Professional Documents
Culture Documents
Lump Sum Contracts
Lump Sum Contracts
Lump Sum Contracts
All construction contracts address critical aspects of a project, including its scope of work,
price and payment terms, schedule and an explanation of each party’s rights and
responsibilities. However, lump sum contracts have specific criteria that can be both a benefit
and a hindrance to a construction project.
Under a lump sum contract, also known as a stipulated sum contract, the project owner
provides explicit specifications for the work, and the contractor provides a fixed price for the
project. These contracts require the owner to complete the project’s plans, designs,
specifications and schedule before the contractor can establish a price. The contractor then
estimates the costs of materials, tools, labor and indirect costs such as overhead and profit
margin and provides a quote. If the project’s final costs are lower than the contactor’s
estimate, then their profit increases. If the estimate is too low, the contractor’s bottom line
suffers. However, the project owner’s finances are unaffected in either scenario.
So, what does lump sum mean in a contract? Despite the “lump-sum” moniker, this term
refers to how the project is priced rather than the payment terms. With these contracts,
payment usually occurs on an instalment basis. This can be as project benchmarks are met or
in regular increments (e.g., monthly). To modify a lump-sum contract, project owners must
submit a change order document that the contractor must approve along with any price
changes. That makes lump-sum contracts somewhat inflexible, but they provide a reliable
price for owners and reliable revenue for contractors, making them one of the most popular
types of construction agreements.
Contractors and project owners often wonder, “what is the difference between fixed price and
lump sum contracts?” Simply put, these terms are interchangeable and are two names for the
same concept. However, there are some crucial distinctions between lump sum contracts and
other construction agreements.
Cost-plus contracts are similar to lump sum contracts in that the owner agrees to pay the
contractor’s costs, including labor, subcontractors, equipment and materials and an amount
for the contractor’s profit and overhead. But instead of a lump sum to cover all the expenses,
those costs are reimbursed individually.
These agreements do not require the project owner to have finalized plans for the project.
That means that the scope and cost are subject to change. Unlike lump-sum agreements,
owners take on more risk and will benefit or be disadvantaged if the final costs are lower or
higher than estimated as they are directly reimbursing the contractor’s expenses.
The main advantage of cost-plus contracts for both owners and contractors is that the work
likely gets done to specifications because the contractor won’t incur any extra costs for
increased materials or labor costs. However, contractors and project owners must track costs
and supervise the project carefully to ensure fair payment, requiring more burdensome
paperwork and oversight.
Time and materials (T&M) contracts stipulate that the owner provides reimbursement for
materials and a daily or weekly payment for labor costs. Like cost-plus contracts, time and
materials contracts work well with project specifications and scopes that are still ambiguous
as the project starts.
T&M contracts provide contractors with a daily or weekly rate, providing a steady income.
Project owners benefit from the adaptability of these agreements, ensuring that the work
occurs to specification. Time and materials contracts require additional paperwork compared
to lump sum contracts because labor costs must be recorded accurately.
For unit price contracts, the price is based on the estimated per-unit cost of the materials and
is divided into stages, usually by construction trade (e.g., carpentry, electric, plumbing and
more). For this reason, unit price contracts are standard in subcontracting agreements. Many
painting contracts, for example, follow a unit-price structure as painting is generally charged
on a square-foot basis.
As with cost-plus and T&M contracts, unit price contracts benefit project owners when they
have a general idea of the project that needs to be done, but the concrete planning isn’t
completed. For example, you may establish a per-square-foot price for flooring and
installation, even though you don’t know exactly how many square feet of flooring you’ll
need covered.
Because you know approximately how much materials and labor would cost, you can
establish a unit price for this and other aspects of a construction project. Contractors can get a
handle on good approximations of costs and revenue from each stage. Both owners and
contractors can adapt the project as necessary without having to submit change orders and
renegotiate prices, as they would have to do with a lump sum contract.
A notable shortcoming is that there is a significant risk of cost overrun since these contracts
usually lack a unit threshold.
