WFN-RW1A Working platform for predrilling works (12d) (Timber) 12/10
25/04A 25/07
Predrilling (6nr., 6d/nr, 1 rig, 36d)
25/06 13/08
Temp piling platform (42d)
15/08 08/10
Soldier piles (29nr., 3d/nr., 2 rigs, 45d)
13/09 25/10
Capping beam (35m, 1d/m, 35d)
03/01A 20/01A
WFN-RW1B Working platform for predrilling works (RW1B &1C) (12d)
21/01A 06/06
Predrilling (RW1B & 1C (7nr., 6d/nr, 1 rig, 42d)
18/06 22/07
Temp piling platform (RW1B & 1C) (28d)
10/10 31/12
Bored piles (14nr., 1.5m dia., 1 rig, 4.3d/pile, 60d)
30/05 20/06
WFN-RW1C Soldier piles (6nr., 3d/nr., 1 rig, 18d)
03/01 17/02
Capping beam (RW1B & 1C) (37m, 1m/d, 37d)
26/07 29/08
WFN-RW2 Temp piling platform (30d)
30/08 20/09
(SP45 to SP56) Predrilling (3nr., 6d/nr, 1 rig, 18d)
09/09 24/10
Soldier piles (12nr., 3d/nr., 1 rig, 36d)
25/10 09/11
Capping beam (14m, 1m/d, 14d)
30/08 13/10
WFN-RW2 Temp piling platform (36d)
14/10 10/11
(SP26 to SP44) Predrilling (4nr., 6d/nr, 1 rig, 24d)
28/10 05/01
Soldier piles (19nr., 3d/nr., 1 rig, 57d)
06/01 04/02 18/09 18/10
Capping beam (23m, 1m/d, 23d) Slope cut & fill WFN-S1 to +76mPD (25d)
19/10 20/11
Upper Part Slope cut & fill WFN-S1 to +84mPD (27d)
07/07A 17/05
WFN-RW2 Predrilling (13nr., 6d/nr, 2 rigs, 42d)
03/01A 25/07
(SP57 to SP77) Soldier piles (36nr., 3d/nr., 1 rig, 108d)
01/06 29/08 21/11 22/12
(SP92 to SP106)Capping beam (75m, 1m/d, 75d) Slope cut & fill WFN-S1 to +92mPD (27d)
23/12 23/01
Slope cut & fill WFN-S3 to +92mPD (24d)
Submitted on 20/05/2022
Page 2 of 15
Wah Fu North Site and Sewerage at Wah Fu Road 11/11/2022 Slope cut & fill WFN-S3 to +92mPD (24d)
17/01 26/02 Erect Permanent Chain Link Fence
(32d)
Submitted on 20/05/2022
Page 3 of 15
12/07A 19/05
WFN-RW3 Temp piling platform (63d)
15/07A 20/05
(SP55 to SP99) Predrilling (12nr., 6d/nr, 2 rigs, 36d)
15/11A 15/07
Soldier piles (45nr., 3d/nr., 1 rig,135d)
31/05 26/08 03/05 06/06
Capping beam (74m, 1m/d, 74d) Slope cut WFN-S2 to +86.5mPD (29d)
31/05 23/06
Construct skin wall WFN-RW3 (20d)
30/06 11/08
WFN-RW3 Temp piling platform (36d)
12/08 08/09
(SP38 to SP54) Predrilling (4nr., 6d/nr, 1 rig, 24d)
02/09 03/11
Soldier piles (17nr., 3d/nr., 1 rig, 51d)
04/11 28/11
Capping beam (21m, 1m/d, 21d)
12/08 23/09
WFN-RW3 Temp piling platform 36d)
24/09 14/10
(SP25 to SP37) Predrilling (3nr., 6d/nr, 1 rig, 18d)
04/11 19/12
Soldier piles (13nr., 3d/nr., 1 rig, 39d)
20/12 10/01
Capping beam (16m, 1m/d, 16d)
24/09 07/11
WFN-RW3 Temp piling platform (36d)
08/11 05/12
(SP01 to SP24) Predrilling (4nr., 6d/nr, 1 rig, 24d)
20/12 20/03
Soldier piles (24nr., 3d/nr., 1 rig, 72d)
21/03 26/04
Capping beam (28m, 1m/d, 28d)
