bringing documents that have no legality and can lead to dangerous criminal acts and court
cases; As we have found that the employer and the technical committees as well as this will put the
administration of the parish in unnecessary confusion and liability, and in addition, as we understand that
the execution of our building church project has been jeopardized in terms of documents and work
quality, as a technical committee, the decision to terminate the contract of the contractor without any prior
conditions is necessary if the advice of the advisory council as well as the congregation is needed. If it is
decided to be included, we will respectfully inform you that it will be difficult for us to work with the
contractor.
Furthermore, we would like to point out that following the decision of the council, we are preparing
options for the future operation of the project.
Appendix: ____ page
Decision of the Board of Directors.
Sei Consultants Pvt.
September 2014
Introduction
Bole Summit Mekanselam Dorohaalem Beth Christian has been building a church building since January
24, 2012 under the contractorship of Tesfaye Mekonon Building Contractor and the consulting work of
Sey Consultants. Although orders were given regarding the work performance of the contractor at various
times through letters, meetings and the site book, the contractor failed to show this improved work
performance. Manpower, machinery supply are major contributors to the lack of speed and quality of
work. Based on the repeated discussions and meetings held by the consultant and the technical committee
of the church, it was found necessary to prepare the contractor's work performance in a supporting
document so that the church can take steps to terminate the contract. Accordingly, we do not believe that
the performance of the contractor qualifies for the job in terms of the quality of work, supply of resources
and professional competence required for the construction of the building church. To explain this, we
have prepared and presented the points listed below based on the contractor's performance so far.
According to Article GCC 27.3 (The period between program updates is 45 calendar days) of the Special
Agreement, the contractor shall submit a revised work program within 45 days. However, the contractor
was not doing this and the work performance was presented as follows in terms of the work schedules
submitted by the contractor at different times.
According to the work program submitted by the contractor on 02/10/2013, the work performance
should have reached 65.05% (65.05 percent) and the estimated amount is Birr 14,285,192.76 (fourteen
million two hundred eighty five thousand one hundred ninety two Birr and seventy six cents). In terms of
performance, it shows that it is delayed by 53.44% (53.44 percent). This indicates that the contractor's
performance is low when calculated in terms of Birr 11,685,192.76 (Eleven Million Six Hundred Eighty
Five Thousand One Hundred Ninety Two Birr and Seventy Six Cents).
According to the work program submitted by the contractor on 03/02/2013, the work performance
should have reached 46.30% (46.30 percent), and the estimated amount is Birr 10,167,244.16 (ten
million, one hundred and sixty-seven thousand, two hundred and forty-four Birr and sixteen cents). It
shows that it is delayed by 34.7% (34.7 percent) in terms of the existing work performance. This indicates
that the contractor's performance is low when calculated in terms of Birr 7,567,244.16 (seven million five
hundred sixty seven thousand two hundred forty four Birr and sixteen cents).
According to the last work schedule submitted by the contractor on 16/10/2013, it shows that the
current contractor's work performance should have been 19.5% (19.5 percent) of the total work volume.
This means that the contractor currently has to do work amounting to Birr 4,280,075.2 (birr four million
two hundred eighty thousand seventy five two cents). However, the contractor has done 11.61% (11.61
percent) which is 2,600,000.00 Birr (two million six hundred thousand Birr) and it can be understood that
there is a delay of 7.7% (7.7 percent) in terms of the work schedule.
There are various reasons for the above delays, including resource availability, the Corona epidemic, and
design changes. However, the contractor's professional competence and level, non-delivery of the
expected resource supplies from the contractor, incompleteness of machinery, non-performance of side-
by-side works, poor quality of paperwork and non-delivery will take the biggest part in the delay.
1
Project Manager Bsc. In Civil Engineering or Equivalent
6
3
2
Site Engineer Diploma In Building Engineering
4
2
3
Office Engineer Diploma In Building Engineering
4
2
4
General Foreman Diploma in Construction Technologies or Equivalent
4
3
5 Surveyor Diploma in Surveying 4 2
6 Carpenter Foreman Grade 12 or 10 Complete 10 3
It lists the number of professionals and qualification criteria that the contractor must meet. However, on
the part of the contractor, he is working by assigning a site engineer and an occasional foreman to the site
in a way that does not meet the above requirements. This has created a performance gap of its own.
We confirm that the contractor will not supply construction machinery as stated above. If a small
reinforced concrete mixer is used for rent, the failure of the concrete machinery, the failure of the
vibrator, and the insufficient number of plywood or steel formwork have contributed to the performance
of the work. This has caused its own problems in the performance and quality of work.