The document provides a daily log of activities for road reinstatement works on Road 211 over 15 days. Excavation works were conducted for the first 7 days to repair damaged pipes and manholes. Concrete encasement of pipes was done on days 10-12 after recommendations. Compaction testing was conducted by a third party on various days. Asphalt works were completed on days 16-18 along with subbase laying and tack coat application.
The document provides a daily log of activities for road reinstatement works on Road 211 over 15 days. Excavation works were conducted for the first 7 days to repair damaged pipes and manholes. Concrete encasement of pipes was done on days 10-12 after recommendations. Compaction testing was conducted by a third party on various days. Asphalt works were completed on days 16-18 along with subbase laying and tack coat application.
The document provides a daily log of activities for road reinstatement works on Road 211 over 15 days. Excavation works were conducted for the first 7 days to repair damaged pipes and manholes. Concrete encasement of pipes was done on days 10-12 after recommendations. Compaction testing was conducted by a third party on various days. Asphalt works were completed on days 16-18 along with subbase laying and tack coat application.
The document provides a daily log of activities for road reinstatement works on Road 211 over 15 days. Excavation works were conducted for the first 7 days to repair damaged pipes and manholes. Concrete encasement of pipes was done on days 10-12 after recommendations. Compaction testing was conducted by a third party on various days. Asphalt works were completed on days 16-18 along with subbase laying and tack coat application.
DATE No. OF DAYS ACTIVITIES EQUIPMENTS MANPOWER BUYERS ENGINEERS REMARKS
2 nos. Excavator 4 Operators 16-Oct-22 Day 1 Excavation 1 no. Loader 4 Labor 1 no. Jack Hammer 1 Supervisor 2 nos. Excavator 4 Operators It was found out that the Manhole has 17-Oct-22 Day 2 Excavation 1 no. Loader 4 Labor many unclose holes. 1 no. Jack Hammer 1 Supervisor 2 nos. Excavator 4 Operators The RCP pipe found detached joints 18-Oct-22 Day 3 Excavation 1 no. Loader 4 Labor and cracks connected to the road side 1 no. Jack Hammer 1 Supervisor gully. 2 nos. Excavator 4 Operators 19-Oct-22 Day 4 Excavation 1 no. Loader 4 Labor 1 no. Jack Hammer 1 Supervisor 2 nos. Excavator 4 Operators The Field Density Test (FDT) has been Backfilling & 1 no. Loader 4 Labor conducted by Third Party Soil testing 20-Oct-22 Day 5 Compaction 1 no. 1 Ton Vibratory Roller 1 Supervisor (Kuwaiti-Lebanese). Reports are in separate attachment. 1 no. Plate Compactor 2 nos. Excavator 4 Operators The Field Density Test (FDT) has been Backfilling & 1 no. Loader 4 Labor conducted by Third Party Soil testing 21-Oct-22 Day 6 Compaction 1 no. 1 Ton Vibratory Roller 1 Supervisor (Kuwaiti-Lebanese). Reports are in separate attachment. 1 no. Plate Compactor Manhole & RCP pipe 1 No. Mason Repair works with photos are in 22-Oct-22 Day 7 repair 1 No. Labor separate attachment. Manhole & RCP pipe 1 No. Mason Repair works with photos are in 23-Oct-22 Day 8 repair 1 No. Labor separate attachment. 2 nos. Excavator 4 Operators The Field Density Test (FDT) has been Backfilling & 1 no. Loader 4 Labor conducted by Third Party Soil testing 24-Oct-22 Day 9 Compaction 1 no. 1 Ton Vibratory Roller 1 Supervisor (Kuwaiti-Lebanese). Reports are in separate attachment. 1 no. Plate Compactor 1 No. Mason Due to patches to the damage pipes, it Manhole & RCP pipe 1 No. Labor is recommended that concrete 25-Oct-22 Day 10 repair encasement shall be done to protect the pipe 2 Labor The Field Density Test (FDT) has been Concrete pouring of 1 Mason conducted by Third Party Soil testing 26-Oct-22 Day 11 pipe encasement 1 Supervisor (Kuwaiti-Lebanese). Reports are in separate attachment. 2 nos. Excavator 4 Labor The Field Density Test (FDT) has been Backfilling work for pipe 1 no. Loader 1 Supervisor conducted by Third Party Soil testing 27-Oct-22 Day 12 encasement 1 no. 1 Ton Vibratory Roller 1 Operator (Kuwaiti-Lebanese). Reports are in 1 no. Plate Compactor separate attachment. 28-Oct-22 Day 13 No Work
29-Oct-22 Day 14 No Work
30-Oct-22 Day 15 No Work
Subbase Laying / 1 no Grader 4 Operator The Field Density Test (FDT) has been Application of Tack 2 no. Loader 7 Labor conducted by Third Party Soil testing 31-Oct-22 Day 16 Coat and side walk 1 no. 1 Ton Vibratory Roller 1 Supervisor (Kuwaiti-Lebanese). Reports are in repairing 1 no. 10 Ton Vibratory Roller 3 Mason separate attachment. 1 nos. Asphalt paver 4 Operator Asphalt Work (Type 1 1 no. Loader 12 Labor 1-Nov-22 Day 17 Conbined Group Subcontractor 9cm and Type 2 - 6cm) 1 no. 10 Ton Vibratory Roller 1 Supervisor 1 no. Pneumatic tire roller 1 nos. Asphalt paver 4 Operator Asphalt Work (Type 3) 1 no. Loader 12 Labor 2-Nov-22 Day 18 Conbined Group Subcontractor - 5cm 1 no. 10 Ton Vibratory Roller 1 Supervisor 1 no. Pneumatic tire roller