Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 12

DAFTAR KUANTITAS DAN HARGA

NAMA PAKET : PEMBANGUNAN PENYEDIAAN AIR BAKU KOTA GUNUNG SITOLI


SATUAN KERJA : SNVT PJPA SUMATERA II
KEGIATAN KER : AIR TANAH DAN AIR BAKU - I
TAHUN ANGGA : 2022

TOTAL SEBELUM JUMLAH HARGA


HARGA SATUAN PAJAK
NO URAIAN PEKERJAAN SATUAN KUANTITAS PAJAK SETELAH PAJAK
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7 8
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 15,062,067.50 15,062,067.50 11.00 16,718,894.93
2 Fasilitas sementara untuk penyedia jasa (barak gudang) Ls 1.00 61,386,790.62 61,386,790.62 11.00 68,139,337.59
3 Coverdam dan pengeringan Ls 1.00 24,084,000.00 24,084,000.00 11.00 26,733,240.00
4 Penyelidikan tanah Ls 1.00 8,500,000.00 8,500,000.00 11.00 9,435,000.00
5 Biaya SMKK Ls 1.00 48,261,440.00 48,261,440.00 11.00 53,570,198.40
Jumlah Harga Pekerjaan I 157,294,298.12 174,596,670.91
II PEKERJAAN BANGUNAN INTAKE
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 600.00 8,031.89 4,819,134.00 11.00 5,349,238.74
2 Galian tanah berbatu semi mekanis M³ 16.48 78,875.14 1,299,862.31 11.00 1,442,847.16
3 Galian batu semi mekanis M³ 148.35 127,873.16 18,969,983.29 11.00 21,056,681.45
4 Timbunan tanah kembali M³ 10.30 16,063.78 165,456.93 11.00 183,657.20
5 Pembesian Kg 15,158.54 22,557.44 341,937,856.54 11.00 379,551,020.76
6 Bekisting dan Perancah M² 1,341.01 304,374.18 408,168,819.12 11.00 453,067,389.23
7 Beton cor K.100 M³ 12.25 1,264,646.09 15,491,914.60 11.00 17,196,025.21
8 Beton cor K.225 M³ 153.03 1,419,421.91 217,214,134.89 11.00 241,107,689.72
9 Angker Bor Titik 77.00 85,012.07 6,545,929.39 11.00 7,265,981.62
10 Trashrack M² 4.60 1,107,668.99 5,095,277.35 11.00 5,655,757.86
11 Pengadaan dan Pemasangan Pintu Baja 0.60 x 0.80 m Unit 2.00 15,570,340.17 31,140,680.34 11.00 34,566,155.18
12 Pengadaan dan Pemasangan Pintu Baja 0.80 x 1.20 m Unit 1.00 19,733,409.29 19,733,409.29 11.00 21,904,084.31
Jumlah Harga Pekerjaan II 1,070,582,458.05 1,188,346,528.44
III PEKERJAAN PENGADAAN PIPA DAN AKSESORIS
1 Pengadaan pipa GIP ø 250 mm M' 1,150.00 1,397,254.94 1,606,843,181.00 11.00 1,783,595,930.91
2 Pengadaan pipa GIP ø 200 mm M' 10.00 1,155,160.00 11,551,600.00 11.00 12,822,276.00
3 Pengadaan pipa GIP ø 150 mm M' 20.00 644,557.74 12,891,154.80 11.00 14,309,181.83
4 Pengadaan pipa GIP ø 50 mm M' 10.00 173,912.50 1,739,125.00 11.00 1,930,428.75
ø 250 mm x 45⁰
5 Pengadaan bend steel Bh 10.00 812,099.74 8,120,997.40 11.00 9,014,307.11
6 Pengadaan bend steel ø 250 mm x 90⁰ Bh 2.00 1,018,738.69 2,037,477.38 11.00 2,261,599.89
7 Pengadaan Flange steel ø 250 mm Bh 384.00 432,546.30 166,097,779.20 11.00 184,368,534.91
8 Pengadaan Flange steel ø 150 mm Bh 6.00 211,510.28 1,269,061.68 11.00 1,408,658.46
9 Pengadaan Flange buta ø 250 mm Bh 1.00 647,744.56 647,744.56 11.00 718,996.46
10 Pengadaan Gate valve ø 250 mm Bh 2.00 6,328,017.63 12,656,035.26 11.00 14,048,199.14
11 Pengadaan Gate valve ø 200 mm Bh 6.00 4,663,970.05 27,983,820.30 11.00 31,062,040.53
12 Pengadaan Gate valve ø 150 mm Bh 2.00 3,217,289.63 6,434,579.26 11.00 7,142,382.98
13 Pengadaan Tee ø 250 Bh 1.00 2,190,554.23 2,190,554.23 11.00 2,431,515.20
14 Pengadaan Tee ø 200 Bh 2.00 1,471,719.28 2,943,438.56 11.00 3,267,216.80
15 Pengadaan Tee ø 50 Bh 5.00 194,881.13 974,405.65 11.00 1,081,590.27
16 Pengadaan Tee reducer ø 250 ke ø 200 Bh 2.00 1,408,868.62 2,817,737.24 11.00 3,127,688.34
17 Pengadaan Bolt-nut 3/4" x 2,5" Bh 3,840.00 15,000.00 57,600,000.00 11.00 63,936,000.00
18 Pengadaan Packing karet 6 mm Bh 78.13 249,575.89 19,499,364.29 11.00 21,644,294.36
19 Pengadaan spool GIP ø 250 Bh 5.00 3,022,693.53 15,113,467.65 11.00 16,775,949.09
20 Pengadaan spool GIP ø 200 Bh 4.00 2,203,236.12 8,812,944.48 11.00 9,782,368.37
21 Pengadaan spool GIP ø 150 Bh 2.00 1,876,353.13 3,752,706.26 11.00 4,165,503.95
22 Pengadaan Air valve ø 2" Bh 2.00 955,650.00 1,911,300.00 11.00 2,121,543.00
Jumlah Harga Pekerjaan III 1,973,888,474.20 2,191,016,206.36
IV PEKERJAAN PEMASANGAN PERPIPAAN DAN AKSESORIS
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 1,349.60 8,031.89 10,839,838.74 11.00 12,032,221.01
2 Galian tanah biasa kedalaman ≤ 1 m' M³ 240.07 90,439.05 21,711,702.73 11.00 24,099,990.03
3 Galian tanah biasa kedalaman ≥ 1 m' M³ 60.02 108,430.48 6,507,997.41 11.00 7,223,877.12
4 Galian tanah berbatu semi mekanis M³ 20.01 78,875.14 1,578,291.55 11.00 1,751,903.62
5 Galian batu semi mekanis M³ 24.01 127,873.16 3,070,234.57 11.00 3,407,960.37
6 Beton cor K.100 M³ 5.58 1,423,640.02 7,943,911.31 11.00 8,817,741.56
7 Pasangan batu belah camp 1:4 M³ 65.65 1,592,941.01 104,576,577.31 11.00 116,080,000.81
8 Pembesian Kg 5,296.17 23,176.06 122,744,353.69 11.00 136,246,232.60
9 Bekisting Trashblock M² 527.52 179,100.75 94,479,227.64 11.00 104,871,942.68
10 Beton cor K.175 M³ 114.07 1,527,632.94 174,257,089.47 11.00 193,425,369.31
11 Plesteran camp 1:2 M² 191.90 104,917.66 20,133,698.95 11.00 22,348,405.84
12 Timbunan Tanah kembali dipadatkan M³ 112.57 24,663.34 2,776,352.18 11.00 3,081,750.92
13 Timbunan tanah kembali M³ 45.03 16,063.78 723,352.01 11.00 802,920.73
14 Pemasangan pipa GIP ø 250 mm Bh 1,150.00 244,428.91 281,093,246.50 11.00 312,013,503.62
15 Pemasangan Gate valve ø 150 Bh 2.00 380,026.33 760,052.66 11.00 843,658.45
16 Pemasangan Gate valve ø 200 Bh 6.00 477,240.55 2,863,443.30 11.00 3,178,422.06
17 Pemasangan Gate valve ø 250 Bh 2.00 489,267.25 978,534.50 11.00 1,086,173.30
18 Pemasangan Tee ø 250 Bh 1.00 88,705.53 88,705.53 11.00 98,463.14
19 Pemotongan pipa GIP ø 250 mm Bh 10.00 122,074.23 1,220,742.30 11.00 1,355,023.95
20 Pengelasan pipa M' 638.05 358,277.67 228,599,067.34 11.00 253,744,964.75
21 Pekerjaan Besi Plat Strip Kg 72.21 52,719.72 3,806,890.98 11.00 4,225,648.99
22 Baut Bh 250.00 5,854.40 1,463,600.00 11.00 1,624,596.00
23 Angker Bh 70.00 27,631.58 1,934,210.60 11.00 2,146,973.77
24 Mencuci tes jaringan pipa ø 250 mm M' 1,150.00 1,926.35 2,215,302.50 11.00 2,458,985.78
25 Pengecatan pipa manual 3 lapis M² 902.75 253,778.53 229,098,567.96 11.00 254,299,410.43
26 Biaya angkut pipa GIP ø 250 dari direksi keet ke lokasi M' 1,150.00 6,350.00 7,302,500.00 11.00 8,105,775.00
27 Biaya pikul pipa GIP ø 250 ke lokasi pekerjaan M' 1,150.00 19,511.00 22,437,650.00 11.00 24,905,791.50
Jumlah Harga Pekerjaan IV 1,355,205,141.75 1,504,277,707.34
V PEKERJAAN BAK PENAMPUNG
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 450.00 8,031.89 3,614,350.50 11.00 4,011,929.06
2 Galian tanah biasa kedalaman ≤ 1 m' M³ 319.20 90,439.05 28,868,144.76 11.00 32,043,640.68
3 Galian tanah biasa kedalaman ≥ 1 m' M³ 338.16 108,430.48 36,666,851.12 11.00 40,700,204.74
4 Beton cor K.100 M³ 21.92 1,179,032.21 25,844,386.04 11.00 28,687,268.51
5 Timbunan tanah kembali M³ 168.47 16,063.78 2,706,265.02 11.00 3,003,954.17
6 Pembesian Kg 13,018.20 22,148.19 288,329,567.06 11.00 320,045,819.43
7 Bekisting dan perancah untuk lantai M² 17.54 361,985.95 6,349,233.56 11.00 7,047,649.25
8 Bekisting dan perancah untuk dinding M² 628.47 348,962.55 219,312,493.80 11.00 243,436,868.12
9 Beton cor K. 225 M³ 129.32 1,335,010.69 172,643,582.43 11.00 191,634,376.50
10 Pengecatan Dengan Cat Tembok M² 247.02 32,696.79 8,076,761.07 11.00 8,965,204.78
11 Water Stop M' 52.00 115,847.54 6,024,072.08 11.00 6,686,720.01
12 Pekerjaan Besi Plat Strip Kg 23.55 51,806.45 1,220,041.90 11.00 1,354,246.51
13 Pekerjaan Besi Profil Kg 6.28 54,576.46 342,740.17 11.00 380,441.59
14 Pengelasan Besi Profil M' 8.00 358,277.67 2,866,221.36 11.00 3,181,505.71
15 Pengecatan Besi Profil M² 1.00 253,028.02 253,028.02 11.00 280,861.10
16 Baut Bh 48.00 7,138.29 342,637.92 11.00 380,328.09
17 Angker Bh 16.00 27,544.33 440,709.28 11.00 489,187.30
18 Kunci Gembok Bh 4.00 83,478.94 333,915.76 11.00 370,646.49
19 Membuang tanah bekas galian sejauh 500 m M³ 83.94 59,898.28 5,027,861.62 11.00 5,580,926.40
Jumlah Harga Pekerjaan V 809,262,863.46 898,281,778.44
TOTAL HARGA PEKERJAAN 5,366,233,235.58 5,956,518,891.49
PEMBULATAN 5,956,435,284.00

