This document is a progress report for an air conditioning project for IAcademy with a budget of 4.5 million pesos. It outlines payments received so far totaling over 1 million pesos for the down payment and progress billings. Materials and other costs total over 1.2 million pesos. The total payment so far is over 2.2 million pesos, with a remaining balance of over 2.2 million pesos. Progress is currently at 51% completion.
This document is a progress report for an air conditioning project for IAcademy with a budget of 4.5 million pesos. It outlines payments received so far totaling over 1 million pesos for the down payment and progress billings. Materials and other costs total over 1.2 million pesos. The total payment so far is over 2.2 million pesos, with a remaining balance of over 2.2 million pesos. Progress is currently at 51% completion.
This document is a progress report for an air conditioning project for IAcademy with a budget of 4.5 million pesos. It outlines payments received so far totaling over 1 million pesos for the down payment and progress billings. Materials and other costs total over 1.2 million pesos. The total payment so far is over 2.2 million pesos, with a remaining balance of over 2.2 million pesos. Progress is currently at 51% completion.
PROJECT STATUS On Going BUDGET 4,500,000.00 Down Payment and PB DP 150,000.00 13-Jan-23 PB1 500,000.00 18-Jan-23 PB2 400,000.00 27-Jan-23 PB3 PB4 PB5 Sub Total - DP & PB 1,050,000.00 Cash Advance Cash Advance 1 Cash Advance 2 Sub Total - CA - Materials and Other Deductions Materials Batch 1 955,915.55 18-Jan-23 Materials Batch 2 193,005.12 21-Jan-23 Materials Batch 3 49,692.36 27-Jan-23 Materials Jan-30-2023 6,336.20 Materials Jan-31-2023 11,500.00 Materials Feb-02-2023 31,005.00 Other Deductions Sub Total - Mats and Other Ded 1,247,454.23 Retention - Hold