Cement Mill 1 Planned Stoppage

ID Asset Code Description Departemnt Duration % Start Finish


Complete Jan 21, '23 Jan 28, '23
S M T W T F S
1 Production Activities 144 hrs 0% Sun 1/22/23 Sat 1/28/23
2 4611BM1 Cut Feed Production 0 hrs 100% Sun 1/22/23 Sun 1/22/23 1/22
3 4611BM1 Start Feed Production 0 hrs 0% Thu 1/26/23 Thu 1/26/23 1/26
4 Safety Activities 144 hrs 50% Sun 1/22/23 Sat 1/28/23
5 Energy Isolation Electrical 1 hr 100% Sun 1/22/23 Sun 1/22/23
6 Energy De-isolation Electrical 1 hr 0% Sat 1/28/23 Sat 1/28/23
7 Mechanical Activities 144 hrs 82% Sun 1/22/23 Sat 1/28/23
8 4221BE1 Repair cracked buckets by welding Mechanical 2 days 10% Thu 1/26/23 Sat 1/28/23
9 4415BC1 Seal feeding chutes Mechanical 4 hrs 0% Thu 1/26/23 Thu 1/26/23
10 4415BC1 Change drive drum lagging Mechanical 12 hrs 0% Thu 1/26/23 Thu 1/26/23
11 4415BC1 Repair stepped chute Mechanical 1 hr 0% Thu 1/26/23 Thu 1/26/23
12 4415BC1 open feeding chutes inspection doors Mechanical 1 hr 0% Thu 1/26/23 Thu 1/26/23
13 4415BC1 Change side skirts Mechanical 1 hr 0% Thu 1/26/23 Thu 1/26/23
14 4415BC1 Install return skirt at drive drum Mechanical 1 hr 0% Thu 1/26/23 Thu 1/26/23
15 4415SX1 Install scrapper chain Mechanical 4 hrs 50% Thu 1/26/23 Thu 1/26/23
16 4415BC2 open feeding chutes inspection doors Mechanical 1 hr 0% Thu 1/26/23 Thu 1/26/23
17 4417FN1 open fan inspection door Mechanical 1 hr 0% Fri 1/27/23 Fri 1/27/23
18 4417BF1 open discharge hopper inspection door Mechanical 1 hr 0% Fri 1/27/23 Fri 1/27/23
19 4611MD1 Open Main drive bearings for inspectionMechanical 8 hrs 50% Wed 1/25/23 Wed 1/25/23
20 4611MD1 Change oil seals for inboard bearing Mechanical 2 hrs 0% Thu 1/26/23 Thu 1/26/23
21 4611BM1 Open mill for inspection Mechanical 2 hrs 100% Sun 1/22/23 Sun 1/22/23
22 461BM1 open mill discharge chute Mechanical 1 hr 100% Tue 1/24/23 Tue 1/24/23
23 4611BM1 Change air hose for outlet water injection
Mechanical
system 3 hrs 0% Sat 1/28/23 Sat 1/28/23
24 461BM1 open shoe bearings inspection doors Mechanical 4 hrs 50% Thu 1/26/23 Thu 1/26/23
25 4612SR1 Adjusting seal air gap for the separator Mechanical 3 days 100% Sun 1/22/23 Wed 1/25/23
26 4612SR1 Change LSS seal for separator gearboxMechanical 3 days 100% Sun 1/22/23 Wed 1/25/23
27 4612SR1 open separator inspection door Mechanical 1 hr 100% Sun 1/22/23 Sun 1/22/23
28 4615BE1 Repair cracked buckets by welding Mechanical 4 days 100% Sun 1/22/23 Thu 1/26/23
29 4617FN1 Change fan main drive Mechanical 3 days 100% Sun 1/22/23 Wed 1/25/23
30 4617BF1 Open bag filter inspection doors and hopper
Mechanical
inspection
1 hrdoors 0% Fri 1/27/23 Fri 1/27/23
31 4617BF2 Open bag filter inspection doors and hopper
Mechanical
inspection
1 hrdoors 0% Fri 1/27/23 Fri 1/27/23
32 4617FN6 Install cooling fan cover for motor Mechanical 1 hr 100% Sun 1/22/23 Sun 1/22/23
33 4615AS1 open inspection doors Mechanical 2 hrs 0% Fri 1/27/23 Fri 1/27/23
34 4615AS2 open inspection doors Mechanical 2 hrs 0% Fri 1/27/23 Fri 1/27/23
35 4615AS3 open inspection doors Mechanical 2 hrs 0% Fri 1/27/23 Fri 1/27/23
36 4617AS4 open inspection doors Mechanical 2 hrs 0% Fri 1/27/23 Fri 1/27/23
37 4617FN4 open fan bearings for inspection Mechanical 12 hrs 100% Thu 1/26/23 Thu 1/26/23
38 4617FN3 Repair shaft Mechanical 3 days 100% Sun 1/22/23 Sat 1/28/23
39 4915BE1 change driven shaft bearings Mechanical 5 hrs 100% Wed 1/25/23 Wed 1/25/23

