Professional Documents
Culture Documents
Tender Doc NJPC
Tender Doc NJPC
DGM,
Procurement & Contract Deptt.
NJHPS, SJVN LTD., Jhakri-172201.
For wider publicity and awareness among the bidders, it is intimated that all open tenders having estimated cost more
than 25.0 lacs only are published in the print media. For regular updates on all other open tenders having estimated
cost below 25.0 lacs, please visit websites www.sjvn.nic.in or www.tenders.gov.in & www.eprocure.gov.in.
Registered & SJVN Corporate office complex, Shanan Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh, Pin No.-171006. ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
INSTRUCTIONS TO BIDDERS (ITB)
The bids are invited using e-procurement mode, so please read the instructions carefully and
upload the filled in bids as per requirement of bid documents. The acknowledgement copy is
to be sent as a proof for the bid submission through tendering.
1.2 SJVN Ltd. has issued an invitation to bid as enclosed and will receive bids as set forth in the
accompanying Bid documents.
1.3 Bids cannot be uploaded after the time & date fixed for receipt of bids as set out in the
Invitation of Bid.
1.4 SJVN Ltd. reserves the right to accept or reject any or all Bids without assigning any reason
for such a decision.
1.5 All the cost and expenses incidental to preparation of the proposals, discussions and
conferences, if any, including pre-award discussions with the Bidder, technical and other
presentation including any demonstrations etc. shall be to the account of the Bidder and
Owner shall bear no liability whatsoever on such costs and expenses.
1.6 The last date of availability /downloading of the bid document are 31.05.2018 at 12:00 hrs.
The complete filled in bids and necessary scanned documents shall be uploaded at the
mentioned address up to 20.06.2018 at 13:00 hrs. The techno-commercial bid shall be
opened on 20.06.2018 at 14:00 hrs. The bids cannot be uploaded / submitted later than
20.06.2018 at 13:00 hrs. However, Price bid part of qualified & commercial responsive
bidders shall be opened on subsequent date, for which the qualified bidders shall be
informed separately.
1.7 Please note that bids in physical form shall not be entertained under any
circumstances and are only to be submitted through e-tendering at
https://sjvn.abcprocure.com.
1.8 DIGITAL SIGNATURES: The bidder should also have the Digital Signatures (Class II or
higher with signing & encryption both) which are mandatory for security purpose. The
digital signatures can be obtained from any of the authorized agencies in India as per IT
Act.2000. Valid Digital Certificate must be installed in a computer system from where you
want to login on website. Perform the below steps to confirm whether valid digital
certificate is available on your computer system or not.
Steps:
Open Internet Explorer.
Select Tools menu from menu bar. OR (Press Alt + T on your keyboard).
Click on Internet Options >>Content >>Certificate button.
The bidder should view your digital certificate under “Personal” heading
Requirement of Digital Signature Certificate
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
Please enable ActiveX Controls & Plug-ins. (Tools->Internet Options-> Security-
>Custom Level)
1. https://sjvn.abcprocure.com
&
2. https://www.tpsl-india.in
Tools menu of Internet explorer - Internet Options – Security – Click on Internet Icon.
After Click on Custom Level button –
From below ActiveX controls and plug-ins ---- Select below 5 Items to be enabled
1) Download signed ActiveX controls –select Prompt or Enable
2) Download unsigned ActiveX controls – select Prompt or Enable
3) Initialize and script ActiveX controls not marked as safe for scripting – select Prompt or
Enable
4) Run ActiveX controls and plug-ins-select Enable
5) Script ActiveX controls marked safe for scripting – select Enable
After completed this above selection----Below option has available---Reset custom
settings---Reset To: Select low or medium ---Click on OK.
Also, please check your system Date & Time it should be set as current date & time.
In case of Digital Certificate based Login, user need to download & install "Signer" file
available under Download Section at https://sjvn.abcprocure.com.
Download & Install "Intermediary Certificate" available under Download Section at
https://sjvn.abcprocure.com.
Please disable or uninstall Third Party Toolbar / Add-ons from Browser.
1.9 The contract & procurement process through e-tendering/e-procurement system is in process
at NJHPS, SJVN Jhakri and hence this tender is to be processed through e-tendering/e-
procurement system. The bids are to be filled and submitted online. To participate in e-
tendering/e-procurement, it is requested to register with our website
https//:sjvn.abcprocure.com. The one year cost of registration on web site is Rs. 3068/- (Rs
2600/- plus GST@ 18%) is payable directly to M/s e-Procurement Technologies Ltd. The
bidder should also have the Digital Signatures for security purpose. The detailed procedure
for the registration is as under:-
a. Go to the url: - https://sjvn.abcprocure.com In the home page click on vender
Registration.
b. Click on “New Bidder’s Registration” link available on home page.
c. You need to furnish individual details as well as of company details in registration
form.
d. After filling all mandatory fields, you need to click on “submit” button to complete
the registration process.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
e. After submission of the form, the user id and password are generated in the form of
Acknowledgement.
f. The payment of annual registration fee amounting to Rs. 3068/- is to be made
through DD/ Online through Net Banking/ Credit card/ debit card etc.
g. The User ID will be activated after DD/RTGS/NEFT/Net Banking/ Credit Card is
received or realization of payment online. Send the Acknowledgement copy and
uploaded document below mentioned e-Mail ID.
For Registration enquiry and to activate User ID please call abcprocure Help Desk
Centre +91-79-4027-0555| 0507 | 0564 | 0563 | 0548, Cell: +91-93274519729, E-
Mail ID support@abcprocure.com and info@abcprocure.com.
1.10 All the bidders are requested to get themselves registered well in advance to facilitate timely
submission of the bid. In case bidders wait till last moment for uploading the bids and if any
technical problem is encountered at that time, the bid closing date & time may elapse.
1.11 Down loading Bid Documents: Bidder to access e-Tender portal of SJVN
(http://sjvn.abcprocure.com) to access NIT document, after completing registration
formality and successful login vendor need to process for Tender Fee / Document Fee (if
any) and after that bidder can download detailed tender document.
“Download Document” link is available at the end of every tender notice along with access
to “Corrigendum”.
1.12 Bid Submission:
(i) Bidder needs to login first on the tendering portal of SJVN (i.e.
https://sjvn.abcprocure.com).
(ii) Search tender by filling necessary searching criteria after Login.
(iii) After finding the tender on the screen, click on the “Dashboard”.
(iv) Click on “Declaration” and then click on “I Agree”.
(v) Click on the “Tender Fees” (if any) & Pay the tender fees Online.
(vi) Click on the “EMD” & Pay the EMD online.
(vii) Click on “Prepare Bid” and fill necessary Forms (Schedules).
(viii) After filling Price Bid Form click on “Final Encrypt”.
(ix) After filling all Forms & final Encryption of Price Bid click on “Final Submission”.
(x) After Final Submission bidder will get receipt of Final Submission of their Bid.