Medan, 08 Juli 2022


Untuk dan atas nama Penyedia : Untuk dan atas nama
CV. Calista Putri Mandiri Pejabat Penandatangan Kontrak
Air Tanah dan Air Baku - I

Wira Darma Sri Wahdina Rangkuti, ST, MT


Direktur NIP. 198601192009122001
REKAPITULASI DAFTAR KUANTITAS DAN HARGA
NAMA PAKET : PEMBANGUNAN PENYEDIAAN AIR BAKU KOTA GUNUNG SITOLI
SATUAN KERJA : SNVT PJPA SUMATERA II
KEGIATAN KERJA : AIR TANAH DAN AIR BAKU - I
TAHUN ANGGARAN : 2022

NOMOR URAIAN KEGIATAN

1 2

I
PEKERJAAN PERSIAPAN

II
PEKERJAAN BANGUNAN INTAKE

III
PEKERJAAN PENGADAAN PIPA DAN AKSESORIS

IV
PEKERJAAN PEMASANGAN PERPIPAAN DAN AKSESORIS

V
PEKERJAAN BAK PENAMPUNG

A TOTAL HARGA PEKERJAAN

B PEMBULATAN

Terbilang : Lima Miliar Sembilan Ratus Lima Puluh Enam Juta Empat Ratus Tiga Puluh Lima Ribu Du

Delapan Puluh Empat Rupiah

Untuk dan atas nama Penyedia :


CV. Calista Putri Mandiri

Wira Darma
Direktur
TULASI DAFTAR KUANTITAS DAN HARGA
ANGUNAN PENYEDIAAN AIR BAKU KOTA GUNUNG SITOLI

JUMLAH HARGA SETELAH PAJAK

174,596,670.91

1,188,346,528.44

2,191,016,206.36

1,504,277,707.34

898,281,778.44

5,956,518,891.49

5,956,435,284.00

tus Lima Puluh Enam Juta Empat Ratus Tiga Puluh Lima Ribu Dua Ratus

Medan, 08 Juli 2022


Untuk dan atas nama
Pejabat Penandatangan Kontrak
Air Tanah dan Air Baku - I

Sri Wahdina Rangkuti, ST, MT


NIP. 198601192009122001
DAFTAR KUANTITAS DAN HARGA
MUTUAL CHECK AWAL (MC 0)