A guaranteed maximum price contract (GMP), also known as a not-to-exceed price contract,
requires owners to compensate contractors for their direct costs as well as a fixed fee for
overhead and profit — but only to a certain threshold. The contractor is responsible for
additional costs once reaching this amount. The maximum price can be increased via a
change order if the project’s scope changes, but not for errors or cost overruns.
Remember, with lump sum contracts, whether or not the project actually cost the estimated
amount, the contractor gets the same amount. That is not the case with maximum price
contracts and the owner, not the contractor, will keep cost savings if things come in under
budget. In some cases, the owner can share a portion of any savings with the contractor to
encourage timely work and keep costs low.
These contracts are suitable for owners who have a tight budget as there is an absolute upper
limit. For contractors, however, GMP contracts increase their financial risk if costs exceed
the limit.
Lump sum contracts are standard in construction projects, but they aren’t suitable for every
situation. These contracts work best for projects with finalized plans, clearly defined scopes
and schedules and proper documentation of all assessments and other pre-construction
activities. These aspects are crucial to allow the contractor to estimate project costs and
provide the lump-sum amount accurately.
These agreements are best suited for simple projects with subcontractors, specific parameters
and a low risk of unforeseen problems.
When all of these elements align, lump sum contracts provide an uncomplicated agreement
that both project owners and contractors can easily understand and agree on. But what are the
advantages and disadvantages of a lump sum contract? Advantages for owners include
simplified accounting and little financial risk, and disadvantages include rigidity in project
scope and a need to have every detail planned before beginning the project. Advantages for
contractors include clear directions, less paperwork and a potential for profit if the project
comes in well under budget, and disadvantages include risk if the project is more costly than
expected.
Owner supervision of lump-sum contracts is minimal as the owner does not need to track
costs. Also, the payment structure of lump sum contracts usually comprises regular payments
at specific iterations or as a percentage of the work that has been completed, simplifying
accounts payable processes.
Another advantage of lump sum contracts is that they do not require contractors to disclose
how they calculated their materials or labor costs, allowing them to provide estimates with
sufficient cushion to avoid going over budget. If the project is under budget, the contractor
keeps the profit.
Lump sum contracts can have downsides for owners and contractors, as well.
There is also the risk of being charged a higher amount to cover the contractor costs for
unforeseen situations. Similarly, contractors could use inferior materials or otherwise cut
costs to increase their profit from the fixed price. That’s why it’s prudent for owners to
specify materials in the pre-construction documentation they provide to the contractor.
Variations are prevalent triggers of disputes in construction projects. With lump sum
contracts, any change in the plan, scope or costs is considered a variation. The most common
causes of variations include:
In either case, some variations require a formal change order request from either the owner or
the contractor. Change orders must include four key points:
Lump sum contracts are designed to reduce variations significantly, but they can still occur if
there are overlooked details or unforeseen circumstances. Ensuring that all materials are
available, the design and plan are accurate and that everyone fully understands the project can
further protect project owners and contractors from time- and money-consuming variations.
While lump sum contracts are straightforward and reduce many common constructions
contract headaches, they are not without issues that can have varying impacts on project
owners and contractors.
Delays
Delays are often consequences of unforeseen circumstances out of either party’s control, such
as weather or supply chain disruptions. Other times, a lack of clarity, failure to provide timely
instructions, inadequate labor or a lack of equipment or materials is to blame.
Lump sum contracts should include provisions that stipulate the circumstances under which
each party would be responsible for delays and the associated costs. That can reduce the risk
of contract breaches as well as the need for time-consuming and costly litigation.
Cost fluctuations
The price of labor and materials can be fluid and subject to change throughout the project.
Lump sum contracts generally do not account for these fluctuations, so contractors have to
absorb the cost if prices rise. However, they can also realize savings if rates go down. These
risks are arguably more pronounced in extended projects.
Contractors must factor in possible upward fluctuations and price the project accordingly
when providing the estimate.
Provisional sums
Although lump sum contracts are pretty iron-clad as far as scope and cost, provisional or
stipulated sums refer to the price of optional project work. The provisional sum is included as
a separate estimate within the contract and only changes if the owner decides it’s a good idea
to move forward with the elective work.