1.13 The link “help manual” and “vendor help” for submission of bids is also available on the
website. For any assistance/ clarification for e–tendering registration, submission of bid
through e-tendering/ procurement , bidder may contact the following persons/
representatives of M/s abcProcure:-
(i) Mr. Chanderkant-M- 09459242421, e-Mail: Jhakri@eptl.in
(ii) Mr. Raman Kumar-M- 08449744125, e-Mail: dehradun.sjvn@eptl.in
(iii) Mr. Amit Thakur-M- 09265562822, e-Mail: amit.singh@eptl.in
(iv) Mr. Rahul Dixit -Ph- 07940270555, e-Mail: rahul.dixit@eptl.in
(v) Mr. Pankesh Kumar-Ph- 07940270507, e-Mail: pankesh@eptl.in
(vi) Mr. Pradip Parmar-Ph-07940270564 e-Mail: pradip@eptl.in
(vii) Link”Contact us” available on the home page of https://sjvn.abcprocure.com
The above persons are to be contacted for help/ assistance related to e–tendering
registration, submission of bid through e-tendering only.
For any other clarifications regarding the tender bidder may contact the following
persons/ representatives of M/s SJVN:-
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
(i) Ms. Neha Purohit: Mobile No. 08894262507 (E-mail ID: neha.purohit@sjvn.nic.in)
(ii) Sh. Ajay Kumar: Mobile No. 09418014928 (E-mail ID : aj.kumar@sjvn.nic.in)
(iii) Sh. Rajesh Negi: Mobile No. 08894725811 (Email ID: rajeshkr.negi@sjvn.nic.in)
The rail head (broad gauge) is at Kalka (NR). Kalka is about 235 Km (Approx.) from
Jhakri.
Approximate
Distance from To To To
Kalka Mumbai Kolkata Chennai
(i) By Rail 1906 1809 2558
(ii) By Road 1753 1791 2482
The distance from Kalka to Delhi by road is 285 Km (approx.).
From the Kalka rail head, the Project is approachable by the following roads/routes:-
Transport Limitation
The transport limitation by road from Kalka to the Plant Site at Jhakri would be the
governing factor in respect of the permissible package size and weight. Bidder should
consider all factors as can be envisaged for transportation of equipment to avoid and
overcome the hindrances/ limitations on existing road on account of weather
conditions and any other reasons without affecting the schedule .
4.0 Minimum Qualifying Requirement: As per PQR enclosed.
5.1 Scope of work covers Annual Plant Maintenance for year 2018-19 & 2019-2020 of 6 x 250
MW NJHPS, Jhakri.
5.2 The details of the work shall be as elaborated in the BOQ/ Scope of work.
5.4 The list of T&P and consumables to be provided/ arranged by the contractor is provided
along with the scope of work.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
5.5 The bidder is advised to visit and examine the site of the work and its surroundings and
obtain for himself, on his own responsibility all information that may be necessary for
preparing the bid and entering in to contract. The cost of visiting the site shall be at bidder’s
own expenses.
6.0 Quality Assurance Programme: The quality assurance program will be as per relevant
manuals available with SJVN and as per direction of EIC.
8.0 The Bidder is expected to examine all instruction, forms, terms, specifications, and other
information in the bidding documents. Failure to furnish all information required by the
bidding documents or submission of a bid not substantially responsive to the bidding
documents in every respect will be at the Bidder's risk and may result in rejection of its bid.
9.2 The amendment will be notified in writing or by cable or through website (on
www.sjvn.nic.in, www.eprocure.gov.in and https://sjvn.abcprocure.com) to all prospective
Bidders that have received the bidding documents and will be binding on them. Bidders are
required to immediately acknowledge receipt of any such amendment, and it will be
assumed that the information contained therein has been taken into account by the Bidder in
its bid.
9.3 In order to afford prospective Bidders reasonable time in which to take the amendment into
account in preparing their bid, the Owner may, at its discretion, extend the deadline for the
submission of bids.
9.4 After publishing of NIT in Newspaper, any amendment/ corrigendum related to extension of
due date & qualifying requirements shall be published in Newspapers. The amendment(s) of
the NIT shall also be put on our web-sites directly. The bidders who have not informed us
about the download would be required to regularly visit our website for updating themselves
about any amendments which may arise from time to time. It will be assumed that all the
information contained/updated in the website has been taken into account by the Bidder in
its bid.
11.0 Cost of Bid Document and Earnest Money deposit {EMD/ Bid Security (FDR/TDR)}
(ONLINE).
11.1 The cost for purchase of bid document is ₹ 5000/- + GST@18% = Rs. 5900/- (Rs. Five
Thousand Nine Hundred Only) (Non Refundable).
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
11.2 The bidder shall furnish, bid security/earnest money as part of bid amounting to ₹ 7,18,000/-
(Rupees Seven Lac Eighteen Thousands Only).
11.3 Micro or Small Enterprises (MSE)/NSIC/ Startup India registered firms are exempted from
the submission of the “Tender document cost” and “EMD” and must enclose (Upload
scanned copy of the MSE/ NSIC/ Startup India certificate) for the same products as in NIQ
above. If the MSE/ NSIC/ Startup India certificate does not contain the
item(s)/work(s/Services) as listed in our NIQ/NIT and no EMD is found submitted, then
SJVN may ask the bidder to submit the EMD and the same should reach within ten (10)
days from the date of SJVN’s notification by E-mail/ Fax Letter, otherwise the bid shall
be considered as non-responsive and price bid of such firms shall not be opened.
11.4 The “Cost of Bid Document and Earnest Money (EMD)” shall be submitted using below
mentioned facilities:-
a) Credit Card
b) Debit Card
c) Net Banking
d) NEFT/RTGS
► NEFT/RTGS:
To make payment through NEFT/RTGS, bidders will get an auto generated e-Mail which
contains details of their Unique Bidder Code and when and how to do RTGS/NEFT and
details pertaining to it. This information will also be available on screen under heading of
“NEFT/RTGS Instruction” once bidder gets login.
Once bidder deposit amount in Beneficiary account number provided to them, while
making payment for document fees and EMD by RTGS/NEFT payment option at the
document fees and EMD payment screen, bidder shall be able to view the funds already
remitted by him/her through NEFT /RTGS as available. Please proceed to make the
payment. Upon doing so, the required amount to be paid through the document fees and
EMD, shall get appropriately deducted from the available balance and payment shall be
confirmed in real time.
This facility allows you to transfer lump sum amount to your Bidder ID account number
as mentioned above via RTGS / NEFT. Bidder would be able to use the funds as and
when require till the time balance is available in Bidder ID. Also, Bidder can transfer
more amount as and when he/she require. Kindly note that the payment via RTGS /
NEFT is required to be made one working day in advance in order to make it available in
your Bidder ID. Hence please ensure that Bidder remit funds at least one day in advance
before he/she would like to make the document fees and EMD payment through RTGS /
NEFT option on payment gateway.
Caution: Please ensure that you need to mention the correct beneficiary account number
and IFSC code as mentioned above while making payment via RTGS / NEFT. In the
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
event of funds remitted to wrong beneficiary account number, SJVN Limited or its Bank
or its service provider would not responsible for the same.
The EMD submitted in the form of BG, DDs, local Cheque/ outstations Cheque will
not be considered.
11.5 FDR/TDR:
Please note that EMD (Earnest Money Deposit) / Bid Security in the form of
FDR/TDR {Pledged in favour of the NJHPS, SJVN Ltd. Jhakri} is also
acceptable and the same in original/physical form should reach preferably on or
before bid closing date on the following address:
DGM
(Procurement &Contact Deptt.),
NJHPS, SJVN Limited, Jhakri (H.P.)-172201.
