Professional Documents
Culture Documents
FM II Assignment 2 Solution W22
FM II Assignment 2 Solution W22
Financial Management II
The Basics of Capital Budgeting
Chapter 11
Assignment 2 Solution
Examples
Q1) a. Project X: CF0 = -10,000, CF1 = 6,500, CF2 = 3,000, CF3 = 3,000, CF4 = 1,000,
NPV = $966.012. IRR = 18.03%
Project Y: CF0 = -10,000, CF1 = 3,500, CF2 = 3,500, CF3 = 3,500, CF4 = 3,500,
NPV = $630.72. IRR = 14.96%
MIRR:
Project X:
WACC = 12%
CF1 = 6,500, CF2 = 3,000, CF3 = 3,000, CF4 = 1,000, Terminal Value (future value of CFs at end of year 4) =
$17,255.232
Project Y:
CF1 = 3,500, CF2 = 3,500, CF3 = 3,500, CF4 = 3,500, Terminal Value (future value of CFs at end of year 4) =
$16,727.648
Payback Period:
Project X:
b. All methods rank Project X over Project Y. In addition, both projects are acceptable under the NPV, IRR, and
MIRR criteria. Thus, both projects should be accepted if they are independent.
c. When the projects are mutually exclusive, we would choose the project with the higher NPV i.e. Project X.
d. Calculating incremental cash flows: CF0 = 0, CF1 = 3000, CF2 = -500, CF3 = -500, CF4 = -2500,
Crossover rate = IRR of incremental cash flows = 6.21%
Q2) The IRR is the discount rate at which the NPV of a project equals zero. Since we know the project’s initial
investment, its IRR, the length of time that the cash flows occur, and that each cash flow is the same, then we can
determine the project’s cash flows by setting it up as a 10-year annuity.
Project’s MIRR:
Terminal Value = FV of inflows:
N = 10, I = 10, PV = 0, and PMT = -176.98. FV = $2,820.61.
N = 10, PV = -1000, PMT = 0, and FV = 2820.61, I = MIRR = 10.93%.
Q3) Since the IRR is the discount rate at which the NPV of a project equals zero, the project’s inflows can be
evaluated at the IRR and the present value of these inflows must equal the initial investment.
Therefore, the initial investment for this project is $65,002.11. Using a calculator, the project's NPV at the
firm’s WACC can now be solved.
Project B:
CF0 = -20, CF1 = 10, CF2 = 9, CF3 = 6,
At a WACC = 15%, both NPVs are less than zero, so neither project would be chosen.
d. MIRR:
Project A:
WACC = 10%
CF1 = 5, CF2 = 10, CF3 = 17, Terminal Value (future value of CFs at end of year 3) = $34.05
Project B:
CF1 = 10, CF2 = 9, CF3 = 6, Terminal Value (future value of CFs at end of year 3) = $28
Q2)
a. Payback A (cash flows in thousands):
Annual
Period Cash Flows Cumulative
0 ($25,000) ($25,000)
1 5,000 (20,000)
2 10,000 (10,000)
3 15,000 5,000
4 20,000 25,000
At a discount rate of 5%, Project A has the higher NPV; consequently, it should be accepted.
At a discount rate of 15%, Project B has the higher NPV; consequently, it should be accepted.
f. ∆CF =
Year CFA – CFB
0 $ 0
1 (15)
2 0
3 7
4 14
g. MIRRA:
Terminal Value = Total FV of CFs
CF0 = 0; CF1 = 5000; CF2 = 10000; CF3 = 15000; CF4 = 20000; I = 10%, Total FV = $55,255
PV of cost = -$25,000
MIRRB:
Terminal Value = Total FV of CFs
CF0 = 0; CF1 = 20000; CF2 = 10000; CF3 = 8000; CF4 = 6000; I = 10%, Total FV = $53,520
PV of cost = -$25,000
According to the MIRR approach, if the 2 projects were mutually exclusive, Project A would be
chosen because it has the higher MIRR. This is consistent with the NPV approach.
Now, PV = -$1,000, FV = $1,636.368, N = 4, solve for I = MIRR = 13.10%