TASK START DATE DAYS TO COMPLETE

SIGN CONTRACT & SECURE BUILDING PERMIT 19 December 2022 28


CLEARING OF SITE 15 January 2023 7
FENCING OF SITE 22 January 2023 7
MOBILIZATION 15 January 2023 7
CONSTRUCT TEMPORARY SITE 15 January 2023 14
OFFICE AND QUARTERS 22 January 2023 7
PURCHASE OF INITIAL MATERIALS 22 January 2023 7
LAYOUT AND SCAFFOLDING 29 January 2023 7
FOOTING EXCAVATION 29 January 2023 14
REBAR AND FRAMEWORK FOR FOOTING 29 January 2023 14
CONCRETING OF FOOTING 12 February 2023 7
BENDING & INSTALL COLUMN RBARS 19 February 2023 7
FORMWORKS OF COLUMNS 26 February 2023 7
CONCRETING OF COLUMNS 5 March 2023 7
BEND AND INSTALL BEAM & GIRDER REBARS 12 March 2023 7
INSTALL BEAM FORMS 12 March 2023 7
CONCRETING OF BEAMS 19 March 2023 7
ROUGHING IN ELECTRICALS 19 March 2023 7
ROUGHING IN PLUMBING 19 March 2023 7
REMOVE COLUMN FORMWORKS 19 March 2023 7
REMOVE BEAM FORMWORKS 19 March 2023 7
INSTALL 1ST. FLR., CHB WALLINGS 12 March 2023 21
PLASTERING 1ST.FLR.INTERIOR 2 April 2023 21
TRUSS FABRICATION & INSTALLATION 26 March 2023 14
ROFFING PURCHASE & INSTALLATION 9 April 2023 7
TILE INSTALLATION , 1ST.FLR. T&B 26 March 2023 14
PLASTERING EXTERIOR SURFACES 19 March 2023 21
INSTALLATION OF DOOR JAMB 2 April 2023 7
INSTALLATION OF WINDOW FRAME 2 April 2023 7
TILE INSTALLATION 1ST.FLR. 2 April 2023 7
INSTALL CEILING JOIST AND COVER 2 April 2023 14
INSTALL ELECTRICAL FIXTURES 9 April 2023 7
INSTALL PLUMBING FIXTURES 9 April 2023 7
INSTALL PANEL,FLUSH & PVC DOORS 9 April 2023 7
INSTALLATION OF WINDOW GLASS 9 April 2023 7
FABRICATION OF CABINETS & HARDWARES 26 March 2023 14
START OF PAINTING INTERIOR WALL 26 March 2023 21
START OF PAINTING EXTERIOR WALL 9 April 2023 14
START OF PAINTING OF CEILING 16 April 2023 7
START OF PAINTING OF DOORS & CABINETS 16 April 2023 7
REMOVAL OF SCAFFOLDING, CLEARING ALL DEBRIS 16 April 2023 14
APPLICATION OF CERTIFICATE OF OCCUPANCY 16 April 2023 14