If EMD in the form of FDR/TDR does not reach in physical form within seven (07)
days after the bid closing date, the bid(s) shall not be entertained and such bid(s)
shall be treated as late bid(s)/non-responsive bid(s).
11.6 The bid securities of unsuccessful bidders will be returned as promptly as possible, but not
later than twenty-eight (28) days after the expiration of the bid validity period.
11.7 The bid security of the successful bidder will be returned when the bidder has furnished the
required performance security.
11.8 No interest shall be payable by the Owner on the above Bid security.
(c) if the Bidder does not withdraw any deviations listed in Deviation Schedule at the
cost of withdrawal indicated by him;
(d) if the Bidder refuses to withdraw, without any cost to the Owner, any deviation not
listed in Deviation Schedule but found elsewhere in the bid; or
(e) in the case of a successful Bidder, if the Bidder fails within the specified time limit;
(i) To accept the Letter of Award or
(ii) To furnish the required performance security.
(iii) To start activities according to Work Completion Schedule.
12.0 Deviations
Deviations, if any, from the terms and conditions of Bidding Documents or Technical Specifications
including drawings shall be listed only in Deviation Schedule of the bid i.e. Online “Schedule of
Deviations”. The Bidder shall also provide the additional price, if any, for withdrawal of the
deviations.
Bidder may further note that except for deviations listed in Deviation Schedule, the bid shall be
deemed to comply with all the requirement in the bidding documents and the bidders shall be
required to comply with all such requirements of bidding documents and technical specifications and
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
drawings without any extra cost to the Owner irrespective of any mention to the contrary, anywhere
else in the bid, failing which the bid security of the Bidder may be forfeited.
The owner has complete right to evaluate the deviations without prejudice. After evaluation, the
deviations may or may not be agreed by the owner. The bidder shall be intimated in writing
accordingly.
Sr. Period in
Description of work
No. Machine Days
Normal Maintenance
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
1 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 1st Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
2 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 2nd Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
3 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 3rd Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
4 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 4th Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
5 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 5th Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
6 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 6th Unit as per BOQ/ Scope of work.
60
7 Total No. of Days for all six units. (Machine days)
Note:
i) The maximum work completion period for each unit shall be machine days as
above. Next unit work shall be undertaken after completion of work of
first/previous unit and as on date as desired by EIC. EIC may also ask for
parallel work in two units for which nothing extra is payable.
ii) Ventilation work and maintenance of GIS & Protection system shall be
carried out parallel with other works or separately as decided by EIC.
Special Maintenance
8 Annual Overhauling of MIV Maintenance Seal (Per Seal) 07 days
Note:
i) This shall be carried out under Special maintenance of MIV Maintenance
Seal, maintenance of MIV service seal if required shall be a parallel activity.
The Maximum Work Completion Period will be 60 Machine Days for all the units.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
The maximum completion schedule for MIV Maintenance seal (special
maintenance, if any) shall not be more than 7 days in any case. Other parallel
activities could also be performed with this activity as decided by EIC.
Bidder should programme the work activity with three shift working, seven (7)
days a week including holidays with working on a single unit or on two units in
parallel.
The zero date for first unit will start from the date of handing over of the first unit
by the EIC to contractor. The zero date for next machine will start from date of
handing over of next unit. There may be some gap between work completion of
previous unit and start of next unit as per situation and availability of water. For
such gaps nothing extra shall be payable.
In case of delay due to non- availability of material, the same will be to SJVN
account and equal no. of days will be added in machine days for which material is
not available to achieve new normal schedule for work completion. Except change
in completion schedule no other compensation shall be payable on account of this.
The L.D. clause will be applicable considering new/ revised completion period for
unit under consideration at that time.
Bidders offering completion schedule of more than machine days as specified for
each unit and more than 60 machine days for all the six units per year shall not be
considered for evaluation.
Where
P1 = Price for second year contract for any sub activity.
P0 = Price for first year contract for that sub activity.
L1 = All India monthly Consumer Price Index for Industrial worker for the month
previous to month in which the work is carried out as published by Labour
Bureau (Govt. of India).
L0 = All India monthly Consumer Price Index for Industrial worker for the month in
which the bid is submitted as published by Labour Bureau (Govt. of India).
The ceiling of price variation as above for second year is +15%. There will be no ceiling on
negative side.
► Bidders are required to quote the price for the commercial, contractual and technical
obligations outlined in the bidding documents.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
► Bidders shall give the required details and breakup of their prices as per Schedules
specified.
► The Prices quoted by the Bidder shall be FIRM during the performance of the contract
for 1st year (2018-19) and not subject to variation on any account. A bid submitted with
an adjustable price quotation will be treated as non-responsive and rejected. However
for 2nd year, the prices shall be variable as per above price variation formula.
► In exceptional circumstances, the Owner may solicit the Bidder's consent to an extension
of the bid validity period. The request and responses thereto shall be made in writing or
by cable/fax. If a Bidder accepts to prolong the period of validity, the bid security shall
also be suitably extended. A Bidder may refuse the request without forfeiting its bid
security. A Bidder granting the request will not be required nor permitted to modify its
bid.
► The Bid must contain the name, residence and place of business of the person or persons
making the Bid and must be digitally signed. The name of all persons signing should
also be mentioned at appropriate place.
► Bid by Corporation / Company must be digitally signed with the legal name of the
Corporation / Company by the President, Managing Director, or by the Secretary or
other person or persons authorized to bid on behalf of such Corporation / Company in
the matter.
► Bidder's name stated on the proposal shall be the exact legal name of the firm.
► All the requisite documents shall be scanned & uploaded along with bid at
https://sjvn.abcprocure.com. The hard copy of the documents shall also be posted as per
details given in clause 32.0 so as to reach on or before the last date and time of
submission of bid.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
► If situation so warrants, SJVN Ltd./NJHPS may ask the bidders to produce original
documents which were submitted as scanned copies along with bid for verification.
The bids will be submitted electronically at designated places in various schedules. The bid
document except schedules-1, schedule-2, schedule-3 & schedule-4 can be downloaded by
the bidder through https://sjvn.abcprocure.com only after registration as explained above
in clause 1.8. The bid is to be filled only in the schedules available on the web. The
schedules-1, 2, 3 & 4 cannot be downloaded as they are to be filled online, however Bid
Proposal Sheet is to be downloaded first and is to be uploaded again after filling the same.
The bid is called under two parts system as under:-
► The prevailing rate of taxes & duties is to be clearly mentioned in the online
“Schedule of Prices with Taxes & Duties”. In case nothing is mentioned or
mentioned “NIL OR ZERO” then it shall be presumed that the rates quoted are
inclusive of taxes and duties or as else the taxes & duties are not applicable. The
taxes & duties shall be paid as per applicable rate at the time of delivery. Any
increase in taxes & duties /new introduction of new taxes & duties/ levy by the
Govt. shall be paid by SJVN Ltd. provided that such increase in taxes & duties
/new introduction of new taxes & duties/ levy by the Govt. is made with in schedule
delivery period as per LOA, otherwise same shall be paid by the bidders. The
following may be considered by the bidders:-
Remarks: All above dynamic schedules are to be filled ONLINE. The bidders have to fill
all the required information in the above schedule.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
► SJVN reserves the right to ask additional information if necessary after opening of
the bid.
