Brief Scope: This Procedure sets out the methodology to verify effectiveness of the EPG's
Loss Prevention Program incorporating Safety Management System (SMS) at the SATORP
Project .
This document is the property of SA TORP and shall not be reproduced in any form. Copies provided by SA TORP shall only be
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SATORP and the validated version will be published on its intranet site .
Consequently, the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site. Only soft copies on the SA TORP intranet site dedicated to SA TORP QMS are considered controlled documents.
Page 1 of 10
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
ISSUER: PMT-SHE
Apr.2011
PROCEDURE for PROJECT SAFETY INDEX Rev: 00
2-PMTS-002
(PSI) AUDIT
This document is the property of SA TORP and shall not be reproduced in any form. Copies provided by SA TORP shall only be
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SA TORP and the validated version will be published on its intranet site .
Consequently, the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site. Only soft copies on the SA TORP intranet site dedicated to SA TORP QMS are considered controlled documents.
Page 2 of 10
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
ISSUER: PMT-SHE
..,..Jg..:;L.... Apr.2011
satorp PROCEDURE for PROJECT SAFETY INDEX Rev : 00
2-PMTS-002
(PSI) AUDIT
PURPOSE AND SCOPE .. ............ ... ... .. .... .. .. .... ....... ..... ....... .... ....... .... ......... ..... .. .. .... ....... ... ...4
2 DEFINITIONS/ABBREVIATIONS: ...... .... .. .... .... .... .. ..... .. ... ... .. ... .. ... .. .. .... .. ...... ..... ...... ... .... ... ...4
3 REFERENCES .............. ... ... .. .. .... ..... .... ...... ... ....... .. ....... ..... .... .. .... .. .. ... ... ... .... ..... ... ...... ..... ..... 5
4 RESPONSIBILITIES .. .. .. .. ...... ...... ... ...... .. .. ... ... .......... ..... .. .. .. .. .. ...... ..... .. .. .. ... .... ..... ...... ....... ... 5
4.1 TEAM COMPOSITION & RESPONSIBILITY ..... .. ..... ..... ... ...... ................ .. ... ..... ...... ....... 5
5 PROCEDURE .... ........ ... .. .. .... ... ... .. ..... .... ... ...... .. ........... .... ... ..... ...... ..... .. ........ ... .. .. ... .. ..... .. .. .. 7
5.1 AUDIT PROCEDURE. .. ... ... .. ........ .. ...... ... ... .... ... ..... . ...... ........... ... .. ..... ...... .. .. .... ... .. .... ... .7
5.2 SCORING ................. ..... .. ..... ..... ... .. .. .. .. ...... .. ... ... .. ... .. .......... .... ..... ... ...... ....... .. ... ..... ..... ..7
5.3 EVALUATION RATING .... .... .. .... .. .. .. .. ..... ........ ... .. ... ............... .. .. .... .... ..... ...... .. ... .... .... ....7
5.4 PSI EVALUATION SHEET ....... ... .. .. .. ........... .. ........ ... .. ...... .. .... ...... ...... .. .. .. .. .... ......... ... ...8
5.5 EXECUTION OF PSI AUDIT ...... .. ... ..... ... ....... ...... ..... .......... ........ .. ...... .. ... ... ... .. .... ..... ..... 8
5.6 REVIEW AND EVALUATION .. ...... .. ..... ... .... ... ... .. ..... .... .. ..... .. .. ... ... ...... .. ... ... .... .... .. ... ... . 10
6 ATTACHMENTS ..... .. .. ...... .. ..... .. ... ..... ... ...... .. .... ... ...... ... ..... ... .... ...... .. .. .. ..... .. .. ... ... .... .... .. .. .. . 10
This document is the property of SA TORP and shall not be reproduced in any form . Copies provided by SA TORP shall only be
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SA TORP and the validated version will be published on its intranet site.
