SIGN CONTRACT & SECURE BUILDING PERMIT 19 December 2022 28
CLEARING OF SITE 15 January 2023 7 FENCING OF SITE 22 January 2023 7 MOBILIZATION 15 January 2023 7 CONSTRUCT TEMPORARY SITE 15 January 2023 14 OFFICE AND QUARTERS 22 January 2023 7 PURCHASE OF INITIAL MATERIALS 22 January 2023 7 LAYOUT AND SCAFFOLDING 29 January 2023 7 FOOTING EXCAVATION 29 January 2023 14 REBAR AND FRAMEWORK FOR FOOTING 29 January 2023 14 CONCRETING OF FOOTING 12 February 2023 7 BENDING & INSTALL COLUMN RBARS 19 February 2023 7 FORMWORKS OF COLUMNS 26 February 2023 7 CONCRETING OF COLUMNS 5 March 2023 7 BEND AND INSTALL BEAM & GIRDER REBARS 12 March 2023 7 INSTALL BEAM FORMS 12 March 2023 7 CONCRETING OF BEAMS 19 March 2023 7 ROUGHING IN ELECTRICALS 19 March 2023 7 ROUGHING IN PLUMBING 19 March 2023 7 REMOVE COLUMN FORMWORKS 19 March 2023 7 REMOVE BEAM FORMWORKS 19 March 2023 7 INSTALL 1ST. FLR., CHB WALLINGS 12 March 2023 21 PLASTERING 1ST.FLR.INTERIOR 2 April 2023 21 TRUSS FABRICATION & INSTALLATION 26 March 2023 14 ROFFING PURCHASE & INSTALLATION 9 April 2023 7 TILE INSTALLATION , 1ST.FLR. T&B 26 March 2023 14 PLASTERING EXTERIOR SURFACES 19 March 2023 21 INSTALLATION OF DOOR JAMB 2 April 2023 7 INSTALLATION OF WINDOW FRAME 2 April 2023 7 TILE INSTALLATION 1ST.FLR. 2 April 2023 7 INSTALL CEILING JOIST AND COVER 2 April 2023 14 INSTALL ELECTRICAL FIXTURES 9 April 2023 7 INSTALL PLUMBING FIXTURES 9 April 2023 7 INSTALL PANEL,FLUSH & PVC DOORS 9 April 2023 7 INSTALLATION OF WINDOW GLASS 9 April 2023 7 FABRICATION OF CABINETS & HARDWARES 26 March 2023 14 START OF PAINTING INTERIOR WALL 26 March 2023 21 START OF PAINTING EXTERIOR WALL 9 April 2023 14 START OF PAINTING OF CEILING 16 April 2023 7 START OF PAINTING OF DOORS & CABINETS 16 April 2023 7 REMOVAL OF SCAFFOLDING, CLEARING ALL DEBRIS 16 April 2023 14 APPLICATION OF CERTIFICATE OF OCCUPANCY 16 April 2023 14