► The bidder(s) not meeting the above requirements shall be considered techno-
commercial non responsive bidder(s) and price bid of such bidder(s) shall not be
opened.
► The Techno-Commercial Bid part will be opened electronically as per schedule time and
date as indicated in the bid documents in the O/o DGM (P&C), SJVN Ltd., Jhakri, Distt.
Shimla (H.P.) – 172 201.
► The Price Part will be opened electronically at same place only for those bidders whose
techno-commercial part is found to be techno-commercially acceptable and only such
bidders will be intimated subsequently either telephonically or through Fax / e-mail about
the time and date of price bid opening.
► The Owner further, reserves the right to reject any Bid which is not submitted according
to the instructions stipulated above.
► No Mobile Phone will be permitted inside the bid opening room. Therefore, bidders
should deposit Mobile Phones with Security gate at Reception.
► Bids will be evaluated for the complete scope of work/ BOQ on single responsibility
considering the cost as under:-
(i) Total Cost FOR Jhakri including all taxes.
(ii) Cost of withdrawal of deviations mentioned in online deviation schedule.
► No Price preference shall be given to any bidder during the bid evaluation.
► No cost loading will be carried out on account of lower delivery period. However, the
bidder can offer lower delivery period than the scheduled delivery period.
► Cost loading will be carried out for the deviations taken by the bidder to determine
the lowest evaluated Bid which will be considered for acceptance.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
► The bid will be evaluated on single responsibility basis for entire scope of work for both
years.
► The items for which bidder does not quote his price i.e. leaves the rate / amount column
blank or simply puts a (-) mark or (*) mark or indicates ‘NIL’ / ‘NA’ or as applicable,
no cost shall be considered for bid evaluation for these items, and for the purpose of
award the value of such item shall be deemed to have been included in other quoted
items. If the bidder does not agree to this consideration, his bid will be rejected and the
bid guarantee may be forfeited.
A. The bidder has to fill the Unit Rates in the FIGURES only.
B. The entered UNIT RATES in figures shall be automatically converted in to the words.
C. The bidder has to fill the applicable percentage (%) of the taxes & duties. The amount for
the taxes & duties shall be calculated automatically accordingly.
D. The above entered UNIT RATES in the figures and calculated amount of taxes & duties
shall be multiplied with quantity to calculate the TOTAL AMOUNT in figures & as well as
in words automatically.
E. After computation of the amounts as above, the values as computed shall be considered for
evaluation as well as for award. If the bidder does not accept the above consideration, his
bid will be rejected and the Bid Security / EMD may be forfeited.
F. The Owner's determination of a bid's responsiveness is to be based on the contents of the bid
itself without recourse to extrinsic evidence. If a bid is not substantially responsive, it will
be rejected by the Owner, and may not subsequently be made responsive by the Bidder by
correction of the non-conformity.
► No Bidder shall contact the Owner on any matter relating to its bid, from the time of the
opening of bids to the time the contract is awarded.
► Any effort by a Bidder to influence the Owner in the Owner’s bid evaluation, bid
comparison or contract award decisions may result in rejection of the Bidder’s bid.
► The Owner will award the contract to the successful Bidder whose bid has been
determined to be substantially responsive and to be the lowest evaluated bid on single
responsibility basis for entire scope of work, further provided that the bidder is
determined to be qualified to perform the contract satisfactorily.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
► The owner may request the Bidder to withdraw any of the deviations listed in Deviation
Schedule of the winning bid, at the price shown for the deviation in Deviation schedule.
In case the Bidder does not withdraw the deviations proposed by him, if any, at the cost
of withdrawal stated in the bid, his bid will be rejected and bid security forfeited.
► Bidders would be required to comply with all other requirement of the Bidding
Documents except for those deviations in Deviation Schedule, which are accepted by the
Owner, failing which the bid security of the Bidder may be forfeited.
► Award will be placed for total quantity of BOQ on L1 basis for substantially
responsive bid on single responsibility basis.
28.0 Owner's Right to Accept Any Bid and to Reject Any Bids
The Owner reserves the right to accept or reject any bid, and to annul the bidding process
and reject all bids at any time prior to award of contract, without thereby incurring any
liability to the affected Bidder or bidders or any obligation to inform the affected Bidder or
bidders of the grounds for the Owner's action.
► Upon the successful Bidder's furnishing of the performance security, the Owner will
promptly notify each unsuccessful Bidder and will discharge its bid security.
I. The contract agreement shall be signed in the office of undersigned within 30 days
from the date of issue of LOA.
II. The Contract Agreement (s) will be signed in three (3) originals on non –judicial
Stamp Paper (03Nos) of ₹ 100/- each along with Six (06Nos) copies of judicial paper
of ₹ 1/-each within 30(thirty) days of issue of Notification of awards/letter of Awards
and the contractor shall be provided with one signed copy of “Original Agreement”
and other will be retained by the owner. The non-judicial stamp papers & judicial
papers are to be purchased from Himachal Pradesh only.
III. The agreement shall be signed by the authorized signatory of contractor. Satisfactory
evidence of authority of the Authorized Signatory signing on behalf of the
Contractor shall be furnished while signing of agreement on non-judicial stamp
paper of an appropriate value in the form of a Power of Attorney/Authorization
Letter, duly notarized by a Notary Public, indicating that the Authorized
Signatory signing the agreement have the authority to sign the agreement and
that the agreement is binding upon the contractor.
IV. Subsequent to signing of the Contract(s), the contractor at his cost shall provide the
owner with at least four (4) copies of Agreement (Hard Bound) with in twenty (20)
days after signing of the contracts.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
30.0 Corrupt or Fraudulent Practices
A. The Owner requires that Bidders to observe the highest standard of ethics during the
procurement and execution of the Contract. For the purpose, the applicant shall sign
the Integrity Pact as per clause 31.0 of ITB. In pursuance of this policy, the Owner:
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) "corrupt practice" means the offering, giving, receiving or soliciting of any
thing of value to influence the action of a public official in the procurement
process or in contract execution; and
(ii) "fraudulent practice" means a misrepresentation of facts in order to influence
a procurement process or the execution of a contract to the detriment of the
Owner, and includes collusive practice among Bidders (prior to or after bid
submission) designed to establish bid prices at artificial non-competitive
levels and to deprive the Owner of the benefits of free and open competition;
(b) will reject a proposal for award if it determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in competing for the contract in
question;
(c) will declare a firm ineligible, either indefinitely or for a stated period of time, to be
awarded a contract if it at any time determines that the firm has engaged in corrupt
or fraudulent practices in competing for, or in executing, a contract of the Owner.
B. Furthermore, Bidders shall be aware of the provision stated in the "General Conditions of
Contract".
The pact essentially envisages an agreement between the prospective vendors / bidders and
the buyer, committing the persons / officials of both sides, not to resort to any corrupt practices
in any aspect / stage of the contract. Only those vendors / bidders, who commit themselves to
such a Pact with the buyer, would be considered competent to participate in the bidding
process. In other words, entering into this Pact would be a preliminary qualification. The
essential ingredients of the Pact include:
Promise on the part of the principal not to seek or accept any benefit, which is not legally
available.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
Bidders to disclose any transgressions with any other company that may impinge on the anti-
corruption principle
The Integrity Pact shall be applicable for transaction having threshold value of Rs. 8 lac for
procurement of Goods, Rs. 15 lac for procurement of Service and 50 lac for procurement of
Works. Further, the Independent External Monitors (IEMs) would be monitoring the bidding
process and execution of contract and shall be responsible for to oversee the implementation of
Integrity Pact Program to prevent corruption, bribery or any other unethical practices in SJVN
Ltd.
