Construction Logbook Sheet
Construction Logbook Sheet
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1-foreman
4-labor
Equipment Use:
none
Activities:
site clearing and grubbing
building site cover-up
lay-outing
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
3-skilled
2-labor
Equipment Use:
electric bar cutter
Activities:
excavation of the foundation
fabrication of formwork
fabrication of footing and column reinforcement rebar
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
4-skilled
2-labor
1-compactor operator
Equipment Use:
Plate compactor
electric bar cutter
Activities:
excavating work on the foundation continues
sand or gravel bedding
continuation of footing and column reinforcement rebar fabrication
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
4-skilled
2-labor
Equipment Use:
electric bar cutter
manual bar cutter
Activities:
continuation of footing reinforcement rebar fabrication
fabrication of tie beam reinforcement rebar
installation of fabricated rebar for footings and columns
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
4-skilled
5-labor
Equipment Use:
none
Activities:
installation of fabricated rebar for tie beam
concrete pouring for footings
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
4-skilled
3-labor
Equipment Use:
none
Activities:
concrete pouring for tie beam
concrete pouring for footings is still on-going
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
4-skilled
3-labor
Equipment Use:
none
Activities:
concrete pouring for tie beam is still on-going
concrete pouring for column is still on-going
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
2-skilled
3-labor
Equipment Use:
none
Activities:
concrete hollow blocks laying
fabrication of roof beam reinforcement rebar
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
2-skilled
3-labor
Equipment Use:
none
Activities:
continuation of laying of concrete hollow blocks
continuation of roof beam reinforcement rebar fabrication
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
2-skilled
3-labor
Equipment Use:
none
Activities:
continuation of laying of concrete hollow blocks
continuation of roof beam reinforcement rebar fabrication
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
2-skilled
3-labor
Equipment Use:
none
Activities:
continuation of laying of concrete hollow blocks
continuation of roof beam reinforcement rebar fabrication
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
4-skilled
2-labor
Equipment Use:
none
Activities:
continuation of laying of concrete hollow blocks
installation of fabricated rebar for roof beam
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
4-skilled
2-labor
Equipment Use:
none
Activities:
continuation of laying of concrete hollow blocks
installation of fabricated rebar for roof beam
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
4-skilled
2-labor
Equipment Use:
none
Activities:
continuation of laying of concrete hollow blocks
installation of fabricated rebar for roof beam
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
4-skilled
2-labor
Equipment Use:
none
Activities:
continuation of laying of concrete hollow blocks
concrete pouring for roof beam
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Building Permit No.:
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
4-skilled
2-labor
Equipment Use:
none
Activities:
continuation of laying of concrete hollow blocks
concrete pouring for roof beam
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
5-skilled
4-labor
Equipment Use:
grinder
Activities:
continuation of laying of concrete hollow blocks
excavation for septic tank
fabrication of trusses
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
5-skilled
4-labor
Equipment Use:
grinder
Activities:
excavation for septic tank still on-going
fabrication of trusses still on-going
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
5-skilled
4-labor
Equipment Use:
grinder
Activities:
laying of concrete hollow blocks for septic tank
fabrication of trusses still on-going
laying of reinforcement rebar for slab still on-going
plastering of interior walls
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
5-skilled
4-labor
Equipment Use:
grinder
welding machine
Activities:
fabrication of formworks for septic tank cover and manhole
installation of trusses
pouring of concrete slab
plastering of interior walls
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
3-skilled
4-labor
Equipment Use:
welding machine
Activities:
installation of roofing
pouring of concrete slab still ongoing
plastering of interior walls
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
3-skilled
4-labor
Equipment Use:
welding machine
Activities:
installation of roofing
plastering of exterior walls
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
3-skilled
4-labor
Equipment Use:
welding machine
Activities:
installation of roofing
plastering of exterior walls
installation of waterline
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
5-skilled
4-labor
Equipment Use:
welding machine
Activities:
installation of roofing
plastering of exterior walls
installation of ceiling
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
4-skilled
3-labor
Equipment Use:
welding machine
grinder
Activities:
installation of electrical pipes and wires
installation of plumbing fixtures
installation of ceiling
plastering of exterior walls
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Sea
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1-engr
1--foreman
4-skilled
3-labor
Equipment Use:
welding machine
grinder
Activities:
installation of electrical pipes and wires
installation of plumbing fixtures
plastering of exterior walls
installation of ceiling
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
4-skilled
2-labor
Equipment Use:
tile cutter
grinder
Activities:
painting work for exterior walls
installation of tiles
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
3-skilled
2-labor
Equipment Use:
tile cutter
grinder
Activities:
painting work for exterior walls
installation of tiles
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
3-skilled
2-labor
Equipment Use:
tile cutter
grinder
Activities:
painting work for interior walls
installation of tiles
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
3-skilled
2-labor
Equipment Use:
none
Activities:
painting work for interior walls
installation of Doors and Windows
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
3-skilled
2-labor
Equipment Use:
none
Activities:
painting work for interior walls
installation of Doors and Windows
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
3-skilled
Equipment Use:
none
Activities:
painting work for interior walls
installation of grills for Windows
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
3-skilled
Equipment Use:
none
Activities:
installation of special steel railings
installation of grills for Windows
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
CONSTRUCTION LOGBOOK SHEET
Date:
Weather: am:sunny
pm:sunny
Manpower Organization:
1--foreman
2-skilled
Equipment Use:
none
Activities:
clearing of site
(if construction is
Undertaken by contract)
______________________________ ____________________________
Contractor Civil Engineer
Contractor’s License no.: _________ In-Charge of Construction
Date Issued:____________________ Sign and Seal
Project: KITCHENETTE
Location: Brgy. Pundakit, San Antonio, Zambales
Owner : Maria Fe A. Peaker
CONSTRUCTION
LOGBOOK SHEET