Status As on 30.10.

2021
Himachal Pradesh
Status Of Pre-Construction Activity
Inception Report Feasibility Report Draft DPR Final DPR
LA FC

NHDP NH No. Alignment 3D 3G


SL. Name of Length Date of Stage I Stage II Utility Estimated
Phase/ Name of Project (Old/ Approval 3a 3A Notifica Notifica
No. Consultant (Km) Award Approv Approv Shifting Cost
Scheme New) Target Actual Status Target Actual Target Actual Notificatio Notificatio tion tion Target Actual
al date/ al date/ Estimate
Date Date Date Date Date Date n date/ n date/ date/ date/ Date Date
Area in Area in (in Cr)
Area in Ha Area in Ha Area in Area in
Ha Ha
Ha Ha

DPR

A Total 0.00 0.00

Bharatmala

B Total 0.00 0.00


NH-In Principle

3(a)
3(A)
Hathithan (NH-21)- M/s Lion notification Stage-I
In-principle notification under under
1 NK Manikaran-Pulga Engineering 21 42.938 05.09.2016 10.12.2016 19.12.2016 08.05.2017 02.08.2017 09.07.2017 25.11.2017 published under 16.08.2018 31.12.2018 648.97
Approved notified on process process
Consultants on process
11.10.2018
22.06.2017

Rohru-Jangla-Sungri- 3(a)
3(A)
Taklesh-Sarahan- M/s Lion notification Stage-I
In-principle notification under under
2 NK Jeori (NH-5) Engineering 5 109.6 05.09.2016 10.12.2016 19.12.2016 08.05.2017 11.09.2017 09.07.2017 25.11.2017 published under 16.08.2018 31.12.2018 1688.9
Approved notified on process process
Consultants on process
29.06.2018
22.06.2017

Chandigarh-Karoran-
Tanda-Prempura- 3(a)
3(A)
Gariran-Paploha-Bar- M/s Lion notification Stage-I
In-principle notification under under
3 NK Shilukurd-Jangesh- Engineering 5 45.603 05.09.2016 10.12.2016 19.12.2016 08.05.2017 11.09.2017 09.07.2017 25.11.2017 published under 16.08.2018 31.12.2018 916.33
Approved notified on process process
Kasuali-Dharmpur Consultants on process
29.06.2018
(on NH-5) 22.06.2017

C Total 198.14 3254.20

Grand Total (DPR)


198.14 3254.20
(A+B+C)