In order to deal with any grievance/dispute(s) and to oversee implementation and effectiveness
of the Integrity Pact programme pertaining to this tender, Bidders/Contractors may refer the
same to Independent External Monitors (IEMs). Name and Address of the Independent
External Monitor (IEMs) is as under:
All pages of the Integrity pact to be signed between SJVN Ltd. and the bidders / contractors on
plain papers at the time of submission of bid as per the approved format. Signed copy of the
Integrity Pact is to be included in the bid document while issuing Tender Document /
uploading the tender documents on the Portals. The bidders submitting tender document
(including downloaded) shall sign the Integrity Pact in original on the signed / scanned
Integrity Pact. The duly signed Integrity Pact shall be uploaded & submitted by the bidder
along with the bid.
Failure to sign the integrity pact by applicant shall be liable to outright rejection of
application / bid.
The successful bidder (Contractor) shall submit duly executed Integrity Pact on Non-judicial
Stamp Paper of Rs 100/- within 15 days from the date of issue of LOA.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
(i) Earnest Money Deposit (In original) / FDR/TDR as per clause no. 11.0
(ii) Power of Attorney/Affidavit of Proprietorship as per Sr. no. 19.0 above
► These scanned copies of above documents should be uploaded on web and is to be reach
on or before closing date and time as per the bidding document i.e. on or before
20.06.2018 13:00 HRS.
Remarks: The scanned copy (ies) of the document(s) asked as above are to be uploaded on
web and should reach in original/physical form at above address preferably on or before
bid closing date as specified in the tender. However, the original document(s) in physical
shall also be acceptable within 07 days after bid closing date, otherwise bid(s) shall not be
entertained and such bid(s) shall be treated as late bid(s)/non-responsive bid(s). Also if the
original document(s) in physical form are found to be at variance than the scanned copies
submitted /uploaded earlier along with e-bids, the bid(s) will be treated as non-responsive.
33.0 Undertaking:
33.1 We have read carefully all the bidding documents and agreed to the conditions except for
deviation taken clause wise in deviation schedule.
33.2 We have not changed the contents of the bidding documents.
33.3 The Scanned copy of documents uploaded along with the bid is true to the best of my
knowledge.
33.4 We shall not sublet/ sub-contract this work.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New Delhi.
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ITB- (PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
Package (W)-195(O&M)
QUALIFICATION CRITERIA
Qualifying requirement for “Package (W)-195 (O&M) “Work for Annual Plant Maintenance for
2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”.
A. QUALIFYING REQUIREMENTS
1. PROVEN EXPERIENCE:
(i) The bidder must have carried out successful overhauling work of at least three (03) units of Francis
hydro generating units involving Turbine ( having minimum runner inlet diameter of
2833mm),Main Inlet Valve {Spherical Valve having minimum size of 1518mm(ID)},Generator,
Generator Transformer, GIS and Butterfly valve broadly for entire scope of work as mentioned. The
overhauling work must have been completed in maximum within 15 days for each unit. Such work
must have been completed during last 7 years ending the last day of the month previous to one in
which tenders are uploaded on website.
(ii) The bidder must submit the certificates to this effect from their clients without which the price-bids
shall not be considered for opening.
3. The Bidder should have successfully completed/executed similar works* as per any of following
criteria during last 07(Seven) years ending last day of month previous to one in which tender/NIT is
uploaded on websites by SJVN.
(a) The Bidder should have completed the 3 similar works valuing not less than ₹ 71,
71,426/- (₹ Seventy One Lac Seventy One Thousand Four Hundred Twenty Six only)
each.
Or
(b) 2 similar completed works, valuing not less than ₹ 89,64,283/- (₹ Eighty Nine Lac Sixty
Four Thousand Two Hundred Eighty Three only) each.
Or
(c) 1 similar completed work, valuing not less than ₹ 1,43,42,852/- (₹ One Crore Forty
Three Lac Forty Two Thousand Eight Hundred Fifty Two Only).
*Definition of similar work is erection testing and commissioning and /or overhauling work
of Francis Hydro- generating units.
Remarks: - The above mentioned values are exclusive of taxes.
PQR- PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
Registered & SJVN Corporate office complex, Shanan Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh, Pin No.- ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office 171006. FAX: 011- 41659204/14
Page 1 of 3
The bidder must submit the copies of LOAs/ work orders/ agreements for the same along with the
satisfactory completion certificate from the end users and in the case the LOAs/ work orders/
agreements are from the private company (ies) /firm (s), then copy (ies) of TDS for the same are
also need to be submitted along with the satisfactory completion certificate.
2. Detailed scope of work has been described in other sections of bidding documents.
3. SJVN reserves the right to cancel / withdraw the invitation for bid without assigning any
reason and shall bear no liability whatsoever consequent upon such a decision.
4. Notwithstanding anything stated above, SJVN reserves the right to assess the Bidder’s
capability and capacity to perform the contract satisfactorily, should the circumstances
warrant such assessment in the overall interest of SJVN.
5. Price bid of only those bidders shall be opened who qualify based on the specified
qualifying requirements after Scrutiny of details / documents furnished by them and found
to be techno- commercial responsive.
PQR- PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
Registered & SJVN Corporate office complex, Shanan Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh, Pin No.- ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office 171006. FAX: 011- 41659204/14
Page 2 of 3
SJVN Ltd.
Annexure-I’
Under Taking From Bidder
1.1 We are qualified under clause A (1.0 to 3.0) of the qualifying requirements.
1.2 We have carried out the overhauling work of at least three units of Francis hydro generating units
involving Turbine ( having minimum runner inlet diameter of 2833mm),Main Inlet Valve
{Spherical Valve having minimum size of 1518mm(ID)},Generator, Generator Transformer, GIS
and Butterfly valve broadly for entire scope of work as mentioned. The overhauling work have
been completed in maximum within 15 days for each unit for entire scope of work as mentioned
in scope of work during last 7 years ending the last day of the month previous to one in which
tenders are uploaded on website.
Remarks: The detail of the orders executed in the past in support of above is given in the
Schedule-4 of techno-commercial Schedules.
PQR- PKG (W)-195 “Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
Registered & SJVN Corporate office complex, Shanan Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh, Pin No.- ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office 171006. FAX: 011- 41659204/14
Page 3 of 3
1
1.0 Definitions
In this Contract, the following terms shall be interpreted as indicated:
(a) "The Contract" means the Contract Agreement entered between the Owner and
the Contractor, as recorded in the Contract Form signed by the parties, including all
attachments and appendices thereto and all documents incorporated by reference
therein.
(b) "The Contract Price" means the price payable to the Contractor under the
Contract for the full and proper performance of its contractual obligations.
(c) "The Services" means all those services necessary for Supply of the material and
any other incidental services etc and other such obligations of the Contractor
covered under the Contract.
