Professional Documents
Culture Documents
Rbi Aiche 2005
Rbi Aiche 2005
Rbi Aiche 2005
based assessments on 8
ammonia plants and downstream
urea, nitric acid and fertilizer
plants.
As owners of plant, risk management of assets is something we do as part of our day-to-day business,
regardless of whether you are the Manager, plant engineer or a maintenance technician. A RBI (risk
based inspection) approach to management of assets systematizes this thinking and doing action into
a formal, logical and auditable process.
Risk based management is as much about managing people and processes as managing assets. A
RBI program should be the starting point in setting up a management program for all critical and
non-critical equipment on ammonia and downstream plants.
Asset types found to be most at risk of failure and the damage mechanisms applicable to these were:
• Primary Reformer outlet manifolds: creep-fatigue, creep cracking in Inconel 182 welds
• Mixed Feed Coils (part of Reformer waste heat recovery section): creep damage
• Reformed Gas Waste Heat Boilers: Localised overheating of tubes, crevice corrosion
• HT Shifts, Methanators and other hydrogen equipment fabricated from C 0.5Mo steel:
H2 assisted cracking and Hydrogen damage
• Stainless steel vessels: chloride induced stress corrosion cracking beneath lagging
• Material inadequate for service How did the eight plants shape up? Table 3
• No post weld heat treatment / incorrect summarises how each plant ranked in some of
post weld heat treatment the key performance areas of manufacturing.
• Welding process not optimal Two of the plants failed to achieve a 50%
• Quality control during fabrication was score. Key shortfalls were found in the areas of:
inadequate
• Information management
• Human Resource Development (skills,
training, competence)
Where does RBI fit in the overall • Data analysis and reporting
management of pressure • Corrective actioning
equipment? What pressure • Non Conformance management
equipment management processes • Root cause analysis
are important and how did the eight
facilities shape up? Less notable shortfalls were in the areas of:
Plant Process type Age Equipment type Damage mechanism highlighted On-stream failure prevented
(yrs)
A1 Ammonia 35 Reformer outlet Creep fatigue cracking – bending moments Leaking reformed gas to atmosphere, risk of fire and
manifold tee-cone in manifold arms personnel injury; 2-3 weeks lost production
Mixed feed coil Creep - localised damage due to coil design Potential for equipment damage, 2-3 weeks lost
(reformer effluent) (hot spots) production
Reformed Gas Hydrogen damage / creep – long term Potential for tube failures, 1-2 weeks to plug failed
WHB localised overheating of tubes tubes / 6 weeks to re-tube boiler
HT Shift Converter H2 Assisted Cracking – Post weld heat Leaking process gas to atmosphere, risk of fire and
treatment soak temperature too low, HAZ personnel injury; 2-3 weeks lost production
too hard
263
Mixed Feed Stress corrosion cracking of expansion Leaking process gas to atmosphere, risk of fire and
Preheater bellows – low level chlorides in steam personnel injury; 2-3 weeks lost production
Sulfinol Cooler Microbial Induced Corrosion – cooling Tube failure; 2-3 days to plug failed tubes / 6 weeks to
water velocities too low re-tube exchanger.
Methanator H2 Assisted Cracking – PWHT soak Leaking process gas to atmosphere, risk of fire and
temperature too low, HAZ too hard personnel injury; 2-3 weeks lost production
Ammonia H2 Assisted Thermal Fatigue Cracking – Leaking process gas to atmosphere, risk of fire,
Converters S/up procedure and material properties explosion and personnel injury; >3 weeks lost
production
A2 Urea 35 Urea Reactor Localised corrosion of liner – operational Corrosion damage to shell; plant off line for 2-3
problems with purge water weeks to repair.
264
WHB localised overheating of tubes tubes / 6 weeks to re-tube boiler
Purge Gas Potential for brittle fracture during low Potential for catastrophic failure of pressure vessel,
Separator temperature/re-pressure excursion severe property damage, high personnel safety and
environment risk.
Auxiliary Boiler Creep - localised damage due to coil design Potential for equipment damage, 2-3 weeks lost
(hot spots) production
Methanator Hydrogen damage of C 0.5Mo steel Potential for catastrophic failure of pressure vessel,
operating above CS Nelson Curve. severe property damage, high personnel safety and
environment risk.
2005
2005
Plant Process type Age Equipment type Damage mechanism highlighted On-stream failure prevented
(yrs)
NH3 Converter Hydrogen damage of C 0.5Mo steel Potential for catastrophic failure of pressure vessel,
Effluent Exch. operating above CS Nelson Curve. severe property damage, high personnel safety and
environment risk.
NH3 Converter Hydrogen damage of C 0.5Mo steel Potential for catastrophic failure of pressure system,
Effluent piping operating above CS Nelson Curve. severe property damage, high personnel safety and
environment risk.
