Quantity Calculation for Minor Bridge

Description Nos. Unit Length Width Height Quantity Item Rate Amount Remarks

Foundation works:
PCC below GL:
Below box bridge bottom
1 Cum 11.6 16.2 0.1 18.792 10012.30 188151 Release
Raft (M-15)
Below Wing wall (M-15) 4 Cum 10.7 2.9 0.1 12.412 10012.30 124273 Hold
Amount for foundation 312424 2.91
Sub-Structure:
Raft for box bridge M-30 1 Cum 11.4 16 0.5 91.2 13008.00 1186330 Release
Wall M-30 2 Cum 16 0.5 5.35 85.6 13008.00 1113485 Release
Wall middle M-30 1 Cum 16 0.4 5.35 34.24 13008.00 445394 Release
Haunch M-30 8 Cum 16 0.225 0.3 8.64 13008.00 112389 Release
Reinforcement Steel for raft
- MT - - - 19.7712 68312.20 1350614 Release
& wall
Wing Wall (A) in M-20
Wing wall, Section-a 4 Cum 9.1 2.7 0.5 49.14 10777.9 529626 Hold
Wing wall, Section-b 4 Cum 9.1 1.6 0.5 29.12 10777.9 313852 Hold
Wing wall, Section-c 4 Cum 9.1 0.75 3.191 87.1143 10777.9 938909 Hold
Wing wall, Section-d 4 Cum 9.1 0.5 0.5 9.1 10777.9 98079 Hold
Wing wall, Section-e 4 Cum 9.1 0.55 0.05 1.001 10777.9 10789 Hold
Wing wall, Section-f 4 Cum 9 0.6 0.3 6.48 10777.9 69841 Hold
Wing Wall (B)
Section - a 4 Cum 1.4 1.81 0.5 5.068 10777.9 54622 Hold
Section - b 4 Cum 1.4 0.625 2.23 7.805 10777.9 84122 Hold
Section - c 4 Cum 1.4 0.4 0.5 1.12 10777.9 12071 Hold
Section - d 4 Cum 1.4 0.5 0.3 0.84 10777.9 9053 Hold
Amount for sub-Structure 6329176 58.92

Super Structure:
Top Slab 1 Cum 16 11.4 0.35 63.84 13008.00 830431 Release
Reinforcement steel for top
1 MT - - - 5.7456 68312.20 392495 Release
slab
Crash Barrier 2 Cum 11.4 0.4 0.9 8.208 13500.00 110808 Hold
Reinforcement steel for
1 MT - - - 0.73872 68312.20 50464 Hold
crash barrier
Railing Pillar 28 Cum 0.3 0.3 1 2.52 13008.00 32780 Hold
Railing 6 Cum 14.2 0.1 0.15 1.278 13008.00 16624 Hold
Approach slab 2 Cum 3.5 16 0.3 33.6 13008.00 437069 Hold
PCC below approach slab 2 Cum 3.5 16 0.15 16.8 10012.30 168207 Hold
Mastic asphalt & Bituminous
1 Sqm 18.4 14 - 257.6 1513 389749 Hold
concrete
Road marking 1 L/S - - - - - 10000 Hold
Amount for super structure 2438626 22.70

Protection works:
Floor appron (D/S) 1 Cum 3 13.2 0.75 29.7 5951.50 176760 Hold
Flexible appron (D/S) 1 Cum 1.5 17.7 0.3 7.965 5951.50 47404 Hold
Floor appron (U/S) 1 Cum 5 13.2 0.75 49.5 5951.50 294599 Hold
Flexible appron (U/S) 1 Cum 3 23.2 0.3 20.88 5951.50 124267 Hold
1 Cum 20.2 1.65 0.55 18.3315 10012.30 183540 Hold
1 Cum 20.2 0.75 0.75 11.3625 10012.30 113765 Hold
Curtain wall M-15 (D/S)
1 Cum 20.2 0.45 0.75 6.8175 10012.30 68259 Hold
1 Cum 20.2 0.2 0.75 3.03 10012.30 30337 Hold
1 Cum 16.2 1.5 0.8 19.44 10012.30 194639 Hold
Curtain wall M-15 (U/S) 1 Cum 16.2 0.45 0.75 5.4675 10012.30 54742 Hold
1 Cum 16.2 0.2 0.75 2.43 10012.30 24330 Hold
Below curtain wall (U/S) 1 Cum 20.4 1.5 0.15 4.59 10012.30 45956 Hold
Below curtain wall (D/S) 1 Cum 16.4 1.85 0.15 4.551 10012.30 45566 Hold
PCC Below apron (D/S) 1 Cum 8 13.1 0.15 15.72 10012.30 157393 Hold
PCC Below apron (U/S) 1 Cum 4.5 14.7 0.15 9.9225 10012.30 99347 Hold
Amount for Protection work 1660905 15.46
Total Amount 10741131
Quantity Calculation for Box Culvert
Description Nos. Unit Length Width Height Quantity Item Rate Amount Remarks

