Jafurah Project(SACE) Master Schedule

Rev.A 2021.12.28
2021 2022 2023 2024 2025
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Phase 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
A/G Piping PO Piperack UT/OS MC
11/14 Effective Date Complete PAS
U/G Piping PO - Initial MTO Erection Finish
Intergrated FAT (IFAT) SRU 1/2 M/C
- Initial MTO Structural Steel PO
Mile - Initial MTO GIS Test Start
GIS & Main S/S
Complete HAZOP Engergizing
stone Review (Contractual) SRU 3 M/C
Receive Others 60% Design Review All IFC Docs All U/G Work
Package Data 30% Design Completion 90% Design Review Issued Finish
Information Review Completion Completion Loop Test
30% Design 60% Design 90% Design Finish
Review Finish Review Finish Review Finish

Eng.
U/G ISO A/G ISO
FEED Data 30% Model 60% Model 90% Model
Review Finish Review Start Review Start Review Start Incinerator /
Thermal Ox. PKG Reactor
Equip. LLI Equip. PO 1st Issue Vessel Vessel
MFG (24M) MFG (25M)
(Reactor, Vessel, PKG Items) MFG (18M) DTS Reactor
All Engineered EQ. PO
DTS

Column
A/G MFG (20M) Column Incinerator /
U/G 1st PO A/G 1st PO Final PO DTS Thermal Ox. PKG DTS
Piping Pipe MFG(3~8M) Valve MFG(7~12M)
Pro.
A/G Final
U/G 1st DTS A/G 1st DTS DTS
PO
230KV GIS GIS
DTS
PO GIS MFG(16M)
PCS Contractual PO PCS MFG(19M) PCS DTS

Start Site Mobilization (Contractual)


Camp 1st Camp 2nd Camp 3rd
Common & Utility (2,000 beds) (2,500 beds) (2,000 beds)
Temporary Facility
& Site Preparation
Site H/O for Site H/O for Foundation Work
Temp. Main Area
(Requested by (Requested by S/S 1st DTS
Contractor) Contractor)
S/S Fabrication
S/S Erection

BLDG Work
Equip. Installation
LLI Equip. Installation
U/G A/G Field
A/G Shop A/G Field Hydro Start Finish Finish
U/G Hydro
Fab.
Start Finish
Piping Work
Con. Electrical & Instrument
EL GIS Installation
SAT
CI PCS Installation
SAT
Pre-comm.
Loop Test
Foundation Work
SRU
S/S DTS
S/S Fabrication
Steel Structure Erection
Equip. Installation
LLI Equip. Installation
U/G Start A/G Shop Fab. A/G Field Hydro A/G Field Finish
Start U/G Finish Hydro Finish
Piping Work
Electrical & Instrument
Pre-comm.
Loop Test