PROPOSED ADDITIONAL FLOOR TO AN EXISTING BUILDING FOR PCEA UMOJA CHURCH

Subject : Minutes for Site Inspection


No.6 Date : 25/06/2022
Time : 10.30 – 1.30
Venue : On site – PCEA Umoja Church

IN ATTENDANCE

Item
No NAME POSITION CONTACT

1 T. Kamau Project Architect 0717111912

2 Mwangi Chiera Civil/Structural Engineer 0721584516

3 Job Sisungo Electrical Eng. 0723543117

4 Job Kuria Mechanical Eng. 0722912464

5 Gladys Kinyanjui Committee 0724157565

6 Bernard Njenga K M.C Parkin Limited 0738681748

7 Bernard Njenga M.C Parkin Limited 0724777787

8 Nimrod Maina C.O. W 0718254618

APOLOGIES

Item NAME ORGANISATION CONTACT


No
1 Q. S

CALL TO ORDER
 Opening prayers
 Introduction

AGENDA
1. Stanchion columns GF -1F
2. 2F
3. 3F -4F
4. Wet Areas
5. Lab and allocation of Spaces

item Description Comments

Min/6/1 INSPECTION OF NEW STANCHIONS No work on-going


-GF. The new U.C stanchions were -Pending completion
successfully installed
-The MC is waiting for the close of school
to complete pending works in the area. -the plaster on the walls is
to be stripped off and the
-1. F It was observed that cracks had cause of the crack be
occurred on the walling near the determined.
introduced stanchions. -C/S Eng. Will inspect and
guide on the remedy

Min/6/2 2. F INSPECTION Info


-The M.C to complete reconstruction of No work going on
curved slab Pending Completion
- The M.C to proceed to proceed with
works as guided.
- The reconstructed sections will have a
typical facade as the floors above
Min/6/3 INSPECTION OF 3F AND 4F Info
-The M.C was guided on how to Work is on-going
proceed with the masonry walling -Architect to provide updated
with the determination of the drawings showing new
position of the science lab being positions of walls identifying
agreed upon. the location of the science lab
Date: 1st July 2022
- The M.C was guided to proceed
with installation of doors and -Architect to share the
windows as agreed in the meeting window and door schedule
held on 22nd July 2022 Date: 1st July 2022

Min/6/4 -INSPECTION OF WET AREAS Info


- The MC was guided to follow the -The Architect guided that the
approved layouts for the (pupils) layout is in consideration of
boys’ and girls’ washrooms on either future works
floor as they met the design
standards.

-Windows in the wet areas will be -To follow window schedule


maintained at 1500mm from the
finished floor level
-It was agreed staff men’s
-The MC was guided on the layout for washrooms and lady’s
Staff bathroom washroom are to be placed
on separate floors to ensure
proper utilization of space

-Mech Eng. To provide for


drawings
Min/6/5 LAB AND ALLOCATION OF ROOMS Info
- It was agreed that the science -The architect will issue
lab and lab technicians’ office will revised drawings indicating
be placed on 4F the location of the lab, and
positions of doors and walling
-The MC was guided on how to
proceed with walling in the area -Mechanical Engineer to liaise
with Head Teacher and Lab
Specialist to provide drawings
of service features to be
installed in Science
Laboratory

- Services Engineers will


provide for all specialized
rooms as per design and user
requirements for these
spaces and issue drawings to
M.C

-M.C to proceed with walling


and plaster where services
are ready
Min/6/6 AOB
-The MC was issued with drawings
for the Roof plan and elevation
views.

-The C/S Engineer agreed to update


roof designs

-The R.C slab at the top most level on


the side of the secondary staircase
was determined as the Tank area as
opposed to washrooms for the
Youth Hall.

-The Architect provided drawings for


consideration to guide the Youth Hall
design team on the layout of the
fifth-floor level.

-It was observed that, from 3F, the - The Project Arch. to
floor levels from Imani Towers did guide on solution
not align with those of the new
school block.

There being no other


business, the inspection was
adjourned.
Date for next inspection: To be
communicated

Complied By Nimrod Muna

Clerk of works

Confirmed by:

1. …………………………….
2. …………………………