NAMA PAKET : PEMBANGUNAN PENYEDIAAN AIR BAKU KOTA GUNUNG SITOLI


SATUAN KERJA : SNVT PJPA SUMATERA II
KEGIATAN KERJA : AIR TANAH DAN AIR BAKU - I
TAHUN ANGGARAN : 2022

VOLUME VOLUME HARGA SATUAN TOTAL HARGA ADD-I TOTAL HARGA ADD-I TOTAL HARGA MC-0 TOTAL HARGA MC-0
VOLUME VOLUME KONTRAK (SEBELUM PPN) (SESUDAH PPN) (SEBELUM PPN) (SESUDAH PPN)
NO URAIAN PEKERJAAN SATUAN PEKERJAAN PEKERJAAN
ADD-I MC-0
TAMBAH KURANG (Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 6 6 6
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 1.00 - - 15,062,067.500 15,062,067.50 16,718,894.93 15,062,067.50 16,718,894.93
2 Fasilitas sementara untuk penyedia jasa (barak gudang) Ls 1.00 1.00 - - 61,386,790.620 61,386,790.62 68,139,337.59 61,386,790.62 68,139,337.59
3 Coverdam dan pengeringan Ls 1.00 1.00 - - 24,084,000.000 24,084,000.00 26,733,240.00 24,084,000.00 26,733,240.00
4 Penyelidikan tanah Ls 1.00 - 1.00 8,500,000.000 8,500,000.00 9,435,000.00 - -
5 Biaya SMKK Ls 1.00 1.00 - - 48,261,440.000 48,261,440.00 53,570,198.40 48,261,440.00 53,570,198.40
Jumlah Harga Pekerjaan I 157,294,298.12 174,596,670.91 148,794,298.12 165,161,670.91
II PEKERJAAN BANGUNAN INTAKE
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 600.00 500.00 100.00 8,031.890 4,819,134.00 5,349,238.74 4,015,945.00 4,457,698.95
2 Galian tanah berbatu semi mekanis M³ 16.48 4.37 12.11 78,875.140 1,299,862.31 1,442,847.16 344,684.36 382,599.64
3 Galian batu semi mekanis M³ 148.35 121.44 26.91 127,873.160 18,969,983.29 21,056,681.45 15,528,916.55 17,237,097.37
4 Timbunan tanah kembali M³ 10.30 76.77 66.47 16,063.780 165,456.93 183,657.20 1,233,216.39 1,368,870.19
5 Pembesian Kg 15,158.54 7,134.72 8,023.82 22,557.440 341,937,856.54 379,551,020.76 160,941,018.32 178,644,530.33
6 Bekisting dan Perancah M² 1,341.01 270.80 1,070.21 304,374.180 408,168,819.12 453,067,389.23 82,424,527.94 91,491,226.02
7 Beton cor K.100 M³ 12.25 5.39 6.86 1,264,646.090 15,491,914.60 17,196,025.21 6,816,442.43 7,566,251.09
8 Beton cor K.225 M³ 153.03 85.48 67.55 1,419,421.910 217,214,134.89 241,107,689.72 121,332,184.87 134,678,725.20
9 Angker Bor Titik 77.00 - 77.00 85,012.070 6,545,929.39 7,265,981.62 - -
10 Trashrack M² 4.60 - 4.60 1,107,668.990 5,095,277.35 5,655,757.86 - -
11 Pengadaan dan Pemasangan Pintu Baja 0.60 x 0.80 m Unit 2.00 - 2.00 15,570,340.170 31,140,680.34 34,566,155.18 - -
12 Pengadaan dan Pemasangan Pintu Baja 0.80 x 1.20 m Unit 1.00 - 1.00 19,733,409.290 19,733,409.29 21,904,084.31 - -
Jumlah Harga Pekerjaan II 1,070,582,458.05 1,188,346,528.44 392,636,935.86 435,826,998.80
III PEKERJAAN PENGADAAN PIPA DAN AKSESORIS
1 Pengadaan pipa GIP ø 250 mm M' 1,150.00 1,296.00 146.00 1,397,254.940 1,606,843,181.00 1,783,595,930.91 1,810,842,402.24 2,010,035,066.49
2 Pengadaan pipa GIP ø 200 mm M' 10.00 - 10.00 1,155,160.000 11,551,600.00 12,822,276.00 - -
3 Pengadaan pipa GIP ø 150 mm M' 20.00 - 20.00 644,557.740 12,891,154.80 14,309,181.83 - -
4 Pengadaan pipa GIP ø 50 mm M' 10.00 - 10.00 173,912.500 1,739,125.00 1,930,428.75 - -
5 Pengadaan bend steel ø 250 mm x 45⁰ Bh 10.00 10.00 - - 812,099.740 8,120,997.40 9,014,307.11 8,120,997.40 9,014,307.11
6 Pengadaan bend steel ø 250 mm x 90⁰ Bh 2.00 15.00 13.00 1,018,738.690 2,037,477.38 2,261,599.89 15,281,080.35 16,961,999.19
7 Pengadaan Flange steel ø 250 mm Bh 384.00 444.00 60.00 432,546.300 166,097,779.20 184,368,534.91 192,050,557.20 213,176,118.49
8 Pengadaan Flange steel ø 150 mm Bh 6.00 - 6.00 211,510.280 1,269,061.68 1,408,658.46 - -
9 Pengadaan Flange buta ø 250 mm Bh 1.00 1.00 - - 647,744.560 647,744.56 718,996.46 647,744.56 718,996.46
10 Pengadaan Gate valve ø 250 mm Bh 2.00 7.00 5.00 6,328,017.630 12,656,035.26 14,048,199.14 44,296,123.41 49,168,696.99
11 Pengadaan Gate valve ø 200 mm Bh 6.00 - 6.00 4,663,970.050 27,983,820.30 31,062,040.53 - -
12 Pengadaan Gate valve ø 150 mm Bh 2.00 - 2.00 3,217,289.630 6,434,579.26 7,142,382.98 - -
13 Pengadaan Tee ø 250 Bh 1.00 1.00 - - 2,190,554.230 2,190,554.23 2,431,515.20 2,190,554.23 2,431,515.20
14 Pengadaan Tee ø 200 Bh 2.00 - 2.00 1,471,719.280 2,943,438.56 3,267,216.80 - -
VOLUME VOLUME HARGA SATUAN TOTAL HARGA ADD-I TOTAL HARGA ADD-I TOTAL HARGA MC-0 TOTAL HARGA MC-0
VOLUME VOLUME KONTRAK (SEBELUM PPN) (SESUDAH PPN) (SEBELUM PPN) (SESUDAH PPN)