08/09A 14/09A
WFN-RW5 Predrilling (3nr., 6d/nr, 1 rig, 18d)
03/01A 12/03A
Temp piling platform (21d)
17/03A 14/04A
Soldier piles (16nr., 3d/nr., 1 rig, 48d)
17/06 10/07
Capping beam (18m, 1m/d, 18d)
Divert existing stream Stage 1 10/01A 11/04A
23/03A 30/05
Remove existing slope 11SW-C/C98
31/05 29/06
Haul Road - Pok Fu Lam Road to RW4B (25d)
31/05 08/06
WFN-RW4A Temp piling platform (7d)
09/06 29/06
Predrilling (RW4A) (3nr., 6d/nr, 1 rig, 18d)
30/06 08/08
Soldier piles (11nr., 3d/nr., 1 rig, 33d)
09/08 23/08
Capping beam (RW4A) (13m, 1m/d, 13d)
24/08 09/02
WFN-RW4B Bored piles (BP20 to 32) (13nr., 1.5m dia., 1 rig, 10.5d/pile, 137d)
(BP20 to BP32) [Temp Piling Platform > Predrilling > Bored Piles]
24/0
09/06 6 02/08 09/08
WFN-RW4B Stage 1 - BP01 & BP02 (predrilling @ BP01) 03/09
+
13/09
(BP01 to BP19) Stage 2 - BP03 & BP04 (predrilling @ BP04) 05/09 11/10
19/10
Stage 3 - BP05 & BP06 12/10 14/11
Predrilling works cannot be 22/11
Stage 4 - BP07 to BP11 (Predrilling @ BP07 & BP10) carried out concurrently with 12/10
15/11
01/02
construction of temporary 09/02
Stage 5 - BP12 & BP13 (Predrilling @ BP13) piling platform. 02/02 07/03
15/03
Stage 6 - BP14 & BP15 08/03 14/04
12/08 12/09
Construct skin wall WFN-RW3, RW4A & 4B (27d)
Submitted on 20/05/2022
Page 4 of 15
13/09 08/11
Slope cut WFN-S2 to +71.5mPD (46d)
20/10 24/11
Construct skin wall WFN-RW3, RW4B & 5 (30d)
25/11 06/02
Slope cut WFN-S2 to +64.0mPD (59d)
26/02 Construct skin wall WFN-RW3
09/01
(39d)
17/01 26/02
Erect permanent chain link fence (32d)
Submitted on 20/05/2022
Revised Programme (May 2022 Update) (PR10) [Accepted Programme AP12]
2021 2022 2023 2024
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
Data Date
Section 4 (C1, C3 & F9) 14/05/2022 Section 4 Completion Date
22/07A
Predrilling (BP05 to BP23) (10nr, 6d/nr, 1 rig, 60d)15/04A
23/07A 21/09A
Predrilling (BP24 to BP39) (10nr, 6d/nr, 1 rig, 60d)
14/08A 25/11A
WLP-RW1 Temp piling platform (Stage 1) (BP10 to BP22) (49d)
10/06 09/12
WLP-BP08 to BP12 (5nr., 2.5m dia., 1 rig, 30.6d/pile, 153d)
24/12A 22/08
WLP-BP13 to BP17 (5nr., 2.5m dia., 1 rig, 28d/pile, 140d)
02/12A 06/08
WLP-BP18 to BP24 (7nr., 2.5m dia., 1 rig, 21.7d/pile, 152d)
14/05 13/10
Temp piling platform (Stage 2) (BP01 to BP10) (126d)
14/10 27/10
Predrilling BP01 to BP04 (2nr, 6d/nr, 1 rig, 12d)
28/10 14/03
WLP-BP01 to BP04 (4nr., 2.5m dia., 1 rig, 28d/pile, 112d)
10/06 28/09
WLP-BP05 to BP07 (3nr., 2.5m dia., 1 rig, 31d/pile, 93d)
02/09 15/10
Temp piling platform (Stage 3) (BP22 to BP39) (35d)
14/02 14/07
WLP-BP25 to BP36 (12nr., 2.5m dia., 2 rigs, 20.3d/pile, 122d)
