Professional Documents
Culture Documents
Module 3 Notes
Module 3 Notes
CONSTRUCTION AND
PROJECT MANAGEMENT
MODULE III
INTRODUCTION TO CONSTRUCTION SCHEDULING
Project
Project Project
planning and Close-up
Initiation execution
procurement Phase
Phase processes
phase.
Project
Control
Construction
Phase
Processes
PMBOK, 2000
• Scope definition
Work Breakdown Structure
• Activity definition
• Activity Sequencing
• Activity duration estimating
• Schedule development
• Risk Management planning
• Resource planning
• Cost estimating
• Cost Budgeting
• Project plan development
PMBOK, 2000
It decomposes the project work scope into deliverables and splits up deliverables into
various levels such as sub projects or task groups, tasks, work packages and activities
(K.K. Chitkara, Construction Project Management)
LEVEL 1
LEVEL 2
LVL 0
LVL 1 LEVEL 3
LVL 2
LVL 3
Schedule development
Schedule development means determining the start and finish dates for project
activities by analysing activity sequences, activity durations and resource
requirements.
Henry Gantt
PE-563 : Construction and Project Management C.A.T 19
Gantt Chart / Bar Chart
• Task with a short description
• Start and end date
• Time scaled Bars
• Obtain Activities and Durations
• List activities in increasing order
of start date.
• Time - scaled bars
• Earliest start and Finish dates are
represented usually.
• Activities can overlap
PE-563 : Construction and Project Management C.A.T 20
Gantt Chart - Types
Percentage complete
PE-563 : Construction and Project Management C.A.T 21
Gantt Chart - Types
Milestone chart
PE-563 : Construction and Project Management C.A.T 23
Gantt Chart – Real life problems
Duration
Activity Description Cost (Rs) Start date
(days)
Total 15000
Total 15000
Total 15000
Total 15000
Cost of Work done (Rs) 2083 2083 2083 2083 2083 7833 5750 8917 8917 9288 10489 7988 10738 6072 5522 5522 5522 5522 3321 3321 3321 3321 3321 1200
102973
108495
111816
115137
118458
121779
125100
126300
10415
18248
23998
32915
41832
51120
61609
69597
80335
86407
91929
97451
2083
4166
6249
8332
Percentage (%) 1.65 3.30 4.95 6.60 8.25 14.45 19.00 26.06 33.12 40.48 48.78 55.10 63.61 68.41 72.79 77.16 81.53 85.90 88.53 91.16 93.79 96.42 99.05 100.00
Network diagram
Nodes = Events
Activities
Activity
Event 1 Event 2
Duration
Source: IS 14580, 2006
(PMBOK, 2013)
Avoid
Redundancy
2. Generate WBS
2 4
Footing 2 Wall 2
1
Start Finish
Footing 1
3
Wall 1
Source: IS 14580
PE-563 : Construction and Project Management C.A.T 47
Common Errors during Networking
4. Where-crossing of arrows is
inevitable, it should be shown-by the
arrow with a kinc at the crossing
point.
Step2:1:Sequence
Step Dependency
steps
PE-563 : Construction and Project Management C.A.T 50
Network diagram – Illustration 02
Activity Diagram (AoA Network)
2
E
D
1 3 5
Dummy
activity
LSA = LFA – TA
PE-563 : Construction and Project Management C.A.T 57
Floats and Critical Path
Total Float or simply float is the amount of time an activity can delay but not delay
the termination of the project
A CPM critical path is normally characterized by zero total float on the critical path.
Any activity on the critical path is called a critical path activity.
Earliest
Earliest
Occurrence
Occurrence
Time
Time
Event Activity Name Milestone
Float Float
Number Duration Number
Latest Latest
Occurrence Occurrence
Time Time
Earliest Earliest
Activity Name Duration
Start (ES) Finish (EF)
Earliest Latest
Activity Name
Start (ES) Start (LS)
Duration
Earliest Latest Latest Total Latest
Finish (EF) Finish (LF) Start (LS) Float Finish (LF)
2. Traverse the network through the relationship arrows until you reach the end
3. For each activity, the early start is the maximum of the early finishes of the
previous activities
2. Traverse the network backwards through the relationship arrows until you
3. For each activity, the late finish is the minimum of the late starts of the
previous activities.
0 6 6 21 6 27
Start A F Finish
0 0 6 21 0 27
6 8 14 15 4 19
C D
9 3 17 17 2 21
5. Determine floats
0233
E 3
0 6 D 9
0 10 1 37 05 9
2
Dummy
activity
46
1 7
PE-563 : Construction and Project Management C.A.T 68
Critical Path Method – Illustration 02 (AoA)
Float of Activity = Late Occurrence(j) – Early occurrence(i) – Duration
Float (A) = 3 – 0 – 3 = 0
Float (B) = 9 – 3 – 6 = 0
Float (C) = 9 – 6– 2 = 1
Float (D) = 9 – 6– 2 = 1
Float (E) = 7 – 3– 3 = 1
Float (F) = 7 – 0– 4 = 3
4 x 3 = 12 relationships
PE-563 : Construction and Project Management C.A.T 71
Critical Path Method (CPM)
Concept of Relationships
1. Finish – Start Relationship
TFC = 9 – 6 = 3
FFA = 1
(j) TFA = 3
IntFi = TFi– FFi
FFA = 1
Int.FA = 3 – 1 = 2