This document provides a cost estimate for electrical installation work on the New East 2 Marketing Gallery project. It includes itemized estimates for installing smoke detectors, push buttons, speakers, telephones, data/WiFi, and CCTV. The totals for each installation type range from Rp264,500 for smoke detectors to Rp636,000 for data/WiFi installation. The document gives detailed estimates for materials, equipment, and labor costs for each installation point and type.
This document provides a cost estimate for electrical installation work on the New East 2 Marketing Gallery project. It includes itemized estimates for installing smoke detectors, push buttons, speakers, telephones, data/WiFi, and CCTV. The totals for each installation type range from Rp264,500 for smoke detectors to Rp636,000 for data/WiFi installation. The document gives detailed estimates for materials, equipment, and labor costs for each installation point and type.
This document provides a cost estimate for electrical installation work on the New East 2 Marketing Gallery project. It includes itemized estimates for installing smoke detectors, push buttons, speakers, telephones, data/WiFi, and CCTV. The totals for each installation type range from Rp264,500 for smoke detectors to Rp636,000 for data/WiFi installation. The document gives detailed estimates for materials, equipment, and labor costs for each installation point and type.
PEKERJAAN : INSTALASI ELEKTRONIK TANGGAL : 19 AGUSTUS 2021
INSTALASI TITIK SMOKE DETECTOR & ROR
Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah 1 Kabel NYA 2 x 1 x 1,5 mm2 13.00 m 7,500 97,500 2 Conduit PVC Ø 20 mm2 12.00 m 4,750 57,000 3 Flexibel Ø 20 mm2 1.00 m 6,500 6,500 4 Sock 4.00 bh 1,100 4,400 5 Klem 12.00 bh 950 11,400 6 T-doss 1.00 bh 6,100 6,100 7 Material bantu 1.00 ls 9,500 9,500 8 Alat bantu 1.00 ls 3,000 3,000 195,400 9 Upah pasang 1.00 ls 45,000 45,000 Sub Total 240,400 Sub Total + Profit 10% 264,440 TOTAL 264,500
INSTALASI TITIK PUSH BUTTON, ALARM BELL, INDICATOR LAMP
Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah 1 Kabel NYA 2 x 1 x 1,5 mm2 25.00 m 7,500 187,500 2 Conduit PVC Ø 20 mm2 24.00 m 4,750 114,000 3 Flexibel Ø 20 mm2 1.00 m 6,500 6,500 4 Sock 8.00 bh 1,100 8,800 5 Klem 24.00 bh 950 22,800 6 T-doss 1.00 bh 6,100 6,100 7 Bobok dan Plester 2.00 m 7,500 15,000 8 Material bantu 1.00 ls 15,300 15,300 9 Alat bantu 1.00 ls 5,000 5,000 381,000 10 Upah pasang 1.00 ls 45,000 45,000 Sub Total 426,000 Sub Total + Profit 10% 468,600 TOTAL 468,600
INSTALASI TITIK COLUMN SPEAKER
Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah 1 Kabel NYYHY 2 x 1,5 mm2 19.00 m 18,900 359,100 2 Conduit PVC Ø 20 mm2 18.00 m 4,750 85,500 3 Sock 6.00 bh 1,100 6,600 4 Klem 18.00 bh 950 17,100 5 T-doss 1.00 bh 6,100 6,100 6 Material bantu 1.00 ls 15,300 15,300 7 Alat bantu 1.00 ls 7,500 7,500 497,200 8 Upah pasang 1.00 ls 45,000 45,000 Sub Total 542,200 Sub Total + Profit 10% 596,420 TOTAL 596,500
INSTALASI TITIK CEILING SPEAKER & VOLUME CONTROL
Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah 1 Kabel NYMHY 2 x 1,5 mm2 10.00 m 11,200 112,000 2 Conduit PVC Ø 20 mm2 9.00 m 4,750 42,750 3 Sock 3.00 bh 1,100 3,300 4 Klem 9.00 bh 950 8,550 5 T-doss 1.00 bh 6,100 6,100 6 Material bantu 1.00 ls 10,500 10,500 7 Alat bantu 1.00 ls 6,500 6,500 189,700 8 Upah pasang 1.00 ls 45,000 45,000 Sub Total 234,700 Sub Total + Profit 10% 258,170 TOTAL 258,200
INSTALASI TITIK TELEPON
Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah 1 Kabel ITC 2 x 2 x 0,6 mm2 25.00 m 3,900 97,500 2 Conduit PVC Ø 20 mm2 24.00 m 4,750 114,000 3 Sock 15.00 bh 1,100 16,500 4 Klem 24.00 bh 950 22,800 5 T-doss 1.00 bh 6,100 6,100 6 Bobok dan Plester 4.00 m 7,500 30,000 7 Material bantu 1.00 ls 15,300 15,300 8 Alat bantu 1.00 ls 12,400 12,400 314,600 9 Upah pasang 1.00 ls 45,000 45,000 Sub Total 359,600 Sub Total + Profit 10% 395,560 TOTAL 395,600
INSTALASI TITIK DATA & WIFI
Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah 1 Kabel UTP CAT 6 35.00 m 7,400 259,000 2 Conduit PVC Ø 20 mm2 34.00 m 4,750 161,500 3 Sock 15.00 bh 1,100 16,500 4 Klem 34.00 bh 950 32,300 5 T-doss 1.00 bh 6,100 6,100 6 Bobok dan Plester 4.00 m 7,500 30,000 7 Material bantu 1.00 ls 15,300 15,300 8 Alat bantu 1.00 ls 12,400 12,400 533,100 9 Upah pasang 1.00 ls 45,000 45,000 Sub Total 578,100 Sub Total + Profit 10% 635,910 TOTAL 636,000
INSTALASI TITIK CCTV
Bahan dan Material Instalasi Vol. Per Titik Sat. Harga Satuan Jumlah 1 Kabel RG-59 + power 35.00 m 4,500 157,500 2 Conduit PVC Ø 20 mm2 34.00 m 4,750 161,500 3 Sock 12.00 bh 1,100 13,200 4 Klem 34.00 bh 950 32,300 5 Material bantu 1.00 ls 15,300 15,300 6 Alat bantu 1.00 ls 12,600 12,600 392,400 7 Upah pasang 1.00 ls 58,800 58,800 Sub Total 451,200 Sub Total + Profit 10% 496,320 TOTAL 496,400