10/12 13/02
WLP-BP37 to BP39 (3nr., 2.5m dia., 1 rig, 16.7d/pile, 50d)
15/03 27/03
Capping Beam WLP-BP01 to BP04 (11m, 1m/d, 11d)
28/03 06/04
Capping Beam WLP-BP05 to BP07 (8m, 1m/d, 8d)
11/04 26/04
Capping Beam WLP-BP08 to BP12 (14m, 1m/d, 14d)
27/04 13/05
Capping Beam WLP-BP13 to BP17 (14m, 1m/d, 14d)
22/08 11/09
Capping Beam WLP-BP18 to BP24 (18m, 1m/d, 18d)
15/07 21/08
Capping Beam WLP-BP25 to BP36 (32m, 1m/d, 32d)
14/02 22/02
Capping Beam WLP-BP37 to BP39 (8m, 1m/d, 8d)
23/09 04/11
WSD Meter Construct new WSD meter chamber (35d)
05/11 18/11
Chamber Relocate metering meter by WSD (12d)
19/11 09/12
Demolish existing WSD meter chamer (18d)
29/05A 06/07A
WLP-RW2 Predrilling (RW2 & RW3) (9nr, 6d/nr, 1 rig, 54d)
15/01A 23/03A
Temp piling platform (Stage 1B) (24d)
24/02A 01/09
Bored piles (16nr., 1.5m dia., 1 rig, 10.3d/pile, 165d)
23/02 13/05
Capping beam WLP-RW2 (27m, 1m/d, 64d?)
15/05 12/06
WLP-RW3 Remove temp piling platform
13/06 10/08
Soldier piles (17nr., 3d/nr., 1 rig, 49d?)
11/08 11/10
Capping beam WLP-RW3 (16m, 1m/d, 51d?)
26/08 28/02
Slope cut WLP-S1 to +53.0mPD (soil 10678m3, 200m3/d/Tm; Rock 4207m3, 100m3/d/Tm; 150d?)
27/12 15/03
Construct skin walls for WLP-RW1, RW2 & RW3 (65d)
12/03 12/04
Erect permanent chain link fence (24d)
Submitted on 20/05/2022
Revised Programme (May 2022 Update) (PR10) [Accepted Programme AP12 ]
2021 2022 2023 2024
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Data Date
Section 5 (D1, D4, D5 & F2A) 14/05/2022 Section 5 Completion Date
30/08A 22/01A
Internal haul road for RW4A, RW4B & RW5 (60d)
01/04A 29/06
Realign haul road for RW6 & RW8 (28d)
19/05 29/06
Temp deck over existing stream (35d)
09/04A 24/05
Temp diversion of existing sewerage (42d)
30/06 13/12
Construct 900mm dia. drainage pipes & 900mm step channels from CP3.54 to ST3.60
20/10 29/12
Install 900mm dia. drainage pipes from ST3.60 to SCH7002759 (Section 10 Act ID S101140)
21/06 12/12
Construct twin 250mm dia. sewerage pipes from FM17a to FM26
07/10 28/12
Install 250mm dia. sewerage pipes from SM26 to FMH7024721 (Section 10 Act ID S101145)
Drainage & Sewerage Diversion
29/12/2022
22/11A 18/02A
KLWN-RW4B Temp piling platform (RW4A, RW4B & RW5) (60d)
02/11A 06/12A
Predrilling (8nr., 6d/nr, 2 rigs, 24d)
01/03A 12/12
Bored piles (24nr., 1.5m dia., 1 rig, 9.9d/pile, 237d)
13/12 20/01
Capping beam (RW4B) (31m, 1m/d, 31d)
07/12A 10/12A
KLWN-RW4A Predrilling (2nr., 6d/nr, 1 rig, 12d)
23/07 23/08
Soldier piles (9nr., 3d/nr., 1 rig, 27d)
29/11 12/12
Capping beam (RW4A) (12m, 1m/d, 12d)
20/10A 27/04A
KLWN-RW5 Predrilling (10nr., 6d/nr, 1 rig, 30d?)
