INSTALLATION OF 9G-2758 ISOLATION SWITCH

PDI’s , GENERAL WORKSHOP AND FIELD SERVICE JOBS

Wednesday, 18 May 2022


SAFETY
EMERGENCY TAKE MENTAL
ROOM EMERGENCY EMERGENCY SECUTIRY
PHONE EVACUATION & PHYSICAL
HAZARDS PREPAREDNESS PREPAREDNESS CAMERAS
NUMBERS BREAKS

• Be aware of trips • Who will call the • Who will be charge? • AED? - Automated • Who will be charge? • Stand up for 1 minute • Surveillance cameras
hazards - This is the emergency • Who will call the External Defibrillator • What is the alarm for every hour and move and recording are in
leading cause of number? emergency number? • Where is it located? your location? around use throughout the
injuries at home • Know your location • CPR? - Cardio • Who is trained to • Do you know the • Close your eyes, take facility
• Be aware of electrical • What are the Pulmonary use it? escape route? deep breaths for 60
safety numbers for your Resuscitation • Fire Extinguishers • Where is the Muster seconds
• Set up ergonomic location? • Who is trained ? • Where located? Point? • Take stretch breaks
workstation • Can you instantly • Who is trained?
dial them?

Incident Reporting (Near Miss, Unsafe Condition and Unsafe Act)


Incident: An unplanned, undesired event that adversely affects completion of a task (OSHA)
If not corrected, a condition that led to a minor incident can next time cause a serious injury
Capturing less serious safety incidents & putting corrective actions in place avoids future severe injuries
Incident Reporting & Investigation are key risk reduction tools.

Safety Triangle - Ratio between safety incidents …..(Many


Triangles exist with different ratios, the point is that there
is a ratio!)
ISOLATION SWITCH 9G-2758
PDI (PRE- DELIVERY INSPECTION) WORK ORDERS

If not already fitted


 A 9G-2758 (or 433-1540, if there is not space
to fit 9G02758) is fitted
 The cost of 9G02758 is added (booked and
issued) to the PDI job and charged as part of
the PDI to commissioning account
(CG099515)
NON-PDI WORK ORDERS (GENERAL WORKSHOP & FIELD)

If not already fitted


 The customer should be asked if he/she wishes to
purchase 9G-2758 as part of the work order
scope (this would be best asked/confirmed at the
time of the CIF-Customer Interview Form)
 Kerchanshe Serviceman fits the 9G-2758 Isolation
Switch he/she has been issued with the start of
the job.
 If the customer has agreed to purchase 9G02758
it is left on the machine and the Serviceman is
issued a replacement from stock (booked and
charged to the job)
 If the customer does not wish to purchase 9G-
2798, the Serviceman removes his own at the end
of the job and keeps it for the next job.
ADDITIONAL NOTES

In all instances, a picture of the installed isolation switch needs to be taken; during the PDI or
TA1 preceding the General Workshop or Field repair. This should be parts of the CAT inspect
report for PDI or TA1. (See photos)

For enquires, kindly contact Moges Melkamu or Andy Sarson

Moges.Melkamu@kerchansheequipment.com
asarson@unatrac.com