Column Base Design :


C15
Input Data

Base length A (m) 3.5


Base width B (m) 2.5
Columns Col 1 Col 2
C (m) 0.25
D (m) 0.35
E (m)
F (m)
Stub column height X (m) 0.85
Base depth Y (m) 0.65
Soil cover Z (m) 0.7
Concrete density (kN/m3) 25
Soil density (kN/m3) 18
Soil friction angle (°) 22
Base friction constant 0.5
Rebar depth top X (mm) 50
Rebar depth top Y (mm) 60
Rebar depth bottom X (mm) 50
Rebar depth bottom Y (mm) 60
ULS ovt LF: Self weight 0.9
ULS LF: Self weight 1.4
Max. SLS bearing pr. (kN/m2) 350
ULS SF Overturning 1
ULS SF Slip 1
fck base (MPa) 25
fck columns (MPa) 25
fy (MPa) 500
Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

Loading Data

Unfactored loads

Column LF LF P Hx Hy Mx My
Load Case: Number ULS ULS (kN) (kN) (kN) (kNm) (kNm)
ovt

1 1 1 1.35 500

Sketch of Base

Eurocode 2 - 2004 Y

C1
X
D1
B

A
Y

Mx
P

Hx

X
Z

Y
Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

Output for Load Case 1


Note: The calculated flexural reinforcement was used in the calculations.

Output for Load Case 1


Soil pressure (ULS) (kN/m2) 117.65
Soil pressure (SLS) (kN/m2) 86.08
SF overturning (ULS) >100
SF overturning (SLS) >100
Safety Factor slip (ULS) >100
Safety Factor slip (SLS) >100
Bottom
Design moment X (kNm/m) 102.01
Reinforcement X (mm2/m) 394
Design moment Y (kNm/m) 44.64
Reinforcement Y (mm2/m) 175
Top
Design moment X (kNm/m) 0.00
Reinforcement X (mm2/m) 0
Design moment Y (kNm/m) 0.00
Reinforcement Y (mm2/m) 0
Linear Shear X (MPa) 0.133
vc (MPa) 0.347
Linear Shear Y (MPa) 0.064
vc (MPa) 0.348
Linear Shear Other (MPa) 0.000
Punching Shear (MPa) 0.069
vc (MPa) 0.347
vcu (MPa) 4.50
v col face (MPa) 1.43
Cost 0.00

Load Case:1 Legend


Max M (+)
Eurocode 2 - 2004 Y Y Max M (-)
Max Shear

0.25 0.25
X X
2.50

2.50

0.35 0.35

3.50 3.50
Y Y

Mx Mx
P P

Hx Hx
0.70

0.70

0.85 0.85

0.65 0.65

86.08 kN/m^2 117.65 kN/m^2

Soil Pressures at SLS Soil Pressures at ULS


Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

Reinforcement Calculation for X-direction:Positive Moments

Load Case: 1

Design moment:102.01 kNm/m

Calculation of the maximum steel strain:

f st
est =
Es
434.78
=
200000
= 0.0022

Balanced neutral axis

d
xb =
est
1+
ec
600
=
.00217
1+
.0035
= 370.370 mm

Maximum allowed neutral axis depth:


5.5
k 1 = 0.44

5.5

100 - %redis
d=
100
100 - 0
=
100
= 1.0000

5.5
Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

k 2 = 1.25

5.5

min ( d - k 1) . d
x= xo,
k2
min (0 - .44 )×600
= 370.11 ,
1.25
= - 211.2000 mm

Depth of rectangular stress block:

a = l. x
= .8 ×268.8
= 215.040 mm

Concrete moment capacity: 6.1

a . . . . .
Mu = a . d - b a f f ck 1×10-6
2
215.04
= 215.04 × 600 - ×1000 ×1 ×.66667 ×25 ×1×10-6
2
= 1 765.057 kNm

Lever arm 6.1

M
z = d . 0.5 + 0.25 -
2 a f b . d 2 . f ck
. . .

1020×105
= 600 × 0.5 + 0.25 -
2 ×1 ×.66667 ×1000 ×600 2 ×25
= 594.856 mm

Tension steel 6.1


Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

M
Ast =
f st . z
1020×105
=
434.78 ×594.86
= 394.381 mm2

Neutral axis depth 6.1

2 . (d - z )
NA =
b
2 ×(600 - 594.86 )
=
.8
= 12.850 mm

Reinforcement Calculation for Y-direction:Positive Moments

Load Case: 1

Design moment:44.64 kNm/m

Calculation of the maximum steel strain:

f st
est =
Es
434.78
=
200000
= 0.0022

Balanced neutral axis

d
xb =
est
1+
ec
590
=
.00217
1+
.0035
= 364.198 mm
Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

Maximum allowed neutral axis depth:


5.5

k 1 = 0.44

5.5

100 - %redis
d=
100
100 - 0
=
100
= 1.0000

5.5
k 2 = 1.25

5.5

min ( d - k 1) . d
x= xo,
k2
min (0 - .44 )×590
= 363.95 ,
1.25
= - 207.6800 mm

Depth of rectangular stress block:

a = l. x
= .8 ×264.32
= 211.456 mm

Concrete moment capacity: 6.1

a . . . . .
Mu = a . d - b a f f ck 1×10-6
2
211.46
= 211.46 × 590 - ×1000 ×1 ×.66667 ×25 ×1×10-6
2
= 1 706.737 kNm

Lever arm 6.1


Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

M
z = d . 0.5 + 0.25 -
2 a f b . d 2 . f ck
. . .

