V1.3E 2008.11.17 Add load balance abnormal function C.Y.Jeong S.W.Jeong J.Y.Chung
V1.4E 2009.02.02. Add troubles and correcting measures C.Y.Jeong S.W.Jeong J.Y.Chung
V1.6E 2010.07.08. Changed Operating Temperature follow by ENV Test Report C.Y.Jeong S.W.Jeong J.Y.Chung
TABLE OF CONTENT
1. SPECIFICATIONS........................................................................................................... 3
1.1. APPLICATIONS ...................................................................................................................3
1.2. GENERAL SPECIFICATIONS ..............................................................................................4
2. SYSTEM CONSTRUCTION ............................................................................................ 5
2.1. DIAGRAM OF POWER MANAGEMENT CONTROL SYSTEM (FOR SHIP) ........................5
2.2. DIAGRAM OF POWER MANAGEMENT CONTROL SYSTEM ............................................6
3. SYSTEM FLOW CHARTS .............................................................................................. 7
3.1. Auto Parallel Running by Heavy Load & Pref. Trip ...........................................................8
3.2. Auto Parallel Running Cancellation by Light Load...........................................................9
3.3. Auto Changeover by BUS No Voltage .............................................................................10
3.4. Auto Changeover by BUS Abnormal ............................................................................... 11
3.5. Auto Parallel Running by ACB Trip .................................................................................12
4. INPUT / OUTPUT SPECIFICATIONS ........................................................................... 13
4.1. TERMINAL INPUT 00 .........................................................................................................13
4.2. TERMINAL INPUT 01 .........................................................................................................14
4.3. TERMINAL OUTPUT 03 .....................................................................................................15
4.4. TERMINAL OUTPUT 04 .....................................................................................................16
5. INPUT / OUTPUT REFERENCE TABLES .................................................................... 17
6. INTERNAL SETTING & ADJUSTING ........................................................................... 21
6.1. INTERNAL SETTING TABLE .............................................................................................21
6.2. Panel Switch using method ..............................................................................................22
7. DIAGNOSTIC & TROUBLES AND CORRECTING MEASURES ................................. 23
8. EXTERNAL FORM ........................................................................................................ 24
9. PRODUCT STORAGE PRECAUTIONS ....................................................................... 25
1. SPECIFICATIONS
1.1. APPLICATIONS
KT-PPC(Programmable Power Controller) optimizes the ship and ground power generation systems
and efficiently perform an active power management & control by controlling KT-ASD(Auto synchronizing
Device) and KT-PWC(Power Controller). Normally KT-PPC is designed to control 3 generators but you
can enlarge its capacity to maximum 5 generators with extension module.
AND self-diagnosis function lets you find out the cause of the errors in the case of problems, so it is
easy for you to maintain the power control system. You can build electric power control system for
various applications by modifying or changing the control program according to your system
configurations.
【 MODEL CLASSIFICATION 】
① KT-PPC (without Big Motor Starting function)
② KT-PPC-A (with Big Motor Starting function)
◈ MAIN FUNCTIONS
• Auto Parallel Running by Heavy Load & Pref. Trip
• Auto Parallel Running Cancellation by Light Load
• Auto Changeover by BUS NO Voltage
• Auto Changeover by BUS Abnormal
• Auto Parallel Running by ACB Trip
• Generator Engine Control ( Start / Stop)
• Big Motor Start Control
• Input / Output LED Display
• Self test & Error Display
• Load Balance Abnormal (RATING POWER X ±5%, DELAY TIME 120SEC.)
Item Description
2. SYSTEM CONSTRUCTION
<REMARK>
1. PWC : Generator power controller for ship.
2. Each PWC is used for controlling up to 3 generators
3. PWC can be connected up to max. 5 units by communication line.
<REMARK>
One unit of PWC used for each generator.
