Government of Karnataka

Summary of the Mineral Block


(to be made available on the website of e-auction platform provider)
(As per GoI Notification No:1/15/2015-M.VI Dated:02.07.2015)

Part A - GENERAL INFORMATION ABOUT MINERAL BLOCK


Features Details
1 Location
Mineral Block Maruthipura Gold Block
Corner Points
Between Latitudes N15⁰00’00” and 15⁰04’33”
Latitude-Longitude
Longitudes E75⁰19’58” and 75⁰24’37”
A = N15°04'31.89513", E75°19'58.07919"
Latitude, Longitude of Corner Points B = N15°04'32.45829", E75°22'00.03490"
as per DGPS C = N14°59'59.90298", E75°24'37.41854"
D = N14°59'59.97255", E75°22'48.01017"
Villages Maruthipura
Tehsil/ Taluka Savanur, Kundgol
District Dharwar and Haveri
State Karnataka
2 Area Total area – 28.92 sq.km.
Mineralised Area in Ha. Mineralised area approximation for gold
mineralisation is not attempted with G4 data as the
gold mineralisation is subjective to many factors and
Non-mineralised Area in Ha.
detailed exploration is required to ascertain the
actual extent.
3 Exploration
G4 level as per Minerals (Evidence of Mineral
Status (G1/G2/G3/G4 etc.)
Contents) Rules, 2015.
Exploration Agency Geological Survey of India
10 core boreholes with a total meterage of 1039.9m
Total Number of Boreholes with
has been carried out in the northern part of the
Meterage
block.
100m interval along the strike in northern part of the
Borehole Spacing (Density)
block.
4 Quantity of Minerals (Grade-wise)
Gold
Resources have not been fully estimated in the entire
block. However 0.06 MMT at 0.5g/t Au resources
Total Geological Resources
has been estimated by considering one borehole
data.
Due to absence of resource estimation for the entire
Value of Estimated resources of the block, Value of estimated resources is not
Concession area in Indian Rupees calculated.

Information Memorandum/ Mine Block Summery Page 1


Government of Karnataka

5 Mineralised Zones
Number of Mineral Zones Mineral content established
Trend (Dip and Strike) NNW-SSE direction
Total Thickness Not applicable
6 Accessibility
Nearest Rail Head Gudageri Railway Station
It is situated about 400km NNW of Bangalore and is
well connected by Bangalore-Pune highway (NH-4).
The interior villages are connected to Taluk
Road headquarters by number of tar roads. The nearest
railway station Gudageri is located on Bangalore –
Hubli Broad gauge line located in the Ranibennur
Hubli section of SW Railway.
Airport Hubbali
7 Hydrography
Local Surface Drainage Pattern
Dendritic drainage pattern
(Channels)
The area is having high density of ephemeral
Rivers/Streams
streams due to undulatory terrain conditions.
8 Climate
Mean Annual Rainfall 650-700mm
Temperatures (December) Min 17⁰C
Temperatures (June) Max 42⁰C
9 Topography Undulating topography
Topo Sheet Number 48M/8
Morphology of the Area Isolated linear ridges (Hills)
Part B - PARTICULARS OF STATUTORY LICENSES, PERMITS, PERMISSIONS,
CONCESSIONS, APPROVALS AND CONSENTS RELATED TO MINING OPERATIONS
Particulars Details/Status
To be obtained by the successful bidder where ever
1 Forest clearance for leased area
it is required
Wild life clearance (sanctuary, reserve To be obtained by the successful bidder where ever
2
or special zone clearances) it is required
To be obtained by the successful bidder where ever
3 Environmental Clearance
it is required
To be obtained by the successful bidder where ever
4 Consent to establish
it is required
To be obtained by the successful bidder where ever
5 Explosive licence
it is required
To be obtained by the successful bidder where ever
6 Permission for mine opening
it is required
Permission of installation/ trial To be obtained by the successful bidder where ever
7
operation of equipment. it is required
To be obtained by the successful bidder where ever
8 Ground water clearance (Centre/State)
it is required

Information Memorandum/ Mine Block Summery Page 2


Government of Karnataka

To be obtained by the successful bidder where ever


9 Railway siding approval
it is required
To be obtained by the successful bidder where ever
10 Approval for diesel storage
it is required
To be obtained by the successful bidder where ever
11 Power line from State Discom
it is required
Clearances relating to work under To be obtained by the successful bidder where ever
12 an existing transmission line or it is required
shifting of the transmission line
To be obtained by the successful bidder where ever
13 Grama Sabha consent
it is required
To be obtained by the successful bidder where ever
14 Consent for Operate (CFO)
it is required
To be obtained by the successful bidder where ever
15 Approval of Mine Plan from IBM
it is required
To be obtained by the successful bidder where ever
16 Others (if any)
it is required
Part C - Particulars of Land
Area Details
1 Total Concession Area 2892.8 Ha
2 Forest Land with Status Nil.
Approximately 351.68 Ha as per Land use land
3 Government Land with Status
cover data computation.
Approximately 2541.12 Ha as per Land use land
4 Private land with Status
cover data computation.
Land use Land cover map prepared using spatial
data with Cadastral details is uploaded for ready
reference. The survey number wise details of land
status with extent as per the revenue records
5 Revenue survey details of the area (Bhoomi database) is also shared for reference.
However, the actual extent and land status of
individual survey numbers may vary in the ground.
The given reference data given to enable the bidders
to get a fair idea of the landuse and extent.

Information Memorandum/ Mine Block Summery Page 3

You might also like