COST CRASHING

TIME COST CRASH COST


ACTIVITY
NORMAL CRASH NORMAL CRASH PER DAY
A 14 DAYS 13 DAYS ₱7,980.00 ₱10,260.00 ₱2,280.00
B 14 DAYS 13 DAYS ₱7,980.00 ₱10,260.00 ₱2,280.00
C 14 DAYS 13 DAYS ₱7,980.00 ₱11,400.00 ₱3,420.00
D 21 DAYS 20 DAYS ₱11,970.00 ₱15,390.00 ₱3,420.00
E 21 DAYS 20 DAYS ₱11,970.00 ₱15,390.00 ₱3,420.00
F 21 DAYS 20 DAYS ₱11,970.00 ₱15,390.00 ₱3,420.00
G 7 DAYS 6 DAYS ₱3,990.00 ₱6,270.00 ₱2,280.00
H 7 DAYS 6 DAYS ₱3,990.00 ₱6,270.00 ₱2,280.00
I 14 DAYS 13 DAYS ₱7,980.00 ₱11,400.00 ₱3,420.00
J 21 DAYS 20 DAYS ₱11,970.00 ₱15,390.00 ₱3,420.00
K 7 DAYS 6 DAYS ₱3,990.00 ₱6,270.00 ₱2,280.00
L 21 DAYS 20 DAYS ₱11,970.00 ₱14,250.00 ₱2,280.00
M 7 DAYS 6 DAYS ₱3,990.00 ₱6,270.00 ₱2,280.00
N 7 DAYS 6 DAYS ₱3,990.00 ₱6,270.00 ₱2,280.00
O 7 DAYS 6 DAYS ₱3,990.00 ₱6,270.00 ₱2,280.00
P 14 DAYS 13 DAYS ₱7,980.00 ₱10,260.00 ₱2,280.00
Q 7 DAYS 6 DAYS ₱3,990.00 ₱7,410.00 ₱3,420.00
TOTAL 126 DAYS ₱127,680.00

PATH DURATION
A-B-D-F-I-K-M-P-Q 14+14+21+21+14+7+7+14+7 = 119 DAYS
A-C-D-F-I-K-M-P-Q 14+14+21+21+14+7+7+14+7 = 119 DAYS
A-C-E-F-I-K-M-P-Q 14+14+21+21+14+7+7+14+7 = 119 DAYS
A-C-E-G-J-L-N-P-Q 14+14+21+7+21+21+7+14+7 = 126 DAYS
A-C-E-G-J-L-O-P-Q 14+14+21+7+21+21+7+14+7 = 126 DAYS
A-C-E-H-J-L-N-P-Q 14+14+21+7+21+21+7+14+7 = 126 DAYS
A-C-E-H-J-L-O-P-Q 14+14+21+7+21+21+7+14+7 - 126 DAYS

PATH DURATION
A-C-E-G-J-L-N-P-Q 14+14+21+7+21+21+7+14+7 = 126 DAYS
TIME COST CRASH COST PER
ACTIVITY
NORMAL CRASH NORMAL CRASH DAY
A 14 DAYS 13 DAYS 7980 ₱10,260.00 ₱2,280.00
C 14 DAYS 13 DAYS 7980 ₱11,400.00 ₱3,420.00
E 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱3,420.00
G 7 DAYS 6 DAYS 3990 ₱6,270.00 ₱2,280.00
J 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱3,420.00
L 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱2,280.00
N 7 DAYS 6 DAYS 3990 ₱6,270.00 ₱2,280.00
P 14 DAYS 13 DAYS 7980 ₱10,260.00 ₱2,280.00
Q 7 DAYS 6 DAYS 3990 ₱7,410.00 ₱3,420.00
CRASH: Least expensive Activities A, G, L, N, P with 2,280 cost per day
SUBTRACT: 14 days - 13 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 126 days - 1 day = 125 days
SUBTRACT: 7 days - 6 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 125 days - 1 day = 124 days
SUBTRACT: 21 days - 20 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 124 days - 1 day = 123 days
SUBTRACT: 7 days - 6 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 123 days - 1 day = 122 days
SUBTRACT: 14 days - 13 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 122 days - 1 day = 121 days

