Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 35

CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1-foreman
4-labor

Equipment Use:
 none

Activities:
 site clearing and grubbing
 building site cover-up
 lay-outing

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
3-skilled
2-labor

Equipment Use:
 electric bar cutter

Activities:
 excavation of the foundation
 fabrication of formwork
 fabrication of footing and column reinforcement rebar

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
4-skilled
2-labor
1-compactor operator

Equipment Use:
 Plate compactor
 electric bar cutter

Activities:
 excavating work on the foundation continues
 sand or gravel bedding
 continuation of footing and column reinforcement rebar fabrication

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
4-skilled
2-labor

Equipment Use:
 electric bar cutter
 manual bar cutter

Activities:
 continuation of footing reinforcement rebar fabrication
 fabrication of tie beam reinforcement rebar
 installation of fabricated rebar for footings and columns

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
4-skilled
5-labor

Equipment Use:
 none

Activities:
 installation of fabricated rebar for tie beam
 concrete pouring for footings

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
4-skilled
3-labor

Equipment Use:
 none

Activities:
 concrete pouring for tie beam
 concrete pouring for footings is still on-going

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
4-skilled
3-labor

Equipment Use:
 none

Activities:
 concrete pouring for tie beam is still on-going
 concrete pouring for column is still on-going

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
2-skilled
3-labor

Equipment Use:
 none

Activities:
 concrete hollow blocks laying
 fabrication of roof beam reinforcement rebar

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
2-skilled
3-labor

Equipment Use:
 none

Activities:
 continuation of laying of concrete hollow blocks
 continuation of roof beam reinforcement rebar fabrication

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
2-skilled
3-labor

Equipment Use:
 none

Activities:
 continuation of laying of concrete hollow blocks
 continuation of roof beam reinforcement rebar fabrication

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
2-skilled
3-labor

Equipment Use:
 none

Activities:
 continuation of laying of concrete hollow blocks
 continuation of roof beam reinforcement rebar fabrication

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
4-skilled
2-labor

Equipment Use:
 none

Activities:
 continuation of laying of concrete hollow blocks
 installation of fabricated rebar for roof beam

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
4-skilled
2-labor

Equipment Use:
 none

Activities:
 continuation of laying of concrete hollow blocks
 installation of fabricated rebar for roof beam

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
4-skilled
2-labor

Equipment Use:
 none

Activities:
 continuation of laying of concrete hollow blocks
 installation of fabricated rebar for roof beam

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
4-skilled
2-labor

Equipment Use:
 none

Activities:
 continuation of laying of concrete hollow blocks
 concrete pouring for roof beam

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
4-skilled
2-labor

Equipment Use:
 none

Activities:
 continuation of laying of concrete hollow blocks
 concrete pouring for roof beam

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
5-skilled
4-labor

Equipment Use:
 grinder

Activities:
 continuation of laying of concrete hollow blocks
 excavation for septic tank
 fabrication of trusses

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
5-skilled
4-labor

Equipment Use:
 grinder

Activities:
 excavation for septic tank still on-going
 fabrication of trusses still on-going

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
5-skilled
4-labor

Equipment Use:
 grinder

Activities:
 laying of concrete hollow blocks for septic tank
 fabrication of trusses still on-going
 laying of reinforcement rebar for slab still on-going
 plastering of interior walls

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
5-skilled
4-labor

Equipment Use:
 grinder
 welding machine

Activities:
 fabrication of formworks for septic tank cover and manhole
 installation of trusses
 pouring of concrete slab
 plastering of interior walls

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
3-skilled
4-labor

Equipment Use:
 welding machine

Activities:
 installation of roofing
 pouring of concrete slab still ongoing
 plastering of interior walls

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
3-skilled
4-labor

Equipment Use:
 welding machine

Activities:
 installation of roofing
 plastering of exterior walls

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
3-skilled
4-labor

Equipment Use:
 welding machine

Activities:
 installation of roofing
 plastering of exterior walls
 installation of waterline

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
5-skilled
4-labor

Equipment Use:
 welding machine

Activities:
 installation of roofing
 plastering of exterior walls
 installation of ceiling

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
4-skilled
3-labor

Equipment Use:
 welding machine
 grinder

Activities:
 installation of electrical pipes and wires
 installation of plumbing fixtures
 installation of ceiling
 plastering of exterior walls

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Sea
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1-engr
1--foreman
4-skilled
3-labor

Equipment Use:
 welding machine
 grinder

Activities:
 installation of electrical pipes and wires
 installation of plumbing fixtures
 plastering of exterior walls
 installation of ceiling

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
4-skilled
2-labor

Equipment Use:
 tile cutter
 grinder

Activities:
 painting work for exterior walls
 installation of tiles

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
3-skilled
2-labor

Equipment Use:
 tile cutter
 grinder

Activities:
 painting work for exterior walls
 installation of tiles

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
3-skilled
2-labor

Equipment Use:
 tile cutter
 grinder

Activities:
 painting work for interior walls
 installation of tiles

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
3-skilled
2-labor

Equipment Use:
 none

Activities:
 painting work for interior walls
 installation of Doors and Windows

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
3-skilled
2-labor

Equipment Use:
 none

Activities:
 painting work for interior walls
 installation of Doors and Windows

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
3-skilled

Equipment Use:
 none

Activities:
 painting work for interior walls
 installation of grills for Windows

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
3-skilled

Equipment Use:
 none

Activities:
 installation of special steel railings
 installation of grills for Windows

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET

Building Permit No.:


Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales

Date:
Weather: am:sunny
pm:sunny

Manpower Organization:
1--foreman
2-skilled

Equipment Use:
 none

Activities:
 clearing of site

(if construction is
Undertaken by contract)

Prepared by: Submitted by:

______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales
Owner : Maria Fe A. Peaker

CONSTRUCTION
LOGBOOK SHEET

You might also like