24/08 22/11
Soldier piles (49nr., 3d/nr., 2 rigs, 75d)
21/01 19/04
Capping beam (RW5) (69m, 1m/d, 69d)
08/02 25/05
Slope cut KLWN-S7 to +94.0mPD (87d)
01/04A 30/06 14/03 25/05
KLWN-RW8 Temp piling platform (RW6, RW7 & RW8) (60d) Install tie-back for RW5 (58d)
20/12A 30/12A 30/03 12/06
Predrilling (4nr., 6d/nr, 1 rig, 24d) Skin wall RW4A, RW4B & RW5 (58d)
30/05 22/07
Soldier piles (14nr., 3d/nr., 1 rig, 45d)
22/07 02/08
Capping beam (RW8) (20m, 1m/d, 2 teams, 10d)
30/12A 29/01A
KLWN-RW7 Predrilling (7nr., 6d/nr, 1 rig, 42d)
23/07 02/09
Bored piles (3nr., 1.5m dia., 1 rig, 12d/pile, 36d)
03/09 25/11
Bored piles (14nr., 2.5m dia., 1 rig, 10.4d/pile, 145d)
24/06 21/07
Capping beam (RW7) (45m, 1m/d, 2 teams, 23d)
17/12A 07/05A
KLWN-RW6 Predrilling (14nr., 6d/nr, 2 rigs, 42d)
30/06 11/05
Bored piles (28nr., 3.3m dia., 4 rigs, 29.3d/pile, 205d)
20/04 23/06
Capping beam (RW6) (106m, 1m/d, 2 teams, 53d)
12/05 24/07
Rigid barrier - mini-piles (30nr., 2d/nr., 1 rig, 60d)
25/07 04/10
Construct rigid barrier (60d)
27/05 27/10 Slope cut KLWN-S3 to +84.0mPD (127d)
Submitted on 20/05/2022
Revised Programme (May 2022 Update) (PR10) [Accepted Programme AP12]
2021 2022 2023 2024
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
Data Date
Section 6 (E1 & E2) 14/05/2022 Section 6 Completion Date
11/05A 17/06
Tree felling (981nr.)
20/09A 18/12A
Realign existing Wah Fu Rd to allow site access (12d)
08/04A 24/06
Temp decking over existing stream near Shek Pai Wan Road (35d)
Internal haul road - Road Entrance at Shek Pai Wan Rd (Stage 1) (60d) 20/04A 15/06
23/05 02/08
Internal haul road - Wah Fu Rd to RW3D to RW3G (Stage 1) (60d)
16/06 25/08
Internal haul road - from Shek Pai Wan Rd to RW3E, F & G (Stage 2) (60d)
22/07 20/10
Temp piling platform (RW3D to RW3H-BP05) (75d)
17/09A 16/12A
KLWS-RW3G Predrilling (7nr., 6d/nr, 2 rigs, 30d)
14/09 22/02
Bored piles (15nr., 3.3m dia., 3 rigs, 25.9d/pile, 131d)
12/04 12/06
Capping beam (51m, 1m/d, 51d)
19/01A 07/04A
KLWS-RW3E Predrilling (8nr., 6d/nr, 2 rigs, 30d)
14/09 27/05
Bored piles (20nr., 3.3m dia., 3 rigs, 30.6d/pile, 206d)
14/04 05/07
Capping beam (67m, 1m/d, 67d)
08/04A 28/04A
KLWS-RW3D Predrilling (3nr., 6d/nr, 1 rig, 18d)
29/05 28/09
Bored piles (5nr., 3m dia., 1 rig, 21.4d/pile, 104d)
29/09 20/10
Capping beam (17m, 1m/d, 17d)
Slope cut of KLWS-S2 to +70mPD
can not commence before
17/12A 17/01A completion of bored piling works
KLWS-RW3F Predrilling (6nr., 6d/nr, 1 rig, 36d)
at KLWS-RW3D and 3H (BP01 to
23/02 06/07 BP07).
