RC 16 Site Visit Report
RC 16 Site Visit Report
Launching Pit:
Scaffolding Supervisor Qualification ( Certificate and Level ) must be
checked and provided.
Scaffolding planks needs to be aligned in good position with the pipe
support.
Drop bar for the scaffolding must be replaced and keep apart from
the working platform.
Large size Concrete Stones should be removed from the excavation
edge.
Reallocate the control cabin from the excavation edge and keep at
least 1 meter apart.
Arrange the power electrical cables and put in proper hard
barrication with safety signage.
The electrical cable connector must be inspected and verified as per
standard.
Emergency Buzzer Alarm must be installed inside the launching pit.
Refill the gaps for concrete barricade around launching pit.
Gas Cylinders storage for Acetylene and Oxygen Cylinder must be
properly chained, locked and put in trolley.These cylinder must be
inspected before use.
Provide specific inspection for Hydraulic Power Pack ,feed pumps,
the site.
Store room.
Remove the damage electrical cables and web slings.
Inspection of full body harness is required as per ANSI standards and
certificate to be provided.
Generator.
Signage for ARC flash and *emergency switch button* must be
provided at site.
Electrical Cables inside generator are exposed and uncovered. These
must be properly covered.
2
Environmental
The Toilet must be provided for the welfare facility.
Tires and general waste must be removed from site.