(e) "The Contractor" means the individual or firm supplying the material under this
Contract.
(f) "Corrupt Practice" means the offering, giving, receiving or soliciting of any thing
of value to influence the action of a public official in the procurement process or in
contract execution.
2.2 The proceeds of the performance security shall be payable to the Owner as compensation
for any loss resulting from the Contractor's failure to complete its obligations under the
Contract.
2.3 The performance security shall be denominated in the currency of the Contract and shall be
in the form of Bank Guarantee ( As per SJVN standard format enclosed) issued
preferably by a nationalized Bank/ scheduled bank as per RBI guide line (As per the list
enclosed) , acceptable to the Owner or in the form of FDR or TDR etc.
2.4 The performance security will be discharged by the Owner and returned to the Contractor
not later than sixty (60) days after completion of guarantee period of the work.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
2
2.5 The interest @ 15.5% shall be charged on delayed period for breach in timely
submission of CPG/Initial Security Deposit without prejudice to right of SJVN to
other remedies available under the contract.
2.6 The MSE/ NSIC registered firms are not exempted from submission of contract
performance Security.
3.0 INSURANCE
3.1 Any loss or damage to the deployed man and machinery by the successful bidder during
carrying out the work and any accident or death of persons due to negligence on the part of
the contractor shall be to the contractor’s account for all risks. The contractor shall be
responsible for his man machinery deployed to carry out the job. The contractor shall
obtain insurance policy for the deployed man power accordingly.
5.2 If a Force Majeure situation arises, the Contractor shall promptly notify the Owner in
writing of such condition and the cause thereof. Unless otherwise directed by the Owner in
writing, the Contractor shall continue to perform its obligations under the Contract as far as
is reasonably practical, and shall seek all reasonable alternative means for performance not
prevented by the Force Majeure event.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
3
6.2 The GST shall be paid as per the GST rules on submission of the following information
along with the invoices:-
(i) Name, Address Contact Details (Tel. No. etc.) of service provider.
(ii) Specific Invoice Number format.
(iii) Name and address of recipient.
(iv) Address of Delivery.
(v) HSN code of goods/ SAC for Services.
(vi) Description and quantity of goods/services.
(vii) Value of goods.
(viii) Rate and amount of tax.
(ix) Other prescribed information.
6.3 TAX DEDUCTION AT SOURCE: SJVN Ltd. shall be entitled to make all deduction
towards taxes from the payments to be made as per rules. However SJVN Ltd. shall
give a statement in respect of such deductions to the contractor.
6.5 The payment shall be released through electronic fund transfer and hence you are requested
to give your bank account detail along with IFSC/RTGS code of your bank branch. The
required detail is to be filled in the online “Schedule-3-General Information & Bank
account details”. Bank charges if any, shall be borne by you. The details to be submitted
in the schedule as enclosed.
6.6 This however, shall not be linked with liability of the contractor to pay wages to his worker
as per provisions of wages act. The contractor shall make payment to the workmen hired by
him for this job by 7th of each month. In case of his failure to do so, EIC shall make direct
payment to the workmen hired by him and shall recover the payments so made by SJVN
from the pending dues of the contractor alongwith 25% cost as SJVN Ltd., over head.
6.7 All the payments for the supplies and/or services (as applicable) rendered by MSEs (Micro
& Small Enterprises) supplier/contractor under the contract shall be released within forty
five (45) days from the day of acceptance.
Day of acceptance means day of actual delivery of goods or the rendering of services; or
where any objection is made in writing by SJVN regarding acceptance of goods or services
within fifteen days from the date of delivery of goods or the rendering of services, the day
on which such objection is removed by the contractor/supplier.
In case payments are not released as mentioned above, SJVN shall pay the principal
amount plus compound interest with monthly rests from the date immediately following the
date agreed upon @ three times of bank rates as notified by Reserve Bank of India time to
time.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
4
6.8 All the payments for the supplier and/or services (as applicable) rendered by non-MSEs
(Non- Micro & Small Enterprises) supplier/ contractor under the contract shall be released
within forty five (45) days from the receipt of invoices/bills from the contractor/ supplier
complete in all respects.
In case payments are not released as mentioned above, SJVN shall pay the principal
amount plus simple interest from the date immediately following the date agreed upon @
8% p.a.
ii) As regards the Income Tax, Surcharge on Income tax any other Tax such as Corporate
Tax etc. shall not bear any Tax liability whatsoever. The contractor shall be liable and
responsible for payment of such Tax if attracted under the provisions of law present or
future and SJVN will make deductions at source as applicable.
iii) The taxes and duties as indicated in schedule of taxes and duties in price schedule shall
be considered for evaluation of bids and shall be paid extra by SJVN.
Sr. Period in
Description of work
No. Machine Days
Normal Maintenance
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
1 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 1st Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
2 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 2nd Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
3 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 3rd Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
4 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 4th Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
5 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 5th Unit as per BOQ/ Scope of work.
Annual Overhauling of Turbine, Generator, Governor, MIV Service 10
6 seal, Butterfly valve, GIS Protection and transformers along with
their auxiliaries of 6th Unit as per BOQ/ Scope of work.
60
7 Total No. of Days for all six units. (Machine days)
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
5
Note:
i) The maximum work completion period for each unit shall be machine days as
above. Next unit work shall be undertaken after completion of work of
first/previous unit and as on date as desired by EIC. EIC may also ask for
parallel work in two units for which nothing extra is payable.
ii) Ventilation work and maintenance of GIS & Protection system shall be
carried out parallel with other works or separately as decided by EIC.
Special Maintenance
8 Annual Overhauling of MIV Maintenance Seal (Per Seal) 07 days
Note:
i) This shall be carried out under Special maintenance of MIV Maintenance
Seal, maintenance of MIV service seal if required shall be a parallel activity.
The Maximum Work Completion Period will be 60 Machine Days for all the units.
The maximum completion schedule for MIV Maintenance seal (special
maintenance, if any) shall not be more than 7 days in any case. Other parallel
activities could also be performed with this activity as decided by EIC.
Bidder should programme the work activity with three shift working, seven (7)
days a week including holidays with working on a single unit or on two units in
parallel.
The zero date for first unit will start from the date of handing over of the first unit
by the EIC to contractor. The zero date for next machine will start from date of
handing over of next unit. There may be some gap between work completion of
previous unit and start of next unit as per situation and availability of water. For
such gaps nothing extra shall be payable.
In case of delay due to non- availability of material, the same will be to SJVN
account and equal no. of days will be added in machine days for which material is
not available to achieve new normal schedule for work completion. Except change
in completion schedule no other compensation shall be payable on account of this.
The L.D. clause will be applicable considering new/ revised completion period for
unit under consideration at that time.
Bidders offering completion schedule of more than machine days as specified for
each unit and more than 60 machine days for all the six units per year shall not be
considered for evaluation.
9.2 In case of delay in the completion of work beyond the work completion schedule as
stipulated in clause 8 above i.e. 07 machine days for MIV maintenance seal of each unit of
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
6
9.3 The GST shall be levied extra on above L D Charges as per applicable rule under GST.
a) If the Contractor fails to complete any part of all the work or all of the Goods within the
period(s) specified in the Contract, or within any extension thereof granted by the Owner.
b) If the Contractor fails to perform any other obligation(s) under the Contract.
c) If the Contractor, in the judgment of the Owner has engaged in corrupt or fraudulent
practices in competing for or in executing the Contract.