NO URAIAN PEKERJAAN SATUAN PEKERJAAN PEKERJAAN
ADD-I MC-0
TAMBAH KURANG (Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 6 6 6
15 Pengadaan Tee ø 50 Bh 5.00 - 5.00 194,881.130 974,405.65 1,081,590.27 - -
16 Pengadaan Tee reducer ø 250 ke ø 200 Bh 2.00 - 2.00 1,408,868.620 2,817,737.24 3,127,688.34 - -
17 Pengadaan Bolt-nut 3/4" x 2,5" Bh 3,840.00 2,748.00 1,092.00 15,000.000 57,600,000.00 63,936,000.00 41,220,000.00 45,754,200.00
18 Pengadaan Packing karet 6 mm Bh 78.13 105.34 27.21 249,575.890 19,499,364.29 21,644,294.36 26,290,324.25 29,182,259.92
19 Pengadaan spool GIP ø 250 Bh 5.00 - 5.00 3,022,693.530 15,113,467.65 16,775,949.09 - -
20 Pengadaan spool GIP ø 200 Bh 4.00 - 4.00 2,203,236.120 8,812,944.48 9,782,368.37 - -
21 Pengadaan spool GIP ø 150 Bh 2.00 - 2.00 1,876,353.130 3,752,706.26 4,165,503.95 - -
22 Pengadaan Air valve ø 2" Bh 2.00 5.00 3.00 955,650.000 1,911,300.00 2,121,543.00 4,778,250.00 5,303,857.50
Jumlah Harga Pekerjaan III 1,973,888,474.20 2,191,016,206.36 2,145,718,033.64 2,381,747,017.34
IV PEKERJAAN PEMASANGAN PERPIPAAN DAN AKSESORIS
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 1,349.60 1,349.60 - - 8,031.890 10,839,838.74 12,032,221.01 10,839,838.74 12,032,221.01
2 Galian tanah biasa kedalaman ≤ 1 m' M³ 240.07 28.39 211.68 90,439.050 21,711,702.73 24,099,990.03 2,567,564.63 2,849,996.74
3 Galian tanah biasa kedalaman ≥ 1 m' M³ 60.02 - 60.02 108,430.480 6,507,997.41 7,223,877.12 - -
4 Galian tanah berbatu semi mekanis M³ 20.01 9.76 10.25 78,875.140 1,578,291.55 1,751,903.62 769,821.37 854,501.72
5 Galian batu semi mekanis M³ 24.01 106.71 82.70 127,873.160 3,070,234.57 3,407,960.37 13,645,344.90 15,146,332.84
6 Beton cor K.100 M³ 5.58 - 5.58 1,423,640.020 7,943,911.31 8,817,741.56 - -
7 Pasangan batu belah camp 1:4 M³ 65.65 - 65.65 1,592,941.010 104,576,577.31 116,080,000.81 - -
8 Pembesian Kg 5,296.17 4,925.68 370.49 23,176.060 122,744,353.69 136,246,232.60 114,157,855.22 126,715,219.30
9 Bekisting Trashblock M² 527.52 240.33 287.19 179,100.750 94,479,227.64 104,871,942.68 43,043,283.25 47,778,044.40
10 Beton cor K.175 M³ 114.07 46.29 67.78 1,527,632.940 174,257,089.47 193,425,369.31 70,714,128.79 78,492,682.96
11 Plesteran camp 1:2 M² 191.90 - 191.90 104,917.660 20,133,698.95 22,348,405.84 - -
12 Timbunan Tanah kembali dipadatkan M³ 112.57 37.59 74.98 24,663.340 2,776,352.18 3,081,750.92 927,094.95 1,029,075.40
13 Timbunan tanah kembali M³ 45.03 - 45.03 16,063.780 723,352.01 802,920.73 - -
14 Pemasangan pipa GIP ø 250 mm Bh 1,150.00 1,296.00 146.00 244,428.910 281,093,246.50 312,013,503.62 316,779,867.36 351,625,652.77
15 Pemasangan Gate valve ø 150 Bh 2.00 - 2.00 380,026.330 760,052.66 843,658.45 - -
16 Pemasangan Gate valve ø 200 Bh 6.00 - 6.00 477,240.550 2,863,443.30 3,178,422.06 - -
17 Pemasangan Gate valve ø 250 Bh 2.00 7.00 5.00 489,267.250 978,534.50 1,086,173.30 3,424,870.75 3,801,606.53
18 Pemasangan Tee ø 250 Bh 1.00 1.00 - - 88,705.530 88,705.53 98,463.14 88,705.53 98,463.14
19 Pemotongan pipa GIP ø 250 mm Bh 10.00 25.00 15.00 122,074.230 1,220,742.30 1,355,023.95 3,051,855.75 3,387,559.88
20 Pengelasan pipa M' 638.05 1,217.91 579.86 358,277.670 228,599,067.34 253,744,964.75 436,349,957.07 484,348,452.35
21 Pekerjaan Besi Plat Strip Kg 72.21 - 72.21 52,719.720 3,806,890.98 4,225,648.99 - -
22 Baut Bh 250.00 56.00 194.00 5,854.400 1,463,600.00 1,624,596.00 327,846.40 363,909.50
23 Angker Bh 70.00 56.00 14.00 27,631.580 1,934,210.60 2,146,973.77 1,547,368.48 1,717,579.01
24 Mencuci tes jaringan pipa ø 250 mm M' 1,150.00 1,296.00 146.00 1,926.350 2,215,302.50 2,458,985.78 2,496,549.60 2,771,170.06
25 Pengecatan pipa manual 3 lapis M² 902.75 1,058.56 155.81 253,778.530 229,098,567.96 254,299,410.43 268,639,800.72 298,190,178.80
26 Biaya angkut pipa GIP ø 250 dari direksi keet ke lokasi M' 1,150.00 1,290.00 140.00 6,350.000 7,302,500.00 8,105,775.00 8,191,500.00 9,092,565.00
27 Biaya pikul pipa GIP ø 250 ke lokasi pekerjaan M' 1,150.00 12,044.49 10,894.49 19,511.000 22,437,650.00 24,905,791.50 235,000,044.39 260,850,049.27
Jumlah Harga Pekerjaan IV 1,355,205,141.75 1,504,277,707.34 1,532,563,297.90 1,701,145,260.67
TOTAL 4,556,970,372.11 5,058,237,113.05 4,219,712,565.52 4,683,880,947.73
PEMBULATAN 5,058,237,000.00 4,683,880,000.00