Consequently, the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site . Only soft copies on the SA TORP intranet site dedicated to SA TORP QMS are considered controlled documents.
Page 3 of 10
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
ISSUER: PMT-SHE
Apr.2011
PROCEDURE for PROJECT SAFETY INDEX Rev : 00
2-PMTS-002
(PSI) AUDIT
SCOPE
This procedure is applicable to all SATORP designated EPC contractual work locations
including lay down Yards, Camps , Clinics, and Offices. SATORP reserves the right to
inspect camps , fabrication shops, etc. at anytime.
2 DEFINITIONS/ABBREVIATIONS:
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SA TORP and the validated version will be published on its intranet site .
Consequently. the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site. Only soft copies on the SA TORP intranet site dedicated to SA TORP QMS are considered controlled documents.
Page 4 of 10
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
. 1If
'::.. ISSUER: PMT-SHE
YJ~L.J
satorp PROCEDURE for PROJECT SAFETY INDEX
Apr.2011
Rev: 00
2-PMTS-002
(PSI) AUDIT
2.8 Needs improvement Scored "1" in the PSI Checklist. Needs improvement
is raised in the partial absence of, or the partial
failure to implement and maintain one or more
project SHE requirements or when on the basis of
audit evidence the integrity of the arrangement and
its intended effect is insufficient
2.9 Compliance Scored "2" in the PSI Checklist. Compliance is raised
in the presence of completely meeting the
requirements
2.10 Not Applicable (NA) is raised when for some reason the
requirement/s is not related or appropriate to be
audited
3 REFERENCES
4 RESPONSIBILITIES
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SATORP and the validated version will be published on its intranet site .
Consequently, the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site. Only soft copies on the SA TORP infranet site dedicated to SATORP QMS are considered controlled documents.
Page 5 of 10
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
ISSUER: PMT-SHE
""'J~L.. PROCEDURE for PROJECT SAFETY INDEX
Apr.2011
satorp Rev; 00
2-PMTS-002
(PSI) AUDIT
UJ~~ ~III!
satorp PROCEDURE for PROJECT SAFETY INDEX
Apr.2011
Rev: 00
2-PMTS-002
(PSI) AUDIT
5 PROCEDURE
5.2 SCORING
The monthly PSI Compliance Percentage of the audited package shall be computed
using the following principle:
1st PSI Weekly Audit Result for the month = Wk #1 Score x 20%
nd
2 PSI Weekly Audit Result for the month =Wk #2 Score x 20%
3'd PSI Weekly Audit Result for the month = Wk #3 Score x 20%
PSI Monthly Audit Result = Wk #4 Score x 40%
This document is the property of SA TORP and shall not be reproduced in any form. Copies provided by SATORP shall only be
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SATORP and the validated version will be published on its intranet site.
Consequently, the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site. Only soft copies on the SA TORP intranet site dedicated to SA TORP QMS are considered controlled documents .
Page 7 of 10
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
ISSUER: PMT-SHE
""'J~L.... PROCEDURE for PROJECT SAFETY INDEX
Apr.2011
satorp Rev: 00
2-PMTS-002
(PSI) AUDIT
5.5.1.1 Respective EPC Management of the Package shall arrange and facilitate
the accomplishment of the Weekly PSI Audit. Cycle of areas for audit shall
conform to Attachment 4 of this Procedure .
5.5.1 .2 The Package Management Representative which shall vary weekly shall
take the lead of Weekly PSI Audit. SATORP SHE Representative shall
only act as member of the Weekly PSI Audit Team.
5.5 .1.3 Prior to the commencement of the Weekly PSI Audit, briefing shall be held
by the Audit Lead clarifying the following items:
1) Coverage of Audit
2) Previous audit findings including selection of areas (max 8 elements)
for verification.
3) Where to convene for close out and at what time
4) Responsibilities (i.e. who will consolidate the findings, who will prepare
the report, etc.)