"Corrupt practice" means the offering, giving, receiving or soliciting of any thing of value to
influence the action of a public official in the procurement process or in contract execution.
10.2 In the event the Owner terminates the Contract in whole or in part, the Owner may procure
/ get repaired, upon such terms and in such manner as it deems appropriate, Goods or
Services similar to those undelivered / un-repaired, and the Contractor shall be liable to the
Owner for any excess costs for such similar Goods or Services. However, the Contractor
shall continue performance of the Contract to the extent not terminated.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
7
12.2 The Contractor upon receipt of such notice shall discontinue the work on the date and to
the extent specified in the notice, make all reasonable efforts to obtain cancellation of all
orders and contracts to the Owner, stop all further sub-contracting or purchasing activity
related to the work terminated, and assist the Owner in storage, maintenance, protection,
and disposition of the works acquired under the contract by the Owner.
12.3 In the event of such a termination, the Contractor shall be paid equitable and reasonable
compensation, as dictated by the circumstances prevalent at the time of termination.
If any dispute or difference of any kind whatsoever shall arise between the Owner and the
Contractor, arising out of the Contract for the performance of the Works whether during the
progress of the Works or after its completion or whether before or after the termination,
abandonment or breach of the Contract, it shall, in the first place, be referred to and settled
by the Engineer, who within a period of ten (10 ) days after being requested by either party
to do so, shall give written notice of his decision to the Owner and the Contractor.
Save as hereinafter provided, such decision in respect of every matter so referred shall be
final and binding upon the parties until the completion of the entire work under the
Contract and shall forthwith be given effect to by the Contractor who shall comply with all
such decisions, with all due diligence, whether he or the Owner requires arbitration as
hereinafter provided or not.
If after the Engineer has given written notice of his decision to the parties, no claim to
arbitration has been communicated to him by either party within ten (10) days from the
receipt of such notice, the said decision shall become final and binding on the parties.
In the event of the Engineer failing to notify his decision within ten (10) days after being
requested as aforesaid or in the event of either the Owner or the Contractor being
dissatisfied with any such decision, or within ten (10) days after the expiry of the first
mentioned period of ten (10) days, as the case may be, either party may require, by written
notice to the other party, that the matters in dispute be referred to arbitration as hereinafter
provided.
14.2 In the event of the Contractor, that is to say a citizen and/or a permanent resident of India, a
firm or a company duly registered or incorporated in India, the arbitration shall be
conducted by three arbitrators, one each to be nominated by the contractor and the Owner
and the third to be named by the President of Institution of Engineers, India. If either of the
parties fails to appoint its arbitrator within thirty (30) days after receipt of a notice from the
other party invoking the arbitration clause, the President of the Institution of Engineers,
India shall have the power at the request of either of the parties, to appoint the arbitrators.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
8
A certified copy of the said President making such an appointment shall be furnished to
both the parties.
14.3 The arbitration shall be conducted in accordance with the provisions of the Arbitration &
Conciliation Act, 1996 or any statutory modification thereof.
14.5 The decision of the majority of the arbitrators shall be final and binding upon the parties.
The expenses of the arbitration shall be paid as may be determined by the arbitrators. The
arbitrators may, from time to time with the consent of all the parties enlarge the time for
making the award. In the event of any of the aforesaid arbitrators dying, neglecting,
resigning of being unable to act for any reason, it will be lawful for the party concerned to
nominate another arbitrator in place of the outgoing arbitrator.
14.6 The arbitrator shall have full powers to review and/or revise any decision, opinion,
directions certification or valuation of the Engineer in consonance with the contract.
15.2 The arbitration procedure shall be as per the guidelines issued by DPE (department of
Public Enterprise).
“In the event of any dispute or difference relating to the interpretation and application of
the provisions of the contracts, such dispute or difference shall be referred by either party
for Arbitration to the sole Arbitrator in the Department of Public Enterprises to be
nominated by the Secretary to the Government of India in-charge of the Department of
Public Enterprises. The Arbitration and Conciliation Act, 1996 shall not be applicable to
Arbitration under this clause. The Award of Arbitrator shall be binding upon the parties to
the dispute, provided, however, any party aggrieved by such award may make a further
reference for setting aside or revision of the award to the Law Secretary, Department of
Legal Affairs, Ministry of Law & Justice, Government of India. Upon such reference the
dispute shall be decided by the Law Secretary or the Special Secretary/Additional
Secretary, when so authorized by the Law Secretary, whose decision shall bind the Parties
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
9
finally and conclusively? The Parties to the dispute will share equally the cost of arbitration
as intimated by the Arbitrator”.
a) the Contractor shall not be liable to the Employer, whether in contract, tort, or
otherwise, for any indirect or consequential loss or damage, loss of use, loss of
production, or loss of profits or interest costs, provided that this exclusion shall not
apply to any obligation of the Contractor to pay liquidated damages to the Employer and
b) the aggregate liability of the Contractor to the Employer, whether under the Contract, in
tort or otherwise, shall not exceed the total Contract Price, provided that this
limitation shall not apply to the cost of repairing or replacing defective
equipment, or to any obligation of the Contractor to indemnify the Employer with
respect to patent infringement.
18.0 NOTICES
► Any notice given by one party to the other pursuant to this Contract shall be sent to the
other party in writing or by cable telex, or facsimile and confirmed in writing to the other
party's address specified in NIT/NIQ.
► A notice shall be effective when delivered or on the notice's effective date, whichever is
later.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
10
vii) The Payment in respect of EPF and ESIC contribution as applicable shall be made by the
contractor and no additional liability on this account shall be borne by SJVN.
viii) The contractor shall be responsible to ensure all safety measures during the work. In case
any mishap, the contractor shall have to bear all financial liability. SJVN shall not bear
any compensation or responsibility.
ix) The contractor will have to make his own arrangement to reach Jhakri and for local
conveyance during his stay at Jhakri or elsewhere during the execution of the contract.
x) The contractor shall follow all labour law reticulation as applicable in H.P.
xi) The contractor shall follow basic requirements as per attached Annexure.
xii) The contractor or his authorized representative shall make himself available in the
following designated areas/ offices, so that he can be given instructions about the job.
xiii) The contractor shall apply for the photo gate pass to all labourers who are engaging for
the work in the undertaking with their full residential address as per form “B”. The form
“B” shall be issued by P&A Deptt., NJHPS, SJVN Ltd. Jhakri.
xiv) The character and antecedents of all the labourers are required to be verified through
local police before engaging.
xv) The labourers of Nepal, Bangladesh, J&K and Tibet are required to be registered in the
local police station before engaging by the contractor for work and their finger
impression and photographs are required to be recorded in the local police station.
xvi) The labour will not use a dangry, Army/police force colour while doing work.
21.0 CORRESPONDENCE:
i. All correspondence related to this work before award of the contract shall be addressed to
Sr. Manager, Procurement & Contract Deptt, NJHPS, SJVN Ltd., Jhakri, Distt Shimla
(H.P.), PIN- 172201. PH No. 0091-1782-275794 Fax: No. 0091-1782-234049.
ii. All the correspondences after award of the contract shall be addressed to EIC of the work.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
GCC (PKG (P)-195 “ Work for Annual Plant Maintenance for 2018-19 & 2019-20 of Generating units and auxiliaries of NJHPS, Jhakri”)
ANNEXURE
Basic Requirements:
1. The contractor has to observe all site norms applicable for the contractor and
his deployed personnel’s at worksite.
