Work Schedule BANJARI DEVELOPMENT JOB

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

BANJARI ADDITIONAL COAL TRUCK PARKING (Priority 1)

CLIENT: VL
Chainage (RM)
SL NO Cleaning & Embankment GSB Laying WMM Laying PCC laying RCC laying Hume Pipe laying Remarks
From To Grubbing Preparation & encasing

1 Patch A

2 Patch B

NA Around 16772 SQM


area for Truck Parking
3 Patch C
Completed, Curing is
going on & to be
Completed Completed Completed Completed Completed
completed on
4 Patch D 14.10.2022

5 Entry Road 08.10.2022

750 sqm for both Coal


Truck & Exit Parking
6 Exit Road 06.10.2022 to
10.10.2022

NOTE: The above work programme subjected to availability of work fronts & as depending upon the weather conditions.
BANJARI ASH TRUCK PARKING (Priority 1)

CLIENT: VL
Chainage (RM)
SL NO Cleaning & Embankment Preparation GSB Laying WMM Laying PCC laying RCC laying Remarks
From To Grubbing

1 New Parking area WIP & to be completed on To be laid 13.10.2022 To be laid 18.10.2022 Around 5925 SQM area
development 12.10.2022 for Trcuk Parking

Completed NA NA
Perimeter Road
2 around 600 RM in 450 RM completed, balance area to be checked on 16.10.2022 Are around 1200 SQM
APPROX.
length

Existing Ash Truck Dismentaling To


RCC parking be started on 25.10.2022, Curing
To be laid 16.10.2022 to To be laid 19.10.2022
3 damage area 12.10.2022 to NA 18.10.2022 to 21.10.2022 22.10.2022 shall be laying for 14
reparing Patch 1 & completed on days minimum
2 15.09.2022
Area around 2550 SQM
for 05 nos of patchs
approx.
Existing Ash Truck Dismentaling To
RCC parking be stared on 12.11.2022, Curing
To be laid 29.10.2022 to To be laid 03.11.2022 07.11.2022 to
4 damage area 26.10.2022 to NA 01.11.2022 to 06.11.2022 09.11.2022 shall be laying for 14
reparing Patch 3, 4 completed on days minimum
&5 28.10.2022

NOTE: The above work programme subjected to availability of work fronts & as depending upon the weather conditions.
MAIN GATE MATERIALS ENTRY GATE MODIFICATIONS (Priority 1)

CLIENT: VL

SL NO Area Marking Dismenatling Boundary fixing Fabrication & Erection Shifting container by new Paving the Area PCC laying Bituminous/RCC
of Material Entry Gate generation Hydra laying

First stage: 03 no of
container shifting on First stage: 02 no of container Paving/CC
Material Entry Gate Fabrication completed & 28.10.2022 & 30.10.2022 (M 30, 80 mm thickness or as per site
1 erection & Completed To be start on 28.10.2022 To be start on 31.10.2022 will be erected on Second Stage: 02 no of conditions) on 28.10.2022 Second Stage: NA
installation 24.10.2022 container shifting on 02 no of Paving/CC (M 30, 80 mm thickness
or as per site conditions) on 30.10.2022
30.10.2022 & 01.11.2022

Road Widening LHS WMM filling from Bituminous laying


2 (Entry) 05.11.2022 05.11.2022 NA NA NA NA 06.11.2022 to form 11.11.2022 to
08.11.2022 12.11.2022

RCC laying
Road Widening RHS Existing concrete panel PCC laying 19.11.2022 to
(Entry) Wheel Tarck 13.11.2022 NA NA NA NA 17.11.2022 to 22.11.2022,
Washing 13.11.2022 to 16.11.2022 18.11.2022 minimum 14 days
curing reqd.

3 Conteiner Shifting After fixing the Gate 05 conatiner shift from 28.10.2022 to 01.11.2022

Concrete Tiles 25 mm
4 Paver Block fixing Completed Completed Completed NA NA Completed Completed thick will be installed
from 26.10.2022 to
29.10.2022

Bend Beam & Top


Beam of out side
Patch development boundary wall
5 with out side Completed Completed Partially Completed NA NA Completed Completed
Boundary wall installation from
25.10.2022 to
31.10.2022

NOTE: As per site lay out, gate fabrication will be done & shall be start after siging the site lay out plan jointly
Before execution the job passage road reqd. to run the construction equipment
RY GATE MODIFICATIONS (Priority 1)

LIENT: VL

Remarks

Hydra will be arrived for 03 days as


28.10.2022,30.10.2022 &
01.11.2022. Before arrival of Hydra
all types of approvals/permissions
from safety,security & IT dept
reqd. to start this activities.