PATH DURATION
A-C-E-G-J-L-O-P-Q 14+14+21+7+21+21+7+14+7 = 126 DAYS
TIME COST CRASH COST
ACTIVITY
NORMAL CRASH NORMAL CRASH PER DAY
A 14 DAYS 13 DAYS 7980 ₱10,260.00 ₱2,280.00
C 14 DAYS 13 DAYS 7980 ₱11,400.00 ₱3,420.00
E 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱3,420.00
G 7 DAYS 6 DAYS 3990 ₱6,270.00 ₱2,280.00
J 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱3,420.00
L 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱2,280.00
O 7 DAYS 6 DAYS 3990 ₱6,270.00 ₱2,280.00
P 14 DAYS 13 DAYS 7980 ₱10,260.00 ₱2,280.00
Q 7 DAYS 6 DAYS 3990 ₱7,410.00 ₱3,420.00
CRASH: Least expensive Activities A, G, L, O, P with 2,280 cost per day
SUBTRACT: 14 days - 13 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 126 days - 1 day = 125 days
SUBTRACT: 7 days - 6 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 125 days - 1 day = 124 days
SUBTRACT: 21 days - 20 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 124 days - 1 day = 123 days
SUBTRACT: 7 days - 6 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 123 days - 1 day = 122 days
SUBTRACT: 14 days - 13 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 122 days - 1 day = 121 days

PATH DURATION
A-C-E-H-J-L-N-P-Q 14+14+21+7+21+21+7+14+7 = 126 DAYS
TIME COST CRASH COST
ACTIVITY
NORMAL CRASH NORMAL CRASH PER DAY
A 14 DAYS 13 DAYS 7980 ₱10,260.00 ₱2,280.00
C 14 DAYS 13 DAYS 7980 ₱11,400.00 ₱3,420.00
E 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱3,420.00
H 7 DAYS 6 DAYS 3990 ₱6,270.00 ₱2,280.00
J 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱3,420.00
L 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱2,280.00
N 7 DAYS 6 DAYS 3990 ₱6,270.00 ₱2,280.00
P 14 DAYS 13 DAYS 7980 ₱10,260.00 ₱2,280.00
Q 7 DAYS 6 DAYS 3990 ₱7,410.00 ₱3,420.00
CRASH: Least expensive Activities A, H, L, N, P with 2,280 cost per day
SUBTRACT: 14 days - 13 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 126 days - 1 day = 125 days
SUBTRACT: 7 days - 6 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 125 days - 1 day = 124 days
SUBTRACT: 21 days - 20 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 124 days - 1 day = 123 days
SUBTRACT: 7 days - 6 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 123 days - 1 day = 122 days
SUBTRACT: 14 days - 13 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 122 days - 1 day = 121 days

PATH DURATION
A-C-E-H-J-L-O-P-Q 14+14+21+7+21+21+7+14+7 - 126 DAYS
TIME COST CRASH COST
ACTIVITY
NORMAL CRASH NORMAL CRASH PER DAY
A 14 DAYS 13 DAYS 7980 ₱10,260.00 ₱2,280.00
C 14 DAYS 13 DAYS 7980 ₱11,400.00 ₱3,420.00
E 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱3,420.00
H 7 DAYS 6 DAYS 3990 ₱6,270.00 ₱2,280.00
J 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱3,420.00
L 21 DAYS 20 DAYS 11970 ₱15,390.00 ₱2,280.00
O 7 DAYS 6 DAYS 3990 ₱6,270.00 ₱2,280.00
P 14 DAYS 13 DAYS 7980 ₱10,260.00 ₱2,280.00
Q 7 DAYS 6 DAYS 3990 ₱7,410.00 ₱3,420.00
CRASH: Least expensive Activities A, H, L, O, P with 2,280 cost per day
SUBTRACT: 14 days - 13 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 126 days - 1 day = 125 days
SUBTRACT: 7 days - 6 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 125 days - 1 day = 124 days
SUBTRACT: 21 days - 20 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 124 days - 1 day = 123 days
SUBTRACT: 7 days - 6 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 123 days - 1 day = 122 days
SUBTRACT: 14 days - 13 days = 1 day
MULTIPLY: 1 day x 2,280 = 2,280
SUBTRACT: 122 days - 1 day = 121 days