Page 1
Cement Mill 1 Planned Stoppage

ID Asset Code Description Departemnt Duration % Start Finish


Complete Jan 21, '23 Jan 28, '23
S M T W T F S
40 4917FN1 Install missing safety guard at coupling Mechanical 1 hr 0% Fri 1/27/23 Fri 1/27/23
41 4915AS1 open inspection doors Mechanical 2 hrs 0% Fri 1/27/23 Fri 1/27/23
42 4915AS2 open inspection doors Mechanical 2 hrs 0% Fri 1/27/23 Fri 1/27/23
43 Inspection Activities 143 hrs 29% Sun 1/22/23 Sat 1/28/23
44 4415BC1 check feeding chute deflectors Inspection 2 hrs 0% Thu 1/26/23 Thu 1/26/23
45 4415BC2 check feeding chute deflectors Inspection 2 hrs 0% Thu 1/26/23 Thu 1/26/23
46 4417FN1 check fan condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
47 4417BF1 check filter condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
48 4611MD1 Check Main drive bearings Inspection 2 hrs 50% Wed 1/25/23 Wed 1/25/23
49 461BM1 Check Mill internals Inspection 2 hrs 100% Sun 1/22/23 Sun 1/22/23
50 461BM1 check shoe bearings and tyre condition Inspection 4 hrs 50% Tue 1/24/23 Thu 1/26/23
51 461BM1 check discharge chute Inspection 2 hrs 100% Tue 1/24/23 Tue 1/24/23
52 4612SR1 check separator Inspection 2 hrs 100% Sun 1/22/23 Sun 1/22/23
53 4617BF1 check bag filter condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
54 4617BF2 check bag filter condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
55 4615AS1 Check Fabric condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
56 4615AS2 Check Fabric condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
57 4615AS3 Check Fabric condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
58 4617FN4 check fan bearings Inspection 2 hrs 100% Thu 1/26/23 Thu 1/26/23
59 4617AS4 Check Fabric condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
60 4915AS1 Check Fabric condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
61 4915AS2 Check Fabric condition Inspection 2 hrs 0% Fri 1/27/23 Fri 1/27/23
62 Electrical Activities 144 hrs 74% Sun 1/22/23 Sat 1/28/23
63 4617FN1.M01 Replace the motor by spare motor of Electrical 8 hrs 100% Sun 1/22/23 Sun 1/22/23
4617FN1.M01 (400kw).
64 4317FN3.M01 Replace the bearing for fan Electrical 4 hrs 0% Mon 1/23/23 Mon 1/23/23
4317FN3.M01
65 C/M1 MCC feeders Inspection & Electrical 2 hrs 100% Mon 1/23/23 Mon 1/23/23
Maintenance.
66 Reactor for C/M1 main drive (HT) Electrical 2 hrs 30% Mon 1/23/23 Mon 1/23/23
Inspection & Maintenance.
67 Reactor for C/M1 fan motor (HT) Electrical 2 hrs 30% Mon 1/23/23 Mon 1/23/23
Inspection & Maintenance.
68 C/M1 Separator panel (4412SR1.M01) Electrical 2 hrs 100% Mon 1/23/23 Mon 1/23/23
Inspection & Maintenance.
69 Check the power cables box of C/M1 Electrical 2 hrs 100% Mon 1/23/23 Mon 1/23/23
main drive(HT) of 4611MD1.M01
70 Check the power cables box of C/M1 Electrical 2 hrs 100% Mon 1/23/23 Mon 1/23/23
Separator motor 4412SR1.M01
71 Check the LRS systems of Electrical 2 hrs 100% Mon 1/23/23 Tue 1/24/23
4611MD1.M01 and 4617FN1.M01.( HT
72 Motors)
Instrumentation Activities 144 hrs 60% Sun 1/22/23 Sat 1/28/23
73 General maintenance for Intensive Instrument 3 hrs 100% Sun 1/22/23 Sun 1/22/23
filter

Page 2
Cement Mill 1 Planned Stoppage

ID Asset Code Description Departemnt Duration % Start Finish


Complete Jan 21, '23 Jan 28, '23
S M T W T F S
74 General maintenance for Thermax Instrument 3 hrs 60% Sun 1/22/23 Sun 1/22/23
filter
75 General maintenance for Lime stone Instrument 3 hrs 40% Sun 1/22/23 Sun 1/22/23
weigh feeder
76 General maintenance for instrument Instrument 3 hrs 40% Sun 1/22/23 Sun 1/22/23
RTD of level switch in cement mill area