Medan, tanggal tersebut di atas

Tim Mutual Check (MC-0)

1. Rendy Yudhistira Ketua 1. …………………..

2. Fronika Manik, ST Sekretaris/ Anggota 2. …………………..

3. Dedy Syaputra Anggota 3. …………………..

4. Buha Edward Sihombing, ST Anggota 4. …………………..


VOLUME VOLUME HARGA SATUAN TOTAL HARGA ADD-I TOTAL HARGA ADD-I TOTAL HARGA MC-0 TOTAL HARGA MC-0
VOLUME VOLUME KONTRAK (SEBELUM PPN) (SESUDAH PPN) (SEBELUM PPN) (SESUDAH PPN)
NO URAIAN PEKERJAAN SATUAN PEKERJAAN PEKERJAAN
ADD-I MC-0
TAMBAH KURANG (Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 6 6 6
5. Junaedi Anggota 5. …………………..
REKAPITULASI PERHITUNGAN MUTUAL CHECK AWAL (MC-0)
NAMA PAKET : PEMBANGUNAN PENYEDIAAN AIR BAKU KOTA GUNUNG SITOLI
SATUAN KERJA : SNVT PJPA SUMATERA II
KEGIATAN KER : AIR TANAH DAN AIR BAKU - I
TAHUN ANGGA : 2022

VOLUME VOLUME
VOLUME ADD - VOLUME
NO URAIAN PEKERJAAN SATUAN PEKERJAAN PEKERJAAN
I MC 0
TAMBAH KURANG
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 1.00 - -

2 Fasilitas sementara untuk penyedia jasa (barak gudang) Ls 1.00 1.00 - -

3 Coverdam dan pengeringan Ls 1.00 1.00 - -

4 Penyelidikan tanah Ls 1.00 - - 1.00 1.00

5 Biaya SMKK Ls 1.00 1.00 - -

Jumlah Harga Pekerjaan I


II PEKERJAAN BANGUNAN INTAKE
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 600.00 500.00 - 100.00