Bored piles (12nr., 2.5m dia., 2 rigs, 17.5d/pile, 105d)
13/06 25/07
Capping beam (35m, 1m/d, 35d)
26/07 16/12
Rigid Barrier (120d)
21/10 17/11
KLWS-RW3H Predrilling (4nr., 6d/nr, 1 rig, 24d)
23/02 01/08
(BP01 to BP07) Bored piles (7nr., 3m dia., 1 rig, 18d/pile, 126d)
26/07 22/08
Capping beam (24m, 1m/d, 24d)
06/07 22/12 Slope cut KLWS-S2 to +70.0mPD (142d)
Install soil nail, tie-back for RW3E &
05/09 09/01 RW3G
& skin walls for RW3D to RW3H (94d)
06/07 07/08
Internal haul road - +70mPD platform to Shek Pai Wan Rd (Stage 4) (28d)
19/07 05/09
KLWS-RW3H Temp piling platform (RW3H to RW3J) (42d)
04/08 07/09
(BP08 to BP17) Predrilling (4nr., 6d/nr, 1 rig, 30d)
06/09 05/06
Bored piles (10nr., 3m dia., 1 rig, 22.6d/pile, 219d)
Slope cut of KLWS-S2 to +58mPD 14/05 22/06
Capping beam 33m, 1m/d, 33d)
can not commence before
completion of bored piling works 12/01 19/02 Slope cut KLWS-S2 to
at KLWS-RW3H (BP08 to BP17). +66.0mPD (30d)
09/02 06/03
Skin wall for RW3H (20d)
29/09 26/10
KLWS-RW3C Temp piling platform (RW3C) (21d)
30/04A 27/05
Predrilling (3nr., 6d/nr, 1 rig,18d)
27/10 23/01
Bored piles (8nr., 1.5m dia., 1 rig, 9d/pile,72d)
24/01 09/02
Capping beam (15m, 1m/d, 15d)
03/05 05/06
Internal haul road - Main haul Rd to KLWS-RW3J (Stage 5) (28d)
08/09 21/09
KLWS-RW3J Predrilling (2nr., 6d/nr, 1 rig, 12d)
06/06 27/07
Bored piles (5nr., 1.5m dia., 1 rig, 8.4d/pile, 43d)
29/07 07/08
Capping beam (9m, 1m/d, 9d)
Slope cut KLWS-S2 08/08 07/11
to +51.0mPD (76d)
Skin walls for 24/09 23/11
RW3B & RW3J (51d)
24/09 13/11
KLWS-RW3A (1 bay, 42d/bay, 42d)
30/01
Slope cut KLWS-S1 to +79.0mPD (6d) 24/01
10/02 07/03
Slope cut KLWS-S1 to +71.5mPD (20d)
08/03 28/03
Install soil nails KLWS-S1 RD-BA to BG (88nr,18d)
26/03 29/04
Slope cut KLWS-S1 to +64.0mPD (26d)
30/04 25/05
Install soil nails KLWS-S1 RD-AJ to AZ (105nr, 21d)
01/06 20/06
Install soil nails KLWS-S1 RD-AA to AH (77nr., 16d)
03/05 15/07
KLWS-RW1 Predrilling (10nr., 6d/nr, 2 rigs, 30d)
01/06 24/10
SHPs (89nr., 4d/nr., 3 rigs, 120d)
26/07 08/11
Construct retaining wall (5 bays, 21d/bay, 105d)
21/06 09/08
KLWS-RW2A (1 bay, 42d/bay, 42d)
21/06 28/09
KLWS-RW2B (2 bays, 42d/bay, 84d)
10/08 28/09
KLWS-RW2C (1 bay, 42d/bay, 42d)
21/10 23/11
Erect permanent chain link fence (30d)
Submitted on 20/05/2022
Revised Programme (May 2022 Update) (PR10) [Accepted Programme AP12 ]
2021 2022 2023 2024 2025 2026
ACTIVITY 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9
Data Date
Section 7 (A5, A6, A7 & D3) 14/05/2022 Section 7 Completion Date
Kai Lung Wan North Site (Western Part) & Bus Layby at Wah King Street 20/01/2025
06/04
A 30/07
Internal haul road (90d)
13/06 04/08
KLWN-RW1 Temp. piling platform (45d)
12/07 20/09
Predrilling (10nr., 6d/nr., 1 rig, 60d)
13/08 02/08
Bored piles (27nr., 2m dia.; 2 nr., 2.5m dia., 3 rigs, 9.9d/pile, 287d?) (345d?) (420m soil, 5m/d/Tm, 761m rock, 0.8m/d/RCD, 345d)
16/02 18/08
Capping beam (75m, 1m/d, 150d) (75d?)
