INEWVATION INTERNATIONAL CORPORATION

JOB HAZARD ANALYSIS


WORK DESRIPTION: INSTALLATION OF TEMPORARY FACILITY
JHA No: 00001 Project Name: SOLAIRE SMALL OLB Project Location: SOLAIRE SKY GARAGE 5th FLOOR
ACTIVITY HAZARDS PREVENTION/CONTROLS

• Working at Heights • Eye Injuries • Perform a thorough hazard assessment


• Drilling • Electric Shock • Complete Hands On Rotary Hammer Training prior
• Foreign Objects to use
• Working at heights • Perform pre use inspection according to manual
• Slips and trips • Red tag any equipment which does not pass
• Impact inspection
• Penetration/Cuts • Clean the tools air vents by compressed air
• Crush/Pinch • Provide complete PPE
• Chemical/Harmful Dust • Provide FULL BODY HARNESS if Needed
• Heat • Select appropriate drills and bits or attachments
• Environmental that are suitable for the task and material
• Fall of Material • Use of ear muffs when exposed to an 85db noise
• Fall of Person • Always disconnect drills from their power sources
• Repetitive before changing bits or attachments
Motion/Ergonomic • Ensure bits are all properly seated and securely
Concerns tightened in the chuck. Never leave the
adjustment key in the chuck
• Keep drill air vents clear to maintain adequate
ventilation to the internal components.
• Operators of tools and equipment found damage
or defective or otherwise unsafe should
immediately be removed from service
• Never exceed the manufacturers recommended
maximum drilling capacities for the tool or
accessories
• Avoid reaching under or around work pieces or
work surfaces being drilled
• Minimize reaching and/or sitting or working in
awkward positions to prevent strains, soreness
and other discomforts
NAME SIGNATURE DATE
Prepared By: SILVINO A. AYUSTE
Safety Officer 3