Milestone Task (Implementation & Maintenance Phase)

Milestone 1 HOTO
Kick-off Meeting & Information gathering
MileStone 2 Planning & Design
Information Gathering & Implementation Plan Discussion
Review scope of installation and implementation HLD
Milestone 3 DR Setup Installation & Go-Live
Shared High Level Diagram & Low Level Diagram
Taking instances on AWS cloud
Configuration of all Infrastructure
Replication Setup b/w DC & DR
System ready for UAT
Go-live & Testing
Observation period
Final Acceptance Test
Milestone 4 Approval of FAT & Project Acceptance

Submission of Test reports

Project documentation handover(Including training Manuals,


Standard Operating Procedures (SOPs), Configuration Procedures
(SCPs), Emergency Operating Procedures (EOPs) and Method of
Procedures (MOPs).)

Implementation Report listing successfully configured and


operational status of Cloud instances.

Training session for managing infra to customer team

Approval of FAT
Timeline (In Weeks) Remarks

T+1

T+1

T+7

T+10