16/02 31/05
KLWN-RW2 (4 bays, 21d/bay, 84d)
29/02 23/03
KLWN-RW3 (1 bay, 21d/bay, 21d)
16/02 06/04
Flexible barrier (42d)
05/06 31/10
Slope cut KLWN-S1 & S2 to +85.0 mPD (11860m soil, 200m3/d/Tm, 2nr excavators; 18505m rock, 100m3/d/Tm, 2nr breakers; 123d)
25/07 31/10
Soil nail RW1 (137 nr, 82d, 1.7nr/d)
10/08 16/11
Skin wall RW1 (82d)
17/11 28/02
Slope cut KLWN-S1 & S2 to final road level (82d)
03/01 15/04
Soil nail RW1 (241 nr, 82d, 2.9nr/d)
03/01 15/04
Skin wall RW1 (82d)
29/02 14/06
Utility works, road works & covered walkway on access road
Road Bridge
08/12A 27/06
East Abut Predrilling (10nr., 6d/nr., 1 rig, 60d)
02/03 19/06
Bored piles (10nr., 2m dia., 1 rig, 8.8d/pile, 88d)
20/06 24/07
Pile test (28d)
25/03 27/06
Pile cap & abutment (90d)
01/11 16/02
West Abut Predrilling (10nr., 6d/nr., 1 rig, 60d)
01/12 16/02
Temp. piling platform (60d)
17/0
2 05/06
Bored piles (10nr., 2m dia., 1 rig, 8.8d/pile, 88d)
06/06 10/07
Pile test (28d)
11/07 26/10
Pile cap & abutment (75d)
28/10 08/01
Bridge Deck Erect temp. deck (60d)
09/01 22/02
Construct road bridge deck (36d)
24/02 28/05
Prestressing & deck finish works (75d)
submitted on 20/05/2022
Revised Programme (May 2022 Update) (PR10) [Accepted Programme AP12]
2022 2023 2024 2025 2026
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7
Data Date
Section 8 (C2 & C3) 14/05/2022 Section 8 Completion Date
01/06 15/07
Pilecap 2B Predrilling (6nr., 6d/nr., 1 rig, 36d) 24/0
尸
6 05/08
(at KLWS Bored piles (6nr., 1.2m dia., 1 rig, 6d/pile, 36d)
06/08 02/09
site) Pile test (28d)
03/09 28/10
Pile cap (45d)
29/10 27/01
Column, staircase & lift tower (75d)
28/01 24/02
Backfill to final ground level (21d)
Construct temp piling Backfill to final G.L. 08/0 Backfill
15/0 to final G.L.
platform for FR323 04/04 7 9
19/03
FR323-RW5&RW6 FR323-RW1
03/12 16/01
Pilecap 2A Predrilling (6nr., 6d/nr., 1 rig, 36d)
Works for FB2 Pile Cap 2A 30/12 13/02
(near FR323) Bored piles (6nr., 1.2m dia., 1 rig, 6d/pile, 36d) can commence only after
the new land supported by
14/02 13/03
Pile test (28d) FR323-RW1 & RW6 is
formed.
14/03 12/05
Pile cap (45d)
13/05 09/08
Column, staircase & lift tower (75d)
11/08 03/09
Backfill to final ground level (21d)
23/04 09/08
Bridge Deck Off-site fabrication of deck (90d)
11/08 08/11
Deliver & assemble bridge deck on site (75d)
18/09 08/11
Temp. middle supports for deck erection (42d)
Bridge deck erection @ N/B 10/11
24/11
Bridge deck erection @ S/B
24/11 04/02
Bridge deck in-situ works
29/0
07/01 4
E&M & finishing works and Lift Installation
30/04 03/06
T&C
Submitted on 20/05/2022
Revised Programme (May 2022 Update) (PR10) [Accepted Programme AP12]
2022 2023 2024 2025 2026 2027
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 1 2 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3
Data Date
Section 10 (F1, F2, F5 & F6) 14/05/2022
Section 10 Completion Date
