ANALISA HARGA SATUAN

PROYEK : NEW EAST 2 MARKETING GALLERY


PEKERJAAN : INSTALASI ELEKTRONIK
TANGGAL : 19 AGUSTUS 2021

INSTALASI TITIK SMOKE DETECTOR & ROR


Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah
1 Kabel NYA 2 x 1 x 1,5 mm2 13.00 m 7,500 97,500
2 Conduit PVC Ø 20 mm2 12.00 m 4,750 57,000
3 Flexibel Ø 20 mm2 1.00 m 6,500 6,500
4 Sock 4.00 bh 1,100 4,400
5 Klem 12.00 bh 950 11,400
6 T-doss 1.00 bh 6,100 6,100
7 Material bantu 1.00 ls 9,500 9,500
8 Alat bantu 1.00 ls 3,000 3,000
195,400
9 Upah pasang 1.00 ls 45,000 45,000
Sub Total 240,400
Sub Total + Profit 10% 264,440
TOTAL 264,500

INSTALASI TITIK PUSH BUTTON, ALARM BELL, INDICATOR LAMP


Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah
1 Kabel NYA 2 x 1 x 1,5 mm2 25.00 m 7,500 187,500
2 Conduit PVC Ø 20 mm2 24.00 m 4,750 114,000
3 Flexibel Ø 20 mm2 1.00 m 6,500 6,500
4 Sock 8.00 bh 1,100 8,800
5 Klem 24.00 bh 950 22,800
6 T-doss 1.00 bh 6,100 6,100
7 Bobok dan Plester 2.00 m 7,500 15,000
8 Material bantu 1.00 ls 15,300 15,300
9 Alat bantu 1.00 ls 5,000 5,000
381,000
10 Upah pasang 1.00 ls 45,000 45,000
Sub Total 426,000
Sub Total + Profit 10% 468,600
TOTAL 468,600

INSTALASI TITIK COLUMN SPEAKER


Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah
1 Kabel NYYHY 2 x 1,5 mm2 19.00 m 18,900 359,100
2 Conduit PVC Ø 20 mm2 18.00 m 4,750 85,500
3 Sock 6.00 bh 1,100 6,600
4 Klem 18.00 bh 950 17,100
5 T-doss 1.00 bh 6,100 6,100
6 Material bantu 1.00 ls 15,300 15,300
7 Alat bantu 1.00 ls 7,500 7,500
497,200
8 Upah pasang 1.00 ls 45,000 45,000
Sub Total 542,200
Sub Total + Profit 10% 596,420
TOTAL 596,500

INSTALASI TITIK CEILING SPEAKER & VOLUME CONTROL


Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah
1 Kabel NYMHY 2 x 1,5 mm2 10.00 m 11,200 112,000
2 Conduit PVC Ø 20 mm2 9.00 m 4,750 42,750
3 Sock 3.00 bh 1,100 3,300
4 Klem 9.00 bh 950 8,550
5 T-doss 1.00 bh 6,100 6,100
6 Material bantu 1.00 ls 10,500 10,500
7 Alat bantu 1.00 ls 6,500 6,500
189,700
8 Upah pasang 1.00 ls 45,000 45,000
Sub Total 234,700
Sub Total + Profit 10% 258,170
TOTAL 258,200

INSTALASI TITIK TELEPON


Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah
1 Kabel ITC 2 x 2 x 0,6 mm2 25.00 m 3,900 97,500
2 Conduit PVC Ø 20 mm2 24.00 m 4,750 114,000
3 Sock 15.00 bh 1,100 16,500
4 Klem 24.00 bh 950 22,800
5 T-doss 1.00 bh 6,100 6,100
6 Bobok dan Plester 4.00 m 7,500 30,000
7 Material bantu 1.00 ls 15,300 15,300
8 Alat bantu 1.00 ls 12,400 12,400
314,600
9 Upah pasang 1.00 ls 45,000 45,000
Sub Total 359,600
Sub Total + Profit 10% 395,560
TOTAL 395,600

INSTALASI TITIK DATA & WIFI


Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah
1 Kabel UTP CAT 6 35.00 m 7,400 259,000
2 Conduit PVC Ø 20 mm2 34.00 m 4,750 161,500
3 Sock 15.00 bh 1,100 16,500
4 Klem 34.00 bh 950 32,300
5 T-doss 1.00 bh 6,100 6,100
6 Bobok dan Plester 4.00 m 7,500 30,000
7 Material bantu 1.00 ls 15,300 15,300
8 Alat bantu 1.00 ls 12,400 12,400
533,100
9 Upah pasang 1.00 ls 45,000 45,000
Sub Total 578,100
Sub Total + Profit 10% 635,910
TOTAL 636,000

INSTALASI TITIK CCTV


Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah
1 Kabel RG-59 + power 35.00 m 4,500 157,500
2 Conduit PVC Ø 20 mm2 34.00 m 4,750 161,500
3 Sock 12.00 bh 1,100 13,200
4 Klem 34.00 bh 950 32,300
5 Material bantu 1.00 ls 15,300 15,300
6 Alat bantu 1.00 ls 12,600 12,600
392,400
7 Upah pasang 1.00 ls 58,800 58,800
Sub Total 451,200
Sub Total + Profit 10% 496,320
TOTAL 496,400