2 Galian tanah berbatu semi mekanis M³ 16.48 4.37 - 12.11 -

3 Galian batu semi mekanis M³ 148.35 121.44 - 26.91 26.91

4 Timbunan tanah kembali M³ 10.30 76.77 - - 66.47

5 Pembesian Kg 15,158.54 7,134.72 - 8,023.82

6 Bekisting dan Perancah M² 1,341.01 270.80 - 1,070.21

7 Beton cor K.100 M³ 12.25 5.39 - 6.86 -

8 Beton cor K.225 M³ 153.03 85.48 - 67.55

9 Angker Bor Titik 77.00 - - 77.00

10 Trashrack M² 4.60 - - 4.60 4.60

11 Pengadaan dan Pemasangan Pintu Baja 0.60 x 0.80 m Unit 2.00 - - 2.00

12 Pengadaan dan Pemasangan Pintu Baja 0.80 x 1.20 m Unit 1.00 - - 1.00 1.00

Jumlah Harga Pekerjaan II


III PEKERJAAN PENGADAAN PIPA DAN AKSESORIS
1 Pengadaan pipa GIP ø 250 mm M' 1,150.00 1,296.00 146.00 -

2 Pengadaan pipa GIP ø 200 mm M' 10.00 - - 10.00 -

3 Pengadaan pipa GIP ø 150 mm M' 20.00 - - 20.00

4 Pengadaan pipa GIP ø 50 mm M' 10.00 - - 10.00

5 Pengadaan bend steel ø 250 mm x 45⁰ Bh 10.00 10.00 - -

6 Pengadaan bend steel ø 250 mm x 90⁰ Bh 2.00 15.00 13.00 -

7 Pengadaan Flange steel ø 250 mm Bh 384.00 444.00 60.00 -

8 Pengadaan Flange steel ø 150 mm Bh 6.00 - - 6.00

9 Pengadaan Flange buta ø 250 mm Bh 1.00 1.00 - -

10 Pengadaan Gate valve ø 250 mm Bh 2.00 7.00 5.00 -

11 Pengadaan Gate valve ø 200 mm Bh 6.00 - - 6.00

12 Pengadaan Gate valve ø 150 mm Bh 2.00 - - 2.00

13 Pengadaan Tee ø 250 Bh 1.00 1.00 - -

14 Pengadaan Tee ø 200 Bh 2.00 - - 2.00

15 Pengadaan Tee ø 50 Bh 5.00 - - 5.00

16 Pengadaan Tee reducer ø 250 ke ø 200 Bh 2.00 - - 2.00 2.00

17 Pengadaan Bolt-nut 3/4" x 2,5" Bh 3,840.00 2,748.00 - 1,092.00

18 Pengadaan Packing karet 6 mm Bh 78.13 105.34 27.21 -

19 Pengadaan spool GIP ø 250 Bh 5.00 - - 5.00

20 Pengadaan spool GIP ø 200 Bh 4.00 - - 4.00

21 Pengadaan spool GIP ø 150 Bh 2.00 - - 2.00

22 Pengadaan Air valve ø 2" Bh 2.00 5.00 - - 3.00

Jumlah Harga Pekerjaan III


IV PEKERJAAN PEMASANGAN PERPIPAAN DAN AKSESORIS
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 1,349.60 1,349.60 - -

2 Galian tanah biasa kedalaman ≤ 1 m' M³ 240.07 28.39 - 211.68 211.68

3 Galian tanah biasa kedalaman ≥ 1 m' M³ 60.02 - - 60.02 60.02

4 Galian tanah berbatu semi mekanis M³ 20.01 9.76 - 10.25 10.25

5 Galian batu semi mekanis M³ 24.01 106.71 82.70 - 82.70

6 Beton cor K.100 M³ 5.58 - - 5.58 5.58


7 Pasangan batu belah camp 1:4 M³ 65.65 - - 65.65 65.65

8 Pembesian Kg 5,296.17 4,925.68 - 370.49 -

9 Bekisting Trashblock M² 527.52 240.33 - 287.19

10 Beton cor K.175 M³ 114.07 46.29 - 67.78

11 Plesteran camp 1:2 M² 191.90 - - 191.90 191.90

12 Timbunan Tanah kembali dipadatkan M³ 112.57 37.59 - 74.98 74.98

13 Timbunan tanah kembali M³ 45.03 - - 45.03 45.03

14 Pemasangan pipa GIP ø 250 mm Bh 1,150.00 1,296.00 146.00 - 146.00

15 Pemasangan Gate valve ø 150 Bh 2.00 - - 2.00 2.00

16 Pemasangan Gate valve ø 200 Bh 6.00 - - 6.00 6.00

17 Pemasangan Gate valve ø 250 Bh 2.00 7.00 5.00 - 5.00

18 Pemasangan Tee ø 250 Bh 1.00 1.00 - -

19 Pemotongan pipa GIP ø 250 mm Bh 10.00 25.00 15.00 -

20 Pengelasan pipa M' 638.05 1,217.91 579.86 -

21 Pekerjaan Besi Plat Strip Kg 72.21 - - 72.21 72.21

22 Baut Bh 250.00 56.00 - 194.00 -

23 Angker Bh 70.00 56.00 - 14.00 14.00

24 Mencuci tes jaringan pipa ø 250 mm M' 1,150.00 1,296.00 146.00 -

25 Pengecatan pipa manual 3 lapis M² 902.75 1,058.56 155.81 -

26 Biaya angkut pipa GIP ø 250 dari direksi keet ke lokasi M' 1,150.00 1,290.00 140.00 -

27 Biaya pikul pipa GIP ø 250 ke lokasi pekerjaan M' 1,150.00 12,044.49 10,894.49 -

Jumlah Harga Pekerjaan IV

Medan, tanggal tersebut di atas


Untuk dan atas nama Penyedia :
Tim Mutual Check (MC-0)
CV. Calista Putri Mandiri
1. Rendy Yudhistira Ketua 1. …………………..