Features FR36 & FR323, Shek Pai Wan Rd & Widened Pok Fu Lam Rd 21/12/2026
Wah Fu Road
20/10 29/12
900mm dia. drainage pipe from ST3.60 to SCH7002759 (S101140)
07/10 28/12
250mm dia. sewerage pipe from FM26 to FMH7024721 (S101145)
Footbridge FB1 19/02
Complete
Submitted on 20/05/2022
Piling Works (March 2022 Update) (PR09A) [Accepted Programme AP11]
2021 2022 2023 2024 2025
ACT ID ACTIVITY
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9
Data Date
WLP Site - Section 4 26/03/2022
30/11A 10/06
RW1 BP11 to BP22 (12 nr., 2.5m dia., 2 rigs, 13d/pile) 2 bored piling rigs
24/02A 08/07
RW2 (16 nr., 1.5m dia., 1 rig, 6d/pile) 1 bored piling rig
27/08 28/10
RW3 (17 nr., 5d/nr, 1 rig) 1 soldier piling rig
11/06 19/08
RW1 BP05 to BP10 (6 nr., 2.5m dia., 2 rigs, 19.7 d/pile) 2 bored piling rigs
19/08 19/12
RW1 BP23 to BP39 (17 nr., 2.5m dia., 2 rigs, 12 d/pile) 2 bored piling rigs
20/08 30/11
RW1 BP01 to BP04 (4 nr., 2.5m dia., 1 rig, 21.3 d/pile) 1 bored piling rig
07/09 22/02
RW4B (BP20 to BP32) (13nr., 1.5m dia., 1 rig, 10.5 d/pile) 1 bored piling rig
15/11A 16/06
RW3 (SP55 to SP99) (45 nr., 3d/nr, 1 rig) 1 soldier piling rig
03/01A 05/07
RW2 (SP57 to SP77) (36 nr., 3d/nr, 1 rig) 1 soldier piling rig
17/03A 23/04
RW5 (16 nr., 3d/nr, 1 rig) 1 soldier piling rig
04/04 10/06
RW6 (Bays 1 & 2) (26 nr., 4d/nr, 2 rigs) 2 soldier piling rigs
15/07 22/08
RW4A (11 nr., 3d/nr, 1 rig) 1 soldier piling rig
09/08 30/09
RW1A (29 nr., 3d/nr, 2 rigs) 2 soldier piling rigs
20/08 03/10
RW2 (SP45 to SP56) (12 nr., 3d/nr, 1 rig) 1 soldier piling rig
20/08 21/10
RW3 (SP38 to SP54) (17 nr., 3d/nr, 1 rig) 1 soldier piling rig
22/09 14/10
RW1C (6 nr., 3d/nr, 1 rig) 1 soldier piling rig
08/10 13/12
RW2 (SP26 to SP44) (19 nr., 3d/nr, 1 rig) 1 soldier piling rig
22/10 06/12
RW3 (SP25 to SP37) (13 nr., 3d/nr, rig) 1 soldier piling rig
07/12 06/03
RW3 (SP01 to SP24) (24 nr., 3d/nr, 1 rig) 1 soldier piling rig
28/12 04/02
RW6 (Bay 3) (15 nr., 4d/nr, 2 rigs) 2 soldier piling rigs
14/02 17/05
RW2 (SP01 to SP25) (25 nr., 3d/nr, 1 rig) 1 soldier piling rig
28/05 02/02
RW6 (28 nr., 3.3m dia., 4 rigs, 29.3 d/pile) 4 bored piling rigs
13/06 25/11
RW7 (14 nr., 2.5m dia., 1 rig, 9.9 d/pile) 1 bored piling rig
19/01A 30/06
RW9 (43 nr., 3d/nr, 1 rig) 1 soldier piling rig
25/04 27/05
RW4A (9 nr., 3d/nr, 1 rig) 1 soldier piling rig
28/05 04/08
RW8 (19 nr., 3d/nr, 1 rig) 1 soldier piling rig
28/05 25/08
RW5 (49 nr., 3d/nr, 2 rigs) 2 soldier piling rigs
02/07 14/01
RW11 (41 nr., 4d/nr, 1 rig) 1 soldier piling rig
26/07 22/12
RW3H (BP01 to BP07) (7 nr., 3m dia., 1 rig, 18d/pile) 1 bored piling rig
02/08 06/04
RW3E (20 nr., 3.3m dia., 3 rigs, 30.6 d/pile) 3 bored piling rigs
09/08 31/03
RW3G (15 nr., 3.3m dia., 2 rigs, 25.9 d/pile) 2 bored piling rigs
23/12 05/05
RW3F (12 nr., 2.5m dia., 2 rigs, 17.5 d/pile) 2 bored piling rigs
16/02 06/07
RW3H (BP08 to BP17) (10 nr., 3m dia., 2 rigs, 22.6d/pile) 2 bored piling rigs
15/06 06/09
