DETAILED AND ABSTRACT ESTIMATE FOR BRIDGE MRS.

CHINNAMMA, PULAVELIL (H),


PERIYAPURAM , MUVATTUPUZHA IN RE-SURVEY NO 492/7-1,492/8,492/7-2

Sl No SPECIFICATIONS NO L(m) B(m) H(m) QTY. UNIT RATE(Rs) AMOUNT (RS)


1 Foundation work
Earth work in excavation by mechanical means (Hydraulic excavator)/
manual means over areas (exceeding 30 cm in depth, 1.5 m in width as
well as 10 sqm on plan) including getting out and disposal of excavated
earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-incharge.
1
3
RUBBLE FOUNDATION 2 4.5 0.5 2.089.36 m
3
Extra 1m
3
Total 10.36 m
Say 11 m3 2710 29810
Random rubble masonry with hard stone in foundation including
levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12
graded stone aggregate 20 mm nominal size) upto bride slab bottom
2 3
RR 2 4.5 0.5 2.08 9.36 m
3
Total 13.50 m
3
Say 14 m 6120 85680
Providing and laying RCC 1:1.5:3 (M20) using 20mm for concrete slab bridge broken stone

3
Concrete Slab 1 3.20 4 0.3 3.84 m3
3
Total 4.00 m 9763.8 39055.2
Centering and shuttering including strutting, propping etc. and removal
of form forconcrete slab
4 concrete slab bottom 1 4 2.3 1 9.20 m2
concrete slab 2 3.2 0.3 1 1.92 m2
Total 12.00 m2 693.05 8316.6
Steel reinforcement for R.C.C. work ready to use "cut and bend"
rebars of approved make from factory/workshop to construction
5
slab 550.00 kg
Total 550 kg 77 42350
Providing and laying screed 1:4:8 using 20mm broken stone including cost of all materials and labours
for road
6
concrete slab road 1 4 3.2 0.05 0.64 m3
Total 1 m3 5000 5000
TOTAL Rs 210212
TOTAL (ROUNDED) Rs 220000
ROUND OFF: TWO LAKHS TWENTY THOUSAND ONLY