2. Fronika Manik, ST Sekretaris/ Anggota 2. …………………..

3. Dedy Syaputra Anggota 3. …………………..

Wira Darma 4. Buha Edward Sihombing, ST Anggota 4. …………………..


Direktur
5. Junaedi Anggota 5. …………………..
DAFTAR KUANTITAS DAN HARGA
ADDENDUM II

NAMA PAKET : PEMBANGUNAN PENYEDIAAN AIR BAKU KOTA GUNUNG SITOLI


SATUAN KERJA : SNVT PJPA SUMATERA II
KEGIATAN KERJA : AIR TANAH DAN AIR BAKU - I
TAHUN ANGGARAN : 2022

TOTAL SEBELUM JUMLAH HARGA


HARGA SATUAN PAJAK
NO URAIAN PEKERJAAN SATUAN KUANTITAS PAJAK SETELAH PAJAK
(Rp) (Rp) % (Rp)
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 15,062,067.50 15,062,067.50 11.00 16,718,894.93
2 Fasilitas sementara untuk penyedia jasa (barak gudang) Ls 1.00 61,386,790.62 61,386,790.62 11.00 68,139,337.59
3 Coverdam dan pengeringan Ls 1.00 24,084,000.00 24,084,000.00 11.00 26,733,240.00
4 Penyelidikan tanah Ls - 8,500,000.00 - 11.00 -
5 Biaya SMKK Ls 1.00 48,261,440.00 48,261,440.00 11.00 53,570,198.40
Jumlah Harga Pekerjaan I 148,794,298.12 165,161,670.91
II PEKERJAAN BANGUNAN INTAKE
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 500.00 8,031.89 4,015,945.00 11.00 4,457,698.95
2 Galian tanah berbatu semi mekanis M³ 4.37 78,875.14 344,684.36 11.00 382,599.64
3 Galian batu semi mekanis M³ 121.44 127,873.16 15,528,916.55 11.00 17,237,097.37
4 Timbunan tanah kembali M³ 76.77 16,063.78 1,233,216.39 11.00 1,368,870.19
5 Pembesian Kg 7,134.72 22,557.44 160,941,018.32 11.00 178,644,530.33
6 Bekisting dan Perancah M² 270.80 304,374.18 82,424,527.94 11.00 91,491,226.02
7 Beton cor K.100 M³ 5.39 1,264,646.09 6,816,442.43 11.00 7,566,251.09
8 Beton cor K.225 M³ 85.48 1,419,421.91 121,332,184.87 11.00 134,678,725.20
9 Angker Bor Titik - 85,012.07 - 11.00 -
10 Trashrack M² - 1,107,668.99 - 11.00 -
11 Pengadaan dan Pemasangan Pintu Baja 0.60 x 0.80 m Unit - 15,570,340.17 - 11.00 -
12 Pengadaan dan Pemasangan Pintu Baja 0.80 x 1.20 m Unit - 19,733,409.29 - 11.00 -
Jumlah Harga Pekerjaan II 392,636,935.86 435,826,998.80
III PEKERJAAN PENGADAAN PIPA DAN AKSESORIS
1 Pengadaan pipa GIP ø 250 mm M' 1,296.00 1,397,254.94 1,810,842,402.24 11.00 2,010,035,066.49
2 Pengadaan pipa GIP ø 200 mm M' - 1,155,160.00 - 11.00 -
3 Pengadaan pipa GIP ø 150 mm M' - 644,557.74 - 11.00 -
4 Pengadaan pipa GIP ø 50 mm M' - 173,912.50 - 11.00 -
5 Pengadaan bend steel ø 250 mm x 45⁰ Bh 10.00 812,099.74 8,120,997.40 11.00 9,014,307.11
6 Pengadaan bend steel ø 250 mm x 90⁰ Bh 15.00 1,018,738.69 15,281,080.35 11.00 16,961,999.19
7 Pengadaan Flange steel ø 250 mm Bh 444.00 432,546.30 192,050,557.20 11.00 213,176,118.49
8 Pengadaan Flange steel ø 150 mm Bh - 211,510.28 - 11.00 -
9 Pengadaan Flange buta ø 250 mm Bh 1.00 647,744.56 647,744.56 11.00 718,996.46
10 Pengadaan Gate valve ø 250 mm Bh 7.00 6,328,017.63 44,296,123.41 11.00 49,168,696.99
11 Pengadaan Gate valve ø 200 mm Bh - 4,663,970.05 - 11.00 -
12 Pengadaan Gate valve ø 150 mm Bh - 3,217,289.63 - 11.00 -
13 Pengadaan Tee ø 250 Bh 1.00 2,190,554.23 2,190,554.23 11.00 2,431,515.20
14 Pengadaan Tee ø 200 Bh - 1,471,719.28 - 11.00 -
15 Pengadaan Tee ø 50 Bh - 194,881.13 - 11.00 -
16 Pengadaan Tee reducer ø 250 ke ø 200 Bh - 1,408,868.62 - 11.00 -
17 Pengadaan Bolt-nut 3/4" x 2,5" Bh 2,748.00 15,000.00 41,220,000.00 11.00 45,754,200.00
18 Pengadaan Packing karet 6 mm Bh 105.34 249,575.89 26,290,324.25 11.00 29,182,259.92
19 Pengadaan spool GIP ø 250 Bh - 3,022,693.53 - 11.00 -
20 Pengadaan spool GIP ø 200 Bh - 2,203,236.12 - 11.00 -
21 Pengadaan spool GIP ø 150 Bh - 1,876,353.13 - 11.00 -
22 Pengadaan Air valve ø 2" Bh 2.00 955,650.00 1,911,300.00 11.00 2,121,543.00
22.a Pengadaan Air valve ø 2" Bh 3.00 955,650.00 2,866,950.00 11.00 3,182,314.50
Jumlah Harga Pekerjaan III 2,142,851,083.64 2,381,747,017.34
TOTAL SEBELUM JUMLAH HARGA
HARGA SATUAN PAJAK
NO URAIAN PEKERJAAN SATUAN KUANTITAS PAJAK SETELAH PAJAK
(Rp) (Rp) % (Rp)
1 2 3 4 5 6 7
IV PEKERJAAN PEMASANGAN PERPIPAAN DAN AKSESORIS
1 Tebas Tebang dari tanaman/ tumbuhan ø < 15 cm M² 1,349.60 8,031.89 10,839,838.74 11.00 12,032,221.01
2 Galian tanah biasa kedalaman ≤ 1 m' M³ 28.39 90,439.05 2,567,564.63 11.00 2,849,996.74
3 Galian tanah biasa kedalaman ≥ 1 m' M³ - 108,430.48 - 11.00 -
4 Galian tanah berbatu semi mekanis M³ 9.76 78,875.14 769,821.37 11.00 854,501.72
5 Galian batu semi mekanis M³ 106.71 127,873.16 13,645,344.90 11.00 15,146,332.84
6 Beton cor K.100 M³ - 1,423,640.02 - 11.00 -
7 Pasangan batu belah camp 1:4 M³ - 1,592,941.01 - 11.00 -
8 Pembesian Kg 4,925.68 23,176.06 114,157,855.22 11.00 126,715,219.30
9 Bekisting Trashblock M² 240.33 179,100.75 43,043,283.25 11.00 47,778,044.40
10 Beton cor K.175 M³ 46.29 1,527,632.94 70,714,128.79 11.00 78,492,682.96
11 Plesteran camp 1:2 M² - 104,917.66 - 11.00 -
12 Timbunan Tanah kembali dipadatkan M³ 37.59 24,663.34 927,094.95 11.00 1,029,075.40
13 Timbunan tanah kembali M³ - 16,063.78 - 11.00 -
14 Pemasangan pipa GIP ø 250 mm Bh 1,296.00 244,428.91 316,779,867.36 11.00 351,625,652.77
15 Pemasangan Gate valve ø 150 Bh - 380,026.33 - 11.00 -
16 Pemasangan Gate valve ø 200 Bh - 477,240.55 - 11.00 -
17 Pemasangan Gate valve ø 250 Bh 7.00 489,267.25 3,424,870.75 11.00 3,801,606.53
18 Pemasangan Tee ø 250 Bh 1.00 88,705.53 88,705.53 11.00 98,463.14
19 Pemotongan pipa GIP ø 250 mm Bh 25.00 122,074.23 3,051,855.75 11.00 3,387,559.88
20 Pengelasan pipa M' 1,217.91 358,277.67 436,349,957.07 11.00 484,348,452.35
21 Pekerjaan Besi Plat Strip Kg - 52,719.72 - 11.00 -
22 Baut Bh 56.00 5,854.40 327,846.40 11.00 363,909.50
23 Angker Bh 56.00 27,631.58 1,547,368.48 11.00 1,717,579.01
24 Mencuci tes jaringan pipa ø 250 mm M' 1,296.00 1,926.35 2,496,549.60 11.00 2,771,170.06
25 Pengecatan pipa manual 3 lapis M² 1,058.56 253,778.53 268,639,800.72 11.00 298,190,178.80
26 Biaya angkut pipa GIP ø 250 dari direksi keet ke lokasi M' 1,150.00 6,350.00 7,302,500.00 11.00 8,105,775.00
26.a Biaya angkut pipa GIP ø 250 dari direksi keet ke lokasi M' 140.00 3,176.00 444,640.00 11.00 493,550.40
27 Biaya pikul pipa GIP ø 250 ke lokasi pekerjaan M' 12,044.49 19,511.00 235,000,044.39 11.00 260,850,049.27
Jumlah Harga Pekerjaan IV 1,532,118,937.90 1,700,652,021.07