4464×104
= 590 × 0.5 + 0.25 -
2 ×1 ×.66667 ×1000 ×590 2 ×25
= 587.721 mm

Tension steel 6.1

M
Ast =
f st . z
4464×104
=
434.78 ×587.72
= 174.696 mm2

Neutral axis depth 6.1

2 . (d - z )
NA =
b
2 ×(590 - 587.72 )
=
.8
= 5.700 mm

Punching Shear Stress/Reinforcement Calculation

Load Case: 1

Column number:1

The shear force outside the critical perimeter amounts to:162.25 kN

Calculation of required punching shear reinforcement:


Area used for shear

Ash = ucrit . d
= 3 978.5 ×595
= 2.367×106 mm2
Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

% Rebar in X - direction 6.4.3

100 . Asx
F1x =
xb. d
100 ×1 037.3
=
2630 ×595
= 0.0663

% Rebar in Y - direction 6.4.3

100 . Asy
F1y =
yb. d
100 ×436.78
=
2500 ×595
= 0.0294

6.4.3

F1x. F1y
F1 =
10000
.06629 ×.02936
=
10000
= 0.0004

6.4.4

200
k =1 +
d
200
=1 +
595
= 1.580

eq 6.50

v rd1 = CRd_c_sc. k . (100 . F1. f ck)0.3333


= .12 ×1.5798 ×(100 ×.00044 ×25 )0.3333
= 0.1957 MPa

eq 6.3N
Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

v 1 = 0.035 . k 1.5 . f ck
= 0.035 ×1.5798 1.5 × 25
= 0.3475 MPa

v c = max(v 1, v rd1)
= max(.34748 , .19587 )
= 0.3475

Actual Shear stress:

Veff
vv =
Ash
162254
=
2367×103
= 0.0685 MPa

Shear capacity without reinforcement

v c. Ash
Vcap =
1000
.34748 ×2367×103
=
1000
= 822.485 kN

The concrete shear capacity for this perimeter is sufficient: no shear reinforcement required

Shear Stress/Reinforcement Calculation for Y-direction

Load Case: 1

Design shear force:37.67 kN


Based on flexural reinforcement of:175 mm^2/m

Shear Calculations:
Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

Area used for shear calculations:


6.2.2-4

Ash = bw. de - (bw - bf ). bf


= 1000 ×590 - (1000 - 0 )×0
= 590.0×103 mm2

Reinforcement ratio 6.2.2-4

Ast
F1 =
Ash
174.71
=
590000
= 0.0003

F1 = min(F1, 0.02 )
= min( , 0.02 )
= 0.0000×100

6.2.2

200
k =1 +
d
200
=1 +
590
= 1.582

k = min(k , 2 )
= min( , 2 )
= 0.0000×100

6.2.2

v rd1 = CRd_c. k . (100 . F1. f ck)0.333 + k 1. scp


= .12 ×1.5822 ×(100 ×.0003 ×25 )0.333 + .1 ×0
= 0.1725 MPa

6.2.2
Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

v min = 0.035 . k 1.5 . f ck + k 1. scp


= 0.035 ×1.5822 1.5 × 25 + .1 ×0
= 0.3483 MPa

6.2.2

v c = max(v 1, v rd1)
= max(.34829 , .17176 )
= 0.3483

v c = v rd1 = 0.1718 MPa

Shear force capacity with no reinforcement 6.2.2-4

Vco = v c. Ash. 1×10-3


= .34829 ×590000 ×1×10-3
= 205.491 kN

Maximum allowable shear stress

6.2.2-4

f ck
v 1 = 0.6 . 1 -
250
25
= 0.6 × 1 -
250
= 0.5400 MPa

6.2.2-4

v cu = 0.5 . v 1. f . f ck
= 0.5 ×.54 ×.66667 ×25
= 4.500 MPa

Actual Shear stress:


Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

V . 1×103
v=
Ash
37.666 ×1×103
=
590000
= 0.0638 MPa

Design concrete strength 6.2.3

f cd = a cc. f ck. f
= 1 ×25 ×.66667
= 16.667 MPa

Maximum allowable shear force with:


cotq = 2.5

6.2.3

acw. bw. 0.9 . (h - Dcb). v 1. f cd


Vrdmax =
1 .
cotq + 1×103
cotq
1 ×1000 ×0.9 ×(650 - 60 )×.54 ×16.667
=
1
2.5 + ×1×103
2.5
= 1 647.964 kN

since V < Vrdmax kN we can take


cotq = 2.5
(most economical for reinforcement)

Shear reinforcement V<Vco => Asv/sv=0 6.2.3(3)

Min Shear reinforcement factor 9.2.2 (5)

0.08 . f ck
f ac =
f yv
0.08 × 25
=
500
= 0.0008

Minimum links 9.2.2 (5)


Job Number Sheet
Job Title
Client
Your details here
Calcs by Checked by Date

Asv/svn = f ac. b
= .0008 ×1000
= 0.8000

Schematic reinforcement of Base

H10-SA
11H16-A-250 (B1) E E

E E
SECTION: col1
col1

15H16-B-250 (B2)

PLAN

4H16-E

3H10-SA

A
B B B B B B B B B B B B B B B

SECTION