Foundation works:
PCC below GL:
Below box Culvert bottom
1 Cum 12.000 2.560 0.075 2.304 10012.30 23068
P.C.C(M-15)
Shear Key (M-15) 2 Cum 2.56 0.775 0.075 0.298 10012.30 2980
Total 2.602
Amount for foundation 26048
Sub-Structure:
Raft for box Culvert M-30 1 Cum 12.000 2.450 0.250 7.350 13008.00 95609
Wall M-30 2 Cum 12.000 0.300 2.400 17.280 13008.00 224778
Haunch M-30 4 Cum 12.000 0.355 0.150 2.556 13008.00 33248
Shear Key M-30 2 Cum 2.560 0.700 0.950 3.405 13008.00 44290
Wing wall M-30 4 Cum 2.500 0.300 1.967 5.901 13008.00 76760 36.492
Reinforcement Steel for raft &
- MT - - - 0.00 0
wall
Total 32.843 65040.00 474685
Amount for sub-Structure 474685 29.41

Super Structure:
Top Slab 1 Cum 12.00 2.45 0.25 7.35 13008.00 95609

Reinforcement steel for top slab 1 MT - - - 0.6615 0


Crash Barrier 2 Cum 2.45 0.315 0.9 1.38915 13500.00 18754
Mastic asphalt & Bituminous
1 Sqm 12.00 2.45 0 29.4 1513 44482
concrete
Road marking 1 L/S - - - - - 10000
Total 38.80065
Amount for super structure 168845

Protection works:
Floor appron Rectangular
1 Cum 10 1 0.075 0.75 5951.00 4463
Portion P.C.C(R/S) (D/S)
Floor appron Rectangular
1 Cum 10 1 0.225 2.250 5951.00 13390
Portion R.C.C (R/S) (D/S)
Floor appron Trapezoidal
1 Cum 6 3.8 0.075 1.710 5951.00 10176
Portion P.C.C (R/S) (D/S)
Floor appron Trapezoidal
1 Cum 6 3.8 0.225 5.130 5951.00 30529
Portion R.C.C (R/S) (D/S)
curtain wall P.C.C (R/S)(D/S) 1 Cum 5.2 1.85 0.075 0.722 10012.30 7224
curtain wall R.C.C (R/S)(D/S) 1 Cum 5.05 1.85 2.5 23.356 10012.30 233850
curtain wall P.C.C(L/S)(U/S) 1 Cum 5.2 1.5 0.075 0.585 10012.30 5857
curtain wall R.C.C (L/S)(U/S) 1 Cum 5.05 1.5 2 15.150 10012.30 151686
Toe Wall P.C.C (R/S) (D/S) 2 Cum 7 1.6 0.075 1.680 10012.30 16821
Toe Wall R.C.C (R/S)(D/S) 2 Cum 7 0.85 1.9 22.610 10012.30 226378
Toe Wall P.C.C(L/S) (U/S) 2 Cum 6.7 1.6 0.075 1.608 10012.30 16100
Toe Wall R.C.C(L/S) (U/S) 2 Cum 6.7 0.85 2 22.780 10012.30 228080
Total 98.331
Amount for Protection work 944554
Total Amount 1,614,132.00
Quantity Calculation for Minor Bridge
Description Nos. Unit Length Width Height Quantity Item Rate Amount Remarks

Foundation works:
PCC below GL:
Below Wing wall (M-15) 4 Cum 10.7 2.9 0.1 12.412 10012.30 124273 Hold
Amount for foundation 124,273
Sub-Structure:
Wing Wall (A) in M-20
Wing wall, Section-a 4 Cum 9.1 2.7 0.5 49.14 10777.9 529626
Wing wall, Section-b 4 Cum 9.1 1.6 0.5 29.12 10777.9 313852
Wing wall, Section-c 4 Cum 9.1 0.75 3.191 87.1143 10777.9 938909
Wing wall, Section-d 4 Cum 9.1 0.5 0.5 9.1 10777.9 98079
Wing wall, Section-e 4 Cum 9.1 0.55 0.05 1.001 10777.9 10789
Wing wall, Section-f 4 Cum 9 0.6 0.3 6.48 10777.9 69841
Wing Wall (B)
Section - a 4 Cum 1.4 1.81 0.5 5.068 10777.9 54622
Section - b 4 Cum 1.4 0.625 2.23 7.805 10777.9 84122
Section - c 4 Cum 1.4 0.4 0.5 1.12 10777.9 12071
Section - d 4 Cum 1.4 0.5 0.3 0.84 10777.9 9053
Amount for sub-Structure 2,120,965
Amount for foundation & sub-Structure 2,245,237

Super Structure:
Crash Barrier 2 Cum 11.4 0.4 0.9 8.208 13500.00 110808
Reinforcement steel for
1 MT - - - 0.73872 68312.20 50464
crash barrier
Railing Pillar 28 Cum 0.3 0.3 1 2.52 13008.00 32780
Railing 6 Cum 14.2 0.1 0.15 1.278 13008.00 16624
Approach slab 2 Cum 3.5 16 0.3 33.6 13008.00 437069
PCC below approach slab 2 Cum 3.5 16 0.15 16.8 10012.30 168207
Mastic asphalt & Bituminous
1 Sqm 18.4 14 - 257.6 1513 389749
concrete
Road marking 1 L/S - - - - - 10000
Amount for super structure 1,215,700
Total Amount 3,460,937