LOOK AHEAD POB:120 Well: Conquer-1 Date: 9/27/2020

Monday Tuesday Wednesday Thursday Friday


TIME MAIN AUX TIME MAIN AUX TIME MAIN AUX TIME MAIN AUX TIME MAIN AUX
00:00 Perform DP Calibration 00:00 R/U to Run 22” Casing 00:00 Cement 22” casing 00:00 Perform Dead man test on BOP 00:00 Displace well to 11.0 ppg WBM
Stack
3:00 PU/RB Remaining tubulars inc 3:00 3:00 3:00 3:00
DC´S
6:00 PU/RB Remaining tubulars inc 6:00 P/U & Run 22” Csg +/- 80 joints 6:00 WOC 6:00 Function test diverter system 6:00 Drill out shoe +11´new hole
DC´S
9:00 9:00 9:00 9:00 9:00

12:00 R/U to Pick up 36” jetting 12:00 P-test C/K lines 12:00 WOC 12:00 Wash down Tag Cmt 12:00 Circ/cond hole clean for FIT
conductor
15:00 15:00 15:00 15:00 15:00

19:00 RIH with Jetting String on 6 5/8” 19:00 Circ/prepare for cmt operations 19:00 19:00 Drill out cement 19:00 Perform FIT
DP
22:00 22:00 22:00 R/D cmt equipment 22:00 22:00

Other ongoing operations Other ongoing operations Other ongoing operations Other ongoing operations Other ongoing operations
Diverter function BOP Function Port crane GM

Equipment to rig Equipment to rig Equipment to rig Equipment to rig Equipment to rig
6000bbls 16.3 ppg WBM 22 cutting boxes
22” Cmt Equip / Chems /20 mT Gel

ROV Survey Equip

Equipment from rig Equipment from rig Equipment from rig Equipment from rig Equipment from rig
22” TRS tools

ON Crew change OFF ON Crew change OFF ON Crew change OFF ON Crew change OFF ON Crew change OFF
First flight First flight First flight First flight First flight
6 Catering 6 1 Mud engineer 1 Casing crew 5 6 Rope Access personnel No flight
1 ROV technician 1 No flight 1 Casing hanger rep 1 No flight No flight
Second flight Second flight Second flight Second flight Second flight
1 Driller 1 1 Reamer rep No flight 5 Casing crew No flight
No flight No flight No flight No flight No flight