PATH DURATION
A-C-E-G-J-L-N-P-Q 13+14+21+6+21+20+6+13+7 - 121 DAYS
A-C-E-G-J-L-O-P-Q 13+14+21+6+21+20+6+13+7 - 121 DAYS
A-C-E-H-J-L-N-P-Q 13+14+21+6+21+20+6+13+7 - 121 DAYS
A-C-E-H-J-L-O-P-Q 13+14+21+6+21+20+6+13+7 - 121 DAYS

NORMAL PROJECT COST ₱127,680.00


CRASH A 14 D - 13 D = 1 D x ₱2,280.00 ₱2,280.00
CRASH G 7D-6D=1Dx ₱2,280.00 ₱2,280.00
CRASH H 7D-6D=1Dx ₱2,280.00 ₱2,280.00
CRASH L 21 D - 20 D = 1 D x ₱2,280.00 ₱2,280.00
CRASH N 7D-6D=1Dx ₱2,280.00 ₱2,280.00
CRASH O 7 D - 6D = 1 D x ₱2,280.00 ₱2,280.00
CRASH P 14 D - 13 D = 1 D x ₱2,280.00 ₱2,280.00
TOTAL ₱143,640.00
Project construction time is reduced from 126 days to
CONCLUSION:
121 days to a total cost of ₱143,640.00
TASK START DATE DAYS TO COMPLETE
SIGN CONTRACT & SECURE BUILDING PERMIT 19 December 2022 28
CLEARING OF SITE 15 January 2023 7
FENCING OF SITE 22 January 2023 7
MOBILIZATION 15 January 2023 7
CONSTRUCT TEMPORARY SITE 15 January 2023 14
OFFICE AND QUARTERS 22 January 2023 7
PURCHASE OF INITIAL MATERIALS 22 January 2023 7
LAYOUT AND SCAFFOLDING 29 January 2023 7
FOOTING EXCAVATION 29 January 2023 14
REBAR AND FRAMEWORK FOR FOOTING 29 January 2023 14
CONCRETING OF FOOTING 12 February 2023 7
BENDING & INSTALL COLUMN RBARS 19 February 2023 7
FORMWORKS OF COLUMNS 26 February 2023 7
CONCRETING OF COLUMNS 5 March 2023 7
BEND AND INSTALL BEAM & GIRDER REBARS 12 March 2023 7
INSTALL BEAM FORMS 12 March 2023 7
CONCRETING OF BEAMS 19 March 2023 7
ROUGHING IN ELECTRICALS 19 March 2023 7
ROUGHING IN PLUMBING 19 March 2023 7
REMOVE COLUMN FORMWORKS 19 March 2023 7
REMOVE BEAM FORMWORKS 19 March 2023 7
INSTALL 1ST. FLR., CHB WALLINGS 12 March 2023 21
PLASTERING 1ST.FLR.INTERIOR 2 April 2023 21
TRUSS FABRICATION & INSTALLATION 26 March 2023 14
ROFFING PURCHASE & INSTALLATION 9 April 2023 7
TILE INSTALLATION , 1ST.FLR. T&B 26 March 2023 14
PLASTERING EXTERIOR SURFACES 19 March 2023 21
INSTALLATION OF DOOR JAMB 2 April 2023 7
INSTALLATION OF WINDOW FRAME 2 April 2023 7
TILE INSTALLATION 1ST.FLR. 2 April 2023 7
INSTALL CEILING JOIST AND COVER 2 April 2023 14
INSTALL ELECTRICAL FIXTURES 9 April 2023 7
INSTALL PLUMBING FIXTURES 9 April 2023 7
INSTALL PANEL,FLUSH & PVC DOORS 9 April 2023 7
INSTALLATION OF WINDOW GLASS 9 April 2023 7
FABRICATION OF CABINETS & HARDWARES 26 March 2023 14
START OF PAINTING INTERIOR WALL 26 March 2023 21
START OF PAINTING EXTERIOR WALL 9 April 2023 14
START OF PAINTING OF CEILING 16 April 2023 7
START OF PAINTING OF DOORS & CABINETS 16 April 2023 7
REMOVAL OF SCAFFOLDING, CLEARING ALL DEBRIS 16 April 2023 14
APPLICATION OF CERTIFICATE OF OCCUPANCY 16 April 2023 14