(Employees; regular/ daily wages/ contract basis etc.)
2. NJHPS SJVN Ltd. is IS/ISO 9001:2008 Quality Management Systems, IS/ ISO
14001:2004 Environment Management Systems and IS 18001:2007 -
Occupational Health and Safety Management System certified project. In line
with the requirements of same, the Contractor needs to follow health, safety and
environmental norms strictly while working within the premises of the company
during the whole currency of the contract.
a) The contractor and/ or supervisor engaged by the contractor for the supervision of
the work should be well aware of the safety & health practices and effective
implementation.
b) The contractor should have sufficient variety and stock of suitable safety gears
and its use by workmen should be ensured on all occasion.
c) All the equipment deployed for the job should have proper safety guards.
e) The contractor and his employees shall follow Industrial/Project Security Norm
strictly. The contractor or his authorized representative shall arrange all requisite
documents for himself and for his employees or the machinery deployed by him
from the Project Security Wing (P&A deptt. /CISF). Such documents are liable
for scrutiny at any time.
g) All the requisite registers/ documents required under the labour / workmen law
shall be maintained by the contractor and need to be produced if required. The list
of such documents, provided along with the bid, needs to be maintained by the
contractor. Failure to maintain such records and documentation, the contractor
shall only be sole responsible. When desired by the EIC or his representative,
contractor shall produce the same.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
h) No drunken personnel shall be allowed to perform duties or approach the
worksite. Such defaulters shall be taken seriously and dealt severely.
i. The Contractor shall use exhaust blowers/ fans of suitable capacity for
effective ventilation of the workplace.
Note: - Non-adherence of the above shall attract suitable penalties on first &
subsequent observation.
Registered & SJVN Corporate Office Complex, Shanan, Liaison/Co- SJVN, IRCON Building, Ground Floor, Saket New
Corporate Shimla, Himachal Pradesh Pin No.-171006 ordination Office Delhi. PIN-110017, TELE: 011- 41659210/17
Office FAX: 011- 41659204/14
ANNEXURE
Dear Sirs,
In consideration of the SJVN LTD. (hereinafter referred to as the 'Owner,' which expression
shall unless repugnant to the context or meaning thereof, include its successors,
administrators and assigns) having awarded to M/s. ……….. [Contractor's Name] ………..
with its Registered/Head Office at ……… …………………..……………………
(hereinafter referred to as the 'Contractor', which expression shall unless repugnant to the
context or meaning thereof, include its successors administrators, executors and assigns), a
Contract by issue of Owner's Notification of Award No. …………….. dated ………….. and
the same having been unequivocally accepted by the Contractor, resulting in to a contract
bearing No…………. dated …………. Valued at ……………….. for ……………… and the
Contractor having agreed to provide a Contract Performance Guarantee for the faithful
performance of the entire Contract equivalent to ….. (*) ….. % (………………. percent) of
the said value of the Contract to the Owner.
We ……………….. [Name & Address of the Bank] …..………. Having its Head Office at
………………………….. (hereinafter referred to as the 'Bank', which expression shall,
unless repugnant to the context or meaning thereof, include its successors, administrators,
executors and assigns) do hereby guarantee and undertake to pay the Owner, on demand any
and all monies payable by the contractor to the extent of ………... (*) ………. as aforesaid at
any time upto ……………. (@) ………… [days/month/year] without any demur,
reservation, context, recourse or protest and/or without any reference to the Contractor. Any
such demand made by the Owner on the Bank shall be conclusive and binding
notwithstanding any difference between the Owner and the Contractor or any dispute
pending before any Court, Tribunal, Arbitrator or any other authority. The Bank undertakes
not to revoke this guarantee during its currency without previous consent of the Owner and
further agrees that the guarantee herein contained shall continue to be enforceable till the
Owner discharges this guarantee.
The Owner shall have the fullest liberty, without affecting in any way the liability of the
Bank under this guarantee, from time to time to extend the time for performance of the
Contract by the Contractor. The Owner shall have the fullest liberty, without affecting this
guarantee, to postpone from time to time the exercise of any powers vested in them or of any
right which they might have against the Contractor, and to exercise the same at any time in
any manner, and either to enforce or to forbear to enforce any covenants, contained or
implied, in the Contract between the Owner and the Contractor or any other course or remedy
or security available to the Owner. The Bank shall not be released of its obligations under
these presents by any exercise by the Owner of its liberty with reference to the matters
aforesaid or any of them or by reason of any other act or forbearance or other acts of
omission of commission on the part of the Owner or any other indulgence shown by the
Owner or by any other matter or thing whatsoever which under law would, but for this
provision, have the effect of relieving the Bank.
The Bank also agrees that the Owner at its option shall be entitled to enforce this Guarantee
against the Bank as a principal debtor, in the first instance without proceeding against the
Contractor and notwithstanding any security or other guarantee that the Owner may have in
relation to the Contractor's liabilities.
Not withstanding anything contained hereinabove our liability under this guarantee is
restricted to …………. (*) ……….. and it shall remain in force up to and including
…………. (@) ……… and shall be extended from time to time for such period (not
exceeding one year), as may be desired by M/s………….. [Contractor's Name] ………... on
whose behalf this guarantee has been given.
Dated this ………………. day of ………….. 2018 ………. at …………………………...
WITNESS
…………………………..… (Signature) ……….…………
(Signature)
……………………………..
(Name) (Name) ………………….….
…………………………….. ………………………………
(Official Address) (Designation with Bank
Stamp)
Attorney as per Power of
Attorney No………………
Dated …………………….
Notes: 1. (*) this sum shall be ten percent (10%) of the Contract Price.
(@) This date will be sixty (60) days beyond the guarantee period as
specified in the Contract.
AND
1. In this Agreement, words and expression shall assume the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred to and
they shall be deemed to form and be read and construed as part of this Agreement.
3. The Employer hereby covenants and agrees to pay the Contractor in consideration of the
execution and completion of the Works and the remedying the defects therein, the
Accepted Contract Amount or such other sum as may become payable under the
provisions of the Contract at the times and in the manner prescribed by the Contract.
4. The contractor undertakes to execute and complete the Works within the Time for
Completion and to achieve the Milestones within the time prescribed thereof in the
Contract.
5. The following documents shall be deemed to form and be read and construed as integral
part of this Agreement: This Agreement shall prevail over all other Contract Documents.
In witness whereof the parties hereto have executed this Agreement on the day, month and year first
written before.
The Common Seal of both the Parties is hereunto affixed in the presence of:
SCHEDULED BANKS
NATIONALISED BANKS
Allahabad Bank
Andhra Bank
Bank of Baroda
Bank of India
Bank of Maharashtra
Canara Bank
Central Bank of India
Corporation Bank
Dena Bank
Indian Bank
Indian Overseas Bank
Oriental Bank of Commerce
Punjab National Bank
Punjab and Sind Bank
Syndicate Bank
UCO Bank
Union Bank of India
United Bank of India
Vijaya Bank