RW3C (8 nr., 1.5m dia., 1 rig, 8.5 d/pile) 1 bored piling rig
07/07 24/08
RW3J (5 nr., 1.5m dia., 1 rig, 8.4 d/pile) 1 bored piling rig
08/07 18/08
RW3B (12 nr., 3d/nr, 1 rig) 1 soldier piling rig
12/12 11/05
RW1 (89 nr., 4d/nr, 3 rigs) 3 soldier piling rigs
28/11 24/02
RW1 (9 nr., 2m dia., 1 rig, 7.8 d/pile) 1 bored piling rig
25/04/2022
Wah Lok Path Detailed Works Programme R1A
2021 2022 2023 2024
ACTIVITY 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
06/11/2022
WLP-RW1
02/12 19/10
Stage 1A BP20>19>21>17>15>18>16
24/12 28/09
(BP10 to BP21) BP13>14>10>12>11
17/10 06/12
Stage 2A BP39>38
28/12 30/05
(BP22 to BP39) BP26>22>23>24>25
07/01 08/04
BP37>27>28
24/02 01/09
WLP-RW2 BP02>04>08>01>07>05>03>06>09
14/03 23/08
BP14>16>13>11>15>10>12
28/11 28/12
WLP-RW3 SP01>02>03>04>05
29/11 28/12
SP06>07>08>09>10
29/11 28/12
SP11>12>13>14>15
30/11 10/12
SP16>17
13/11 10/05
Bulk Excavation
received on 26/04/2022
Wah Lok Path Detailed Works Programme R2 Draft B
2021 2022 2023 2024
ACTIVITY 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
15/08 10/05
Stage 1 Stage 1- Piling Platform (BP08to BP24) Spacing < 5D
(BP08 to BP24) 02/12 14/01 18/03 29/04 05/06 05/07 08/08 11/09
26/07 22/09
(BP01 to BP07) - RC Butress Wall
23/08 29/10
- Concrete Block & Mass Filling
30/10 19/11
Stage 2B - 1.2 Piling Platform (+65.0mPD) 20/11 31/12 12/02
13/02 26/02
Stage 2B - 1.3 Piling Platform (+63.0mPD) 27/02 06/04 15/05
05/09
WLP-RW1 Stage 2A - 1.1 (+60mPD) & 1.2 (+61.5mPD) Piling Platform (BP37 to BP39)
Stage 2A 06/09 02/10 30/10 26/11
27/11 29/01
Stage 2A - 1.3 (+63.5mPD) Piling Platform (BP25 to BP36)
15/01 17/07
WLP-RW2 Stage 1B Piling Platform
23/014/04 25/0
16/05 18/06 22/07 27/08
24/02 3 4 30/05 08/07 09/08
15/06 17/07
WLP-RW3 SP01>02>03>04>05
16/06 17/07
SP06>07>08>09>10
16/06 17/07
SP11>12>13>14>15
17/06 28/06
SP16>17
17/08 20/04
Bulk Excavation
received on 07/05/2022
Relocation of Bus Kiosk and Demolition of Footbridge at Wah King Street
2022 2023 2024 2025 2026
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
02/02/2023
KLWN-RW1
Tentative
Pile Cut-off
Founding Total Length
Pile No. Level
Level (m)
(mPD)
(mPD)
BP01 92.275 47.000 45.275
BP02 92.525 47.000 45.525
BP03 92.775 47.000 45.775
BP04 93.025 47.000 46.025
BP05 93.275 47.000 46.275
BP06 93.525 47.000 46.525
BP07 93.775 47.000 46.775
BP08 94.025 47.000 47.025
BP09 94.275 47.000 47.275
BP10 94.525 47.000 47.525
BP11 94.575 47.000 47.575
BP12 94.386 47.000 47.386
BP13 94.220 47.000 47.220
BP14 94.054 47.000 47.054
BP15 93.888 47.000 46.888
BP16 93.277 47.000 46.277
BP17 92.230 47.000 45.230
BP18 91.365 47.000 44.365
BP19 90.500 47.000 43.500
BP20 89.490 55.000 34.490
BP21 88.642 55.000 33.642
BP22 87.808 55.000 32.808
BP23 86.942 55.000 31.942
BP24 85.831 55.000 30.831
BP25 84.719 55.000 29.719
BP26 83.608 55.000 28.608
BP27 82.497 55.000 27.497
BP28 81.386 55.000 26.386
BP29 79.654 55.000 24.654
1180.072