CO2 Stripper Gas Chloride induced stress corrosion cracking Leaking process gas to atmosphere, risk of fire and
Re-boiler beneath lagging personnel injury; 2-3 weeks lost production
Shift Effluent BFW Chloride induced stress corrosion cracking Leaking process gas to atmosphere, risk of fire and
Heater beneath lagging personnel injury; 2-3 weeks lost production
265
Transition section – Potential for hydrogen damage due to on- Potential for catastrophic failure of pressure system,
Sec Reformer going refractory problems severe property damage, high personnel safety and
environment risk.
Steam Drum Thermal fatigue cracking due to fast start-up Leaking HP steam to atmosphere; >3 weeks lost
procedure (heavy wall drum) production, potential for personnel injury
B2 Nitric Acid 35 Cooler Condenser Localised corrosion from poor cooling Tube failure; 2-3 days to plug failed tubes / 10 weeks
water treatment (scaling leading to high to re-tube exchanger.
tube wall temperatures).
Waste Heat Boiler Tubes at end of life due to prolonged Tube failure; 2-3 days to plug failed tubes / 6 weeks to
operation 450 embrittlement range. re-tube boiler.
266
environment risk.
Reformed Gas Localised corrosion of tubes in tube to Tube failure; 1 week to plug failed tubes / 4 weeks to
WHB tubesheet crevice re-tube boiler.
Reformed Gas Hydrogen damage / creep – long term Potential for tube failures, 1-2 weeks to plug failed
WHB localised overheating of tubes tubes / 6 weeks to re-tube boiler
Sec Process Steam Coils approaching end of creep life Potential for equipment damage, 2-3 weeks lost
S/H production
Knock-out Pot Localised pitting from carbonic acid attack Perforation of shell, process gas to atmosphere; 1
in high impingement areas week lost production to repair, potential fire risk
2005
2005
Plant Process type Age Equipment type Damage mechanism highlighted On-stream failure prevented
(yrs)
Syn Loop Piping HTHA of C 0.5Mo steel operating above Potential for catastrophic failure of pressure system,
CS Nelson Curve. severe property damage, high personnel safety and
environment risk.
E Ammonia 20 Reformer Outlet Localised creep fatigue damage due to Leaking reformed gas to atmosphere, risk of fire and
Manifold manifold sag. personnel injury; 2-3 weeks lost production
Ref Product / Feed Hydrogen embrittlement of Inconel 600 Leaking reformed gas to atmosphere, risk of fire and
Gas Exch bellows. personnel injury; 2-3 weeks lost production
F Ammonia 2 Syn Loop BFW Hydrogen assisted cracking of channel to Leaking reformed gas to atmosphere, risk of fire and
Pre-heater tubesheet weld (PWHT inadequate) personnel injury; 2-3 weeks lost production
Syn Loop WHB Risk of tube to tubesheet weld cracking – Tube failure; 2 weeks to repair/plug cracked welds / 6
267
weld procedure inadequate weeks to re-tube boiler.
Reformed Gas Hydrogen damage / creep – long term Potential for tube failures, 1-2 weeks to plug failed
WHB localised overheating of tubes tubes / 6 weeks to re-tube boiler
Sec Reformer Creep fatigue cracking at dissimilar metal Burner failure; plant off line for 1-2 weeks to repair
Burner weld existing / install new burner
Purge Gas Potential for brittle fracture during low Potential for catastrophic failure of pressure vessel,
Separator temperature/re-pressure excursion severe property damage, high personnel safety and
environment risk.
Separator Vessel Localised pitting corrosion from carbonic Potential for perforation of pressure containing shell
acid attack of carbon steel vessel leading to plant shutdown to repair
268
temperature/re-pressure excursion severe property damage, high personnel safety and
environment risk.
H1 Ammonia 2 Reformer Creep fatigue cracking of outlet manifold Leaking reformed gas to atmosphere, risk of fire and
tee to cone weld personnel injury; 2-3 weeks lost production
Reformed Gas Hydrogen damage / creep – long term Potential for tube failures, 1-2 weeks to plug failed
WHB localised overheating of tubes tubes / 6 weeks to re-tube boiler
Reformed Gas H2 assisted cracking of inlet nozzle to Leaking reformed gas to atmosphere, risk of fire and
WHB channel weld; inadequate post weld heat personnel injury; 2-3 weeks lost production
treatment
Syn Loop Microbial Induced Corrosion – cooling Tube failure; 2-3 days to plug failed tubes / 4 weeks to
Intercoolers water velocities too low re-tube exchanger.
2005
2005
Plant Process type Age Equipment type Damage mechanism highlighted On-stream failure prevented
(yrs)
MP Flash Drum Potential for brittle fracture during low Potential for catastrophic failure of pressure vessel,
temperature/re-pressure excursion severe property damage, high personnel safety and
environment risk.