The work associated with stipulated sums can cause issues with the project schedule,
primarily if implemented later in the project. It can also lead to modifications that require
formal change orders. That’s why it’s essential that the terms of a lump sum detail how to
handle provisional sums and the limits of any related changes.
It’s essential to develop a lump sum contract correctly and fulfill it to the letter. But what is a
lump sum contract in construction? It’s one kind of construction contract where a single price
is used for an entire project. The estimated cost is developed after the contractor understands
all the details of the construction project, including specifications, materials and timelines.
Proper creation and execution of a lump sum contract for a construction project look
something like this:
A project owner needs to build a storage shed to increase inventory space, so he approaches a
contractor for the job. The owner has already completed the building design and construction
plan, performed the necessary surveys and received the required permits. In the construction
plan, the project owner also notes that he would like to use a particular cement brand. The
contractor evaluates the documentation and calculates how much the labor and materials will
cost. She takes the pricier cement that the owner requested into account and includes a buffer
amount to allow for unanticipated expenses. She then adds another amount to cover overhead
and profit to the final project estimate.
The project owner agrees to the price, and the lump sum contract:
Halfway through the project, the project owner decides to install tile flooring over the
concrete. That is outside of the original agreement’s scope, so the owner submits a formal
change order that the contractor reviews and then provides a new estimate for the project. The
project owner agrees, and work continues. Installing the tile pushes the estimated completion
date out by two weeks and increases labor costs for the contractor, but the additional amount
that was agreed to via change order protects the contractor’s profits. When the project is
complete, the contractor managed to come in under budget, providing her with additional
profits.
Cost reimbursable
Cost reimbursable, otherwise known as cost plus. Essentially, under this option the
contractor is paid actual cost for works carried out, plus an agreed fee. This type of
contract is normally used when the scope cannot be properly defined when works
start, and usually used when risk associated with the works are high and require
immediate attention. For example, emergency work.
Pros to this contract include:
· Works can start immediately with no time spent on agreeing a price beforehand
Cons to this contract include
· Risk to the client is high as the final cost is not known when the contract is initiated
· Productivity can be low, as there is often no monetary incentive for the contractor to
finish ahead of schedule
Re-measurable
Re-measurable contracts, otherwise known as measurement contracts or unit price
contract. Under this contract, payment is made against an agreed schedule of rates.
Each month a valuation of work is undertaken using the agreed schedule of rates
and site measurements.
This contract is used when the scope of works can be described in detail, but the
quantities or amount cannot. For example, under term maintenance contracts, the
maintenance work required maybe fairly repetitive and therefore easy to cost for.
However, the amount of work required is unforeseeable. This contract type may also
be appropriate when design for a project contains insufficient detail for a bill of
quantities to be produced.
Target Cost
You could say this contract is a hybrid of both lump sum and cost reimbursable.
Essentially, a contractor will be reimbursed for the actual cost on an interim basis
similarly to cost reimbursable. However, what makes target cost different, is that
financial gain and financial loss is shared between the client and contractor using a
percentage split agreed at pre-contact stage. This is calculated by taking the agreed
price and deducting the actual cost incurred, the difference is then split between
parties by the agreed percentages (sometimes this is 50/50). The agreed price may
be changed through variations during the project. Financial gain or pain is usually
calculated once works are complete and reflected in the final payment/ final account.
There is a little difference between the term remeasurement and the term
admeasurement. Remeasurement is the whole procedure of re-measuring the
completed amount of work. On the other hand, the admeasurement is the difference
between the estimated amount and the real amount.
All the above information is to help you to know about re-measurement contracts.
But I didn’t stop here; there’s more to know about the plus and negative points of
remeasurement contracts.
1. works can start after finalizing the initial design and BOQ
2. Can reduce the design cost.
3. High possibility to do value engineering
4. Prices (unit rates) will be competitive
5. Contractor’s risk is comparatively low
Below are the main differences between lump-sum contracts and remeasurement
contracts