(Maximum of 15 units can be used)
01 (+)
AN1 No.1 GEN Power
02 (-)
03 (+)
AN2 No.2 GEN Power
04 (-)
05 (+)
AN3 No.3 GEN Power
06 (-)
07 (+)
AN4 No.4 GEN Power
08 (-)
09 (+)
AN5 No.5 GEN Power
10 (-)
11 GND
12 GND
13 F.G Frame Ground
14 F.G Frame Ground
15 Unused I
16 Unused N
17 Unused P
18 Unused U
19 Unused T
20 Unused
21 Unused 0
22 Unused 0
23 Unused
24 Unused
25 No.1 GEN Auto mode select
26 No.2 GEN Auto mode select
27 No.3 GEN Auto mode select
28 No.1 GEN Abnormal Reset
29 No.2 GEN Abnormal Reset
30 No.3 GEN Abnormal Reset
31 No.1 GEN (ENG. START SW.)
32 No.2 GEN (ENG. START SW.)
33 No.3 GEN (ENG. START SW.)
34 No.1 GEN (ENG. STOP SW.)
35 No.2 GEN (ENG. STOP SW.)
36 No.3 GEN (ENG. STOP SW.)
P(+24V) 01 COM
02 Unused
03 Unused
04 Unused
05 No.1 GEN VOLTAGE Build Up
06 No.2 GEN VOLTAGE Build Up
07 No.3 GEN VOLTAGE Build Up
08 No.1 ENG START
09 No.2 ENG START
10 No.3 ENG START
11 No.1 GEN AUTO LOAD SHIFT
12 No.2 GEN AUTO LOAD SHIFT
13 No.3 GEN AUTO LOAD SHIFT
14 No.1 1st ST'BY
15 No.2 1st ST'BY
O
16 No.3 1st ST'BY U
17 No.1 ENG STOP T
18 No.2 ENG STOP P
U
19 No.3 ENG STOP T
20 No.1 2nd ST'BY
21 No.2 2nd ST'BY 0
4
22 No.3 2nd ST'BY
23 No.1 ACB NON CLOSE
24 No.2 ACB NON CLOSE
25 No.3 ACB NON CLOSE
26 No.1 ABNORMAL TRIP
27 No.2 ABNORMAL TRIP
28 No.3 ABNORMAL TRIP
29 BIG MOTOR OUTPUT 1
30 BIG MOTOR OUTPUT 2
31 BIG MOTOR OUTPUT 3
32 LOAD BALANCE ABNORMAL
33 POWER AVAILABLE 1
34 POWER AVAILABLE 2
35 POWER AVAILABLE 3
36 ALARM OUT (System Error)
Application Comments
JP4
C-A
JP5 Communication
Method
JP6 Selection
C-B RS - 232c Serial Communication
JP7
1 ON▪ OFF
2 ON▪ OFF
4 ON▪ OFF
5 ON▪ OFF
(Remark) “ ” : Default setting value (Do not intentional modifying after purchasing)
【 VR Setting 】
VR1 : Volumes for internal power +5V range adjustment (Do not touch)
VR2 : Volumes for internal power +12v range adjustment (Do not touch)
VR3~4 : Volumes for internal power -12V range adjustment (Do not touch)
- - - - : 감소
1 2 3
+ + + + : 증가
SW3 (0~9)
SW2 (0~9)
SW1 (0~9)
Using the panel switch attached to the front, we can recognize internal each data setting value and
status.
Using method is same the following.
(The following can be applied to only KT-PPC-A type model)
※ X:0 ~ 9
As soon as you power on this product, it starts self-diagnosis function and show you the result, so it
help you not to perform a failure due to the initial system errors.
When you need to perform self-diagnosis function, just push the 'RESET' button, then it will show you
the diagnosis results. (Note : Do not push 'RESET' button while the system operate). Error messages and
trouble shooting methods of diagnosis results are explained as follows.
8. EXTERNAL FORM
1) When heavy dust or metal particles are present in the air, store it by using a cover or a package.
2) Do not store it in such an area that is subject to corrosive gases.
3) Do not sort it in such an area that is subject to direct sunlight.
4) Do not store it in such an area that is subject to ambient temperatures lower than -10℃, higher than
70℃ and relative humidity more than 90% RH.