Professional Documents
Culture Documents
Lecture 3 Project Crashing
Lecture 3 Project Crashing
By
Henry Waruhiu
Project Crashing and Time-Cost Trade-Off
Overview
• Project duration can be reduced by assigning more
resources to project activities.
• However, doing this increases project cost.
• Decision is based on analysis of trade-off between time
and cost.
• Project crashing is a method for shortening project
duration by reducing one or more critical activities to a
time less than normal activity time.
Time-Cost Models
A 10 B 10 C 10
• ABC is critical path=30
Crash costCrash
per week wks avail Cheapest way to gain 1
A 500 2 Week is to cut A
B 800 3
C 5,000 2
D 1,100 2
Time-Cost Example D8
A9 B 10 C 10
• ABC is critical path=29
Wks IncrementalTotal
Crash costCrash
GainedCrash $Crash $
per week wks avail 1 500 500
A 500 1
B 800 3
Cheapest way to gain 1 wk
C 5,000 2 Still is to cut A
D 1,100 2
Time-Cost Example D8
A8 B 10 C 10
• ABC is critical path=28
Wks IncrementalTotal
Crash costCrash
GainedCrash $Crash $
per week wks avail 1 500 500
A 500 0 2 500 1,000
B 800 3
Cheapest way to gain 1 wk
C 5,000 2 is to cut B
D 1,100 2
Time-Cost Example D8
A8 B9 C 10
• ABC is critical path=27
Wks IncrementalTotal
Crash costCrash
GainedCrash $Crash $
per week wks avail 1 500 500
A 500 0 2 500 1,000
B 800 2 3 800 1,800
Cheapest way to gain 1 wk
C 5,000 2 Still is to cut B
D 1,100 2
Time-Cost Example D8
A8 B8 C 10
• Critical paths=26 ADC &
ABC
Wks IncrementalTotal
Crash costCrash GainedCrash $Crash $
per week wks avail 1 500 500
2 500 1,000
A 500 0
3 800 1,800
B 800 1 4 800 2,600
C 5,000 2
D 1,100 2 To gain 1 wk, cut B and D,
Or cut C
Cut B&D = $1,900
Cut C = $5,000, So cut B&D
Time-Cost Example D7
A8 B7 C 10
• Critical paths=25 ADC &
ABC
Wks IncrementalTotal
Crash costCrash GainedCrash $Crash $
per week wks avail 1 500 500
2 500 1,000
A 500 0
3 800 1,800
B 800 0 4 800 2,600
C 5,000 2 5 1,900 4,500
D 1,100 1 Can’t cut B any more.
Only way is to cut C
Time-Cost Example D7
A8 B7 C9
• Critical paths=24 ADC &
ABC
Wks IncrementalTotal
Crash costCrash GainedCrash $Crash $
per week wks avail 1 500 500
2 500 1,000
A 500 0
3 800 1,800
B 800 0 4 800 2,600
C 5,000 1 5 1,900 4,500
D 1,100 1 6 5,000 9,500
Only way is to cut C
Time-Cost Example D7
A8 B7 C8
• Critical paths=23 ADC &
ABC
Wks IncrementalTotal
Crash costCrash GainedCrash $Crash $
per week wks avail 1 500 500
2 500 1,000
A 500 0
3 800 1,800
B 800 0 4 800 2,600
C 5,000 0 5 1,900 4,500
D 1,100 1 6 5,000 9,500
7 5,000 14,500
No remaining possibilities to
reduce project length
Time-Cost Example D7