H2 Nitric Acid 2 Cooler Condenser Stress corrosion cracking of stainless steel Plant off line for 5-7 days to repair.
inlet nozzle in cooling water jacket
Economiser Potential for localised pitting corrosion - Tube failure; 2-3 days to plug failed tubes / 6 weeks to
condensing droplets of nitric acid re-tube exchanger.
H3 Ammonium 2 Pipe Reactor Localised corrosion (3mm/yr); material Plant off line for 1-2 days, potential for personnel
Nitrate Separator inadequate for duty injury.
269
AMMONIA TECHNICAL MANUAL
Table 2: Reliability management of production facilities through the application of critical manufacturing processes.
270
process and plant CM task frequency RBI (RMS) RCM RCM RCM
Data Analysis and Reporting RBI (RMS) CMMS (SAP) CMMS (SAP) CMMS (SAP)
Corrective actioning RBI (RMS) CMMS (SAP) CMMS (SAP) CMMS (SAP)
Non Conformance Mgt RBI (RMS) CMMS (SAP) CMMS (SAP) CMMS (SAP)
Remnant Life Quantitative risk assessment RBI (RMS) RCM N/A N/A
management Critical defect size analysis Fracture Mech. Fracture Mech. N/A N/A
Remaining Life Assess FM/life model FM/life model N/A N/A
Life Cycle Planning CMMS (SAP) CMMS (SAP) CMMS (SAP) CMMS (SAP)
Production and Process Process management (production / Process Mgt PMS PMS N/A
Control efficiency) System (PMS)
Information management PMS PMS PMS N/A
Critical Alarm/Trip Systems PMS PMS PMS N/A
Process Procedures PMS PMS PMS N/A
Abnormal Condition Mgt PMS PMS PMS N/A
Human Resource Development HR Plan HR Plan HR Plan HR Plan
Engineering and Process Engineering standards Codes of practice Codes of practice Codes of practice Codes of practice
Design Engineering specifications Process design OEM specs OEM specs Man. Spec.
2005
2005
Primary Process Key Performance Areas Asset Group
Static Plant Rotating Plant Inst / Elect. Infrastructure
Root Cause Analysis of RCA lost production PMS PMS PMS N/A
lost production and
failure RCA lost efficiency PMS PMS PMS N/A
RCA equipment failure RCA / FMEA RCA / FMEA RCA / FMEA RCA / FMEA
Shutdown / Turnaround Work scoping RBI (RMS) CMMS (SAP) CMMS (SAP) CMMS (SAP)
management Planning and Scheduling Planning system Planning system Planning system Planning system
Project Mgt Project Mgt Project Mgt Project Mgt Project Mgt
271
AMMONIA TECHNICAL MANUAL
Table 3: Summary of findings of an audit completed on the eight ammonia facilities based on ‘best practice management of pressure equipment’.
Primary Process Key Performance Areas Plant ID / Static Plant Management Rating
A B C D E F G H Your facility
Maintenance Planning and Scheduling 9 7 5 5 7 9 8 8
Systems and Information Management 5 7 3 3 8 8 8 8
Practices Maint Methods – PMs, PDM, Proactive 8 8 5 7 8 8 9 8
Maintenance procedures 6 6 6 6 6 6 6 6
Maintenance standards 6 6 6 6 6 8 8 8
Spares / Materials Mgt 6 6 6 6 6 8 8 8
272
Non Conformance Mgt 2 5 2 2 7 7 7 7
Remnant Life Critical defect size analysis 9 9 6 3 5 9 9 9
management Remaining Life Assess 9 9 4 3 5 9 9 9
Life Cycle Planning 7 7 4 3 7 7 7 8
Eng / Process Engineering standards 7 7 7 8 8 8 8 8
Design Engineering specifications 7 8 7 8 8 8 8 8
RCA of lost RCA lost production 7 7 4 4 7 7 7 7
production and RCA lost efficiency 7 7 4 4 7 7 7 7
failure RCA equipment failure 6 6 5 5 6 6 6 6
Shutdown / Work scoping 9 9 5 7 8 9 8 9
Turnaround Planning and Scheduling 9 9 6 7 8 9 8 9
management Project Mgt 8 9 7 7 8 9 8 9
Totals Max possible score = 270 187 187 126 128 195 205 209 212
2005
2005
Definitions:
RE = Risk exposure
LoF = Likelihood of failure
CoF = Consequence of failure
RBI = Risk based inspection
RMS = Reliability management system
RCM = Reliability centred maintenance
RCA = Root cause analysis
PMS = Process management system
CMMS = computerised maintenance system
SAP = a brand of CMMS
FMEA = Failure modes and effects analysis
273
AMMONIA TECHNICAL MANUAL