1|
Agenda
2|
Lime Stabilisation
3|
Why did TMR invest
on research, trial and
establish a new
approach to Lime
Stabilisation
4|
Expansive soils in Queensland
• Information supplied by
the Department of Natural
Resources, Queensland
and adapted from the
Atlas of Soils, CSIRO.
5|
6
7|
Pavement failures due to expansive
soils
8|
9
9|
10
10 |
11
11 |
12 |
Black soil subgrade characteristics
13 |
What is lime stabilisation
15 |
Limestone
16 |
Chemical reactions
• Burning
! CaCO3 + heat (>1000°C) -> CaO + CO2
• Slaking
! CaO + H2O -> Ca(OH)2 + heat
• Pozzolanic reation
! Ca++ + OH- + soluble clay silica -> Calcium Silicate Hydrate
(CSH)
! CA++ + OH- + soluble clay alumina -> Calcium Aluminate Hydrate
(CAH).
17 |
Trial section (windrow to stabilise lower layer)
18 |
What did TMR
achieve from
research in Lime
Stabilisation
19 |
Road Foundation
Resilience to
Flooding
20 |
Oakey Pittsworth Road Project
22 |
23 |
Significant increase
to strength of Road
Foundations
24 |
Cunningham Highway, Freestone
Creek – Lime stabilisation
• Subgrade stabilisation to widen existing road
• Construction 1998 (13 years old)
• Wearing surface 100mm asphalt
• After seven years (2005), further 100mm asphalt
• Pavement performing very well.
25 |
26 |
Flinders Highway Lime Stabilised Subgrade (5% Lime)
27 | Type footer details here | May 15, 2015
Toowoomba-Cecil Plains Road Floodway FB/CMSB/LSS
28 | Type footer details here | May 15, 2015
Unconfined Compressive Strength (UCS)
9
8.1 MPa
8
2 Top
7
2 Bot
5.5 MPa 6 Mid
6
5
MPa
4
2.9 MPa
3
0
Core No.
29 |
Documentation of
findings, Technology
Transfer and Project
Linked Training
30 |
Transport and Main Roads Specification
MRS07A
April 2011
31 |
Transport and Main Roads Technical Standard
MRTS07A
April 2011
32 |
Technical Note issue No.39
33 |
Testing protocol for lime stabilisation
34 |
Structural design of granular
pavement depth over lime stabilised
subgrade
TMR vs Austroads
35 |
Comparison of required granular
cover over lime-stabilised subgrade
36 |
Benefits of lime stabilised subgrade
40 |
What is foamed bitumen?
42 |
42
Binder Requirements
Class 170 Bitumen – 3.0%
• Equivalent to Pen 80 – 100
• Inclusion of a bitumen foaming agent
Hydrated Lime – 2%
• Superior early strength & performance
43 |
Benefits of Foamed Bitumen Stabilisation
• Moisture resistant pavement - offers better
resilience to flooding.
• Strong and flexible pavement - foamed bitumen
improves the stiffness and load bearing capacity.
• Reduces shrinkage cracking.
• Better fatigue resistance than using a cement
stabilised base.
• Using lime as a secondary additive provides longer
working times during construction.
44 |
Foamed Bitumen Stabilised Pavements
Past projects in Queensland
45 |
Foamed Bitumen Stabilised Pavements
Recent projects in Queensland
46 |
Project specific benefits
• Gore Highway - Project savings by reducing bitumen
content
! 0.5% reduction of bitumen content =$15,000/ km.
! Increased productivity (more m2/ day).
! 21 days savings at $25,000/day =$525,000
! Total savings of $40,000/day
• Flinders Highway- Optimising bitumen design rate from
3.0% to 2.5% through modulus mix design resulted in
savings of $360,000 or $26,000 / km
• Optimisation of lime in the lime stabilised subgrade from
8% to 5%. Cost savings of $1,362,300 or $48,700 / km
was achieved.
47 |
Gore Highway 28A
Performance
Additive
Depth Content & Construction
Mix Design
50 |
ADVANTAGES
51 |
A Vision of the
52 |
Resilience!
Reduction
in ..
Road user
Maintenance
costs
53 |
But must have construction control
54 | Type footer details here | May 15, 2015
Summary
Improved existing
TMR
technology
Introduced INNOVATIVE
technology
57 |