Medan, 08 Desember 2022

Untuk dan atas nama


Untuk dan atas nama Penyedia : Pejabat Penandatangan Kontrak
CV. Calista Putri Mandiri Air Tanah dan Air Baku - I

Wira Darma Sri Wahdina Rangkuti, ST, MT


Direktur NIP. 198601192009122001
REKAPITULASI
DAFTAR KUANTITAS DAN HARGA ADDENDUM II

NAMA PAKET : PEMBANGUNAN PENYEDIAAN AIR BAKU KOTA GUNUNG SITOLI


SATUAN KERJA : SNVT PJPA SUMATERA II
KEGIATAN KERJA : AIR TANAH DAN AIR BAKU - I
TAHUN ANGGARAN : 2022

JUMLAH HARGA
JUMLAH HARGA SETELAH
NO. URAIAN PEKERJAAN SEBELUM PPN
PPN (Rp.)
(Rp.)
1 2 3 3

I PEKERJAAN PERSIAPAN 148,794,298.12 165,161,670.91

II PEKERJAAN BANGUNAN INTAKE 392,636,935.86 435,826,998.80

III PEKERJAAN PENGADAAN PIPA DAN AKSESORIS 2,142,851,083.64 2,381,747,017.34

IV PEKERJAAN PEMASANGAN PERPIPAAN DAN AKSESORIS 1,532,118,937.90 1,700,652,021.07

TOTAL 4,216,401,255.52 4,683,387,708.13


DIBULATKAN 4,683,387,000.00

Medan, 08 Desember 2022

Untuk dan atas nama Penyedia : Untuk dan atas nama :


CV. Calista Putri Mandiri Pejabat Penandatangan Kontrak
Air Tanah dan Air Baku II

Wira Darma Sri Wahdina Rangkuti, ST, MT


Direktur NIP : 198601192009122001

You might also like