5) Report submission
This document is the property of SA TORP and shall not be reproduced in any form . Copies provided by SA TORP shall only be
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SATORP and the validated version will be published on its intranet site.
Consequently, the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site. Only soft copies on the SA TORP intranet site dedicated to SA TORP QMS are considered controlled documents.
Page 8 of 10
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
ISSUER: PMT-SHE
YJ~L.. Apr.2011
satorp PROCEDURE for PROJECT SAFETY INDEX Rev: 00
2-PMTS-002
(PSI) AUDIT
5.5 .1.4 The Weekly PSI Audit result shall be signed by all the auditing members
mentioned in 4.1.1 .1
nd
5.5.1.5 Weekly PSI Audit result shall be submitted no later than the 2 working
day after the audit conducted. Report shall be submitted to SATORP SHE
Department through the SATORP Package SHE Representative.
5.5.1 .6 One (1) percent from the Total Weekly PSI Result shall also automatically
be deducted for the non-participation of any Audit Team members
identified in 4.1.1.1
5.5.2.1 PSI Audit schedule shall be sent to all Package Managers every Second
Week of Each Month by PMT SHE Department The rotation for area
inspection shall follow the cycle indicated in Attachment 5.
5.5.2 .2 An opening meeting shall be carried out prior to the commencement of the
audit As a minimum, the following items shall be covered by the Leader of
the Audit during the opening meeting:
1) Introduction of participants (15-min. presentation by an EPC to Project
Status and corrective action taken from previous Monthly PSI)
2) Purpose and scope of the audit
3) Schedule or sequence of PSI Audit
4) Minimum PPE needed
5) Document Review and validation of records
5.5.2.3 Audits are carried out against all the requirements listed in Attachment 1
Checklist The sequence of the audit shall follow Number 3 of 5.5.2.2 as
discussed during the opening meeting. Any changes in the audit scope or
sequence shall be at the discretion of the Audit Team Leader.
5.5.2.4 A close out meeting shall be conducted to consolidate all the results of the
audit Venue and time for the Audit Team Members to convene for close
out meeting shall be clearly discussed as part of the audit sequence in the
opening meeting mentioned in Statement 3 of Clause 5.5.2.2 . The scoring
for both Weekly and Monthly PSI Audit shall follow procedure in Clause
5.3.
5.5.2.5 SATORP PMT SHE Representative shall input audit findings and assign
initial score against each requirement of the PSI Checklist.
This document is the property of SA TORP and shall not be reproduced in any form. Copies provided by SATORP shall only be
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SATORP and the validated version will be published on its intranet site.
Consequently, the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site. Only soft copies on the SA TORP intranet site dedicated to SA TORP QMS are considered controlled documents.
Page 9 of 10
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
ISSUER: PMT-SHE
~J~~ ~llt
satorp PROCEDURE for PROJECT SAFETY INDEX
Apr.2011
Rev: 00
2-PMTS-002
(PSI) AUDIT
5.5.2 .6 For any repeated findings , one (1) percent from the total of the particular
PSI Section shall be automatically deducted.
5.5.2.7 One (1) percent from the Total Monthly PS I Result shall also automatically
deducted for the non-participation of any Audit Team members identified in
4.1 .1.1
5.5.3 Issuance of the Monthly PSI Compliance Percentage (Clause 5.2) to the Package
is on the 10th day of the following month .
The result of the PSI Compliance Audit shall be part of the management review of
the package.
6 ATTACHMENTS
This document is the property of SA TORP and shall not be reproduced in any form. Copies provided by SA TORP shall only be
disclosed or provided to third parties insofar as relevant for the operations of SA TORP and the information provided in this document
The content of this document will be regularly updated by SATORP and the validated version will be published on its intranet site .
Consequently, the validity of hard copies of this document must be verified prior to its use against the version on the SA TORP
intranet site. Only soft copies on the SA TORP intranet site dedicated to SA TORP QMS are considered controlled documents.
Page 10 of 10