Professional Documents
Culture Documents
Contract Management Practices and Prospectives
Contract Management Practices and Prospectives
net/publication/366005674
CITATIONS
2 authors, including:
Samir Bhattarai
Pokhara University
2 PUBLICATIONS 0 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Replacement of the Disastrous Tuins in Nepal: Auto Mechanized Bridge View project
All content following this page was uploaded by Samir Bhattarai on 05 December 2022.
BY
SAMIR BHATTARAI
MSC. CONSTRUCTION MANAGEMENT
POKHARA UNIVERSITY
Contract
Offer
Acceptance
Consideration
Intention to create legal relation
Contract shall be:
1. Fair
2. Clear, consistent & retrievable
3. Foresight
Once contract is signed, parties are to follow contract terms. There is no going back.
EOT (Extension of Time)
There is always written “Intended Completion date” in contract.
The Engineer (Consultant) can recommend but has no power to grant Extension of
Time to the Contractor.
Time extension issue, which was to be controlled within the frame of contract,is taken
up in PPR (Public Procurement Regulation) and its ammendments.
Work Schedule (Contract Duration) and EOT. How duration is fixed in a contract ??
(CPM/PERT method and DOR guidelines)
Figure : Cumulative cost vs Time
Extension of intended/initial completion date of contract due to delays is EOT.
EOT is granted mainly when
❑ VO ( Variation Order) is issued.
❑ Compensation event occurs like:
1. Site positioning.
2. Employer requests to change schedule.
3. Delay by client to give specification and drawings.
4. Client wastes in unnecessary tests.
5. Unforeseen site conditions (Ground conditions).
6. Delayed due to other Contractor and Publid authorities.
7. Delayed Advanced Payment (Mobilization).
8. Effect of employers’s risk.
Delays:
❖ Excusable Delay
❖ Unexcusable Delay
Excusable Delay: Delay beyond the fault of either the contractor or the owner; or not
caused by contractor negligence for which Time compensation is to be provided.
To show:
FIDIC | Construction Contract (Red Book) Edition
FIDIC | Construction Contract MDB Harmonised Edition
PPMO:
Public Procurement Monitoring Office (PPMO) has the vision to establish a
centralized e-Government Procurement (e-GP) System for nation wide public
procurement management
Functions:
Advise on public procurement matters for public procurement proceedings.
Establish and maintain websites dedicated to public procurement management.
Develop and Issue the Standard Bidding Documents for Civil Works, Goods and
Consultancy.
To show :
Tender Documents (All package by PPMO)