EXECUTIVE SUMMARY
Project ID :
Project Name : OO1: Ensure Safe and Reliable National Road System,
Bridge - Retrofitting/ Strengthening of Permanent
Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas
Rd
Location of Project : San Antonio, Quezon
2. Project Category :
3. Source of Fund : GAA 2022
4. Action Recommended : For Approval
5. Implementing Office: DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : ₱ 25,312,000.00
8. ABC : ₱ 24,805,760.00
9. Project Duration : 150 C.D.
10. Mode Implementation
: By Contract
PREPARED BY:
KENNY S. AVELLANO
Engineer II
Planning and Design Section
SUBMITTED BY:
Project : OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Net Length (a) Road
Quipot Br. (B02945LZ) along Quezon-Batangas Rd (b) Bridge 50.60 m.
Project ID : (c ) Others
Location : San Antonio, Quezon Target Start Date :
Station Limits : K0099+095.00 - K0099+149.60 Total Project Duration : 150 Calendar days
Appropriation : P 25,312,000.00 No. of Pre-determined : 100 Calendar days
Source of Fund : GAA 2022 Unworkable Days : 50 Calendar days
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
PART A: Facilities for the Engineer 1.33% 262,930.20 1.33% 262,930.20
B: Other General Requirements 3.75% 742,346.93 3.75% 742,346.93
C: Earthwork 0.73% 143,585.91 0.73% 143,585.91
D: Subbase and Base Course 0.00% 0.00 0.00% -
E: Surface Courses (PLS. SEE FORM POW-2015-01C-00) 1.91% 377,679.28 1.91% 377,679.28
F: Bridge Construction 92.29% 18,275,834.61 92.29% 18,275,834.61
G: Drainage and Slope Protection Structures 0.00% 0.00 0.00% -
H: Miscellaneous Structures 0.00% 0.00 0.00% -
I: Provisional Sum 0.00% 0.00 0.00% -
J: Daywork 0.00% 0.00 0.00% -
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
KENNY S. AVELLANO FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO WILFREDO L. RACELIS DEL ROSARIO C. NACA
Engineer II Chief, Planning & Design Section Engineer II Officer-in-Charge Officer-in-Charge
Planning and Design Section Planning and Design Section Office of the Assistant District Engineer Office of the District Engineer
Date: November 2, 2021
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART A FACILITIES FOR THE ENGINEER
As Submitted 0.49% 5.00 37,500.00 - 60,000.00 97,500.00 8% 7,800.00 5,265.00 110,565.00
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) month
As Evaluated 0.49% 5.00 37,500.00 - 60,000.00 97,500.00 8% 7,800.00 5,265.00 110,565.00
As Submitted 0.05% 1.00 9,040.00 - - 9,040.00 8% 723.20 488.16 10,251.36
A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer ea.
As Evaluated 0.05% 1.00 9,040.00 - - 9,040.00 8% 723.20 488.16 10,251.36
As Submitted 0.40% 5.00 40,145.00 39,246.00 - 79,391.00 0% - 3,969.55 83,360.55
A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer mo.
As Evaluated 0.40% 5.00 40,145.00 39,246.00 - 79,391.00 0% - 3,969.55 83,360.55
As Submitted 0.37% 5.00 - 72,499.20 - 72,499.20 8% 5,799.94 3,914.96 82,214.10
A.1.3(1) Provision of Field Office Staff for the Assistance to the Engineer mo.
As Evaluated 0.37% 5.00 - 72,499.20 - 72,499.20 8% 5,799.94 3,914.96 82,214.10
As Submitted 0.02% 300.00 4,500.00 - - 4,500.00 8% 360.00 243.00 5,103.00
A.1.4(1) Provision of Progress Photographs each
As Evaluated 0.02% 300.00 4,500.00 - - 4,500.00 8% 360.00 243.00 5,103.00
As Submitted 1.33% 91,185.00 111,745.20 60,000.00 262,930.20 14,683.14 13,880.67 291,494.01
TOTAL OF PART A
As Evaluated 1.33% 91,185.00 111,745.20 60,000.00 262,930.20 14,683.14 13,880.67 291,494.01
PART B OTHER GENERAL REQUIREMENTS
As Submitted 0.06% 2.00 8,100.00 4,112.96 - 12,212.96 20% 2,442.59 732.78 15,388.33
B.5 Project Billboard / Signboard each
As Evaluated 0.06% 2.00 8,100.00 4,112.96 - 12,212.96 20% 2,442.59 732.78 15,388.33
As Submitted 1.13% 1.00 46,825.79 159,000.00 17,148.00 222,973.79 8% 17,837.90 12,040.58 252,852.27
B.7(2) Occupational Safety and Health Program lump sum
As Evaluated 1.13% 1.00 46,825.79 159,000.00 17,148.00 222,973.79 8% 17,837.90 12,040.58 252,852.27
As Submitted 1.75% 1.00 18,276.18 321,084.00 7,800.00 347,160.18 8% 27,772.81 18,746.65 393,679.64
B.8(2) Traffic Management lump sum
As Evaluated 1.75% 1.00 18,276.18 321,084.00 7,800.00 347,160.18 8% 27,772.81 18,746.65 393,679.64
As Submitted 0.81% 1.00 - - 160,000.00 160,000.00 0% - 8,000.00 168,000.00
B.9 Mobilization / Demobilization lump sum
As Evaluated 0.81% 1.00 - - 160,000.00 160,000.00 0% - 8,000.00 168,000.00
As Submitted 3.75% 73,201.97 484,196.96 184,948.00 742,346.93 48,053.30 39,520.01 829,920.24
TOTAL OF PART B
As Evaluated 3.75% 73,201.97 484,196.96 184,948.00 742,346.93 48,053.30 39,520.01 829,920.24
PART C EARTHWORKS
As Submitted 0.59% 1.00 - 17,519.88 100,199.99 117,719.87 20% 23,543.97 7,063.19 148,327.03
101(1) Removal of Structures and Obstructions lump sum
As Evaluated 0.59% 1.00 - 17,519.88 100,199.99 117,719.87 20% 23,543.97 7,063.19 148,327.03
As Submitted 0.13% 193.05 - 924.95 24,941.09 25,866.04 20% 5,173.21 1,551.96 32,591.21
101(3)a3 Removal of Actual Structures/Obstruction (0.23m thick, PCCP) Unreinforced sq.m.
As Evaluated 0.13% 193.05 - 924.95 24,941.09 25,866.04 20% 5,173.21 1,551.96 32,591.21
As Submitted 0.73% - 18,444.83 125,141.08 143,585.91 28,717.18 8,615.15 180,918.24
TOTAL OF PART C
As Evaluated 0.73% - 18,444.83 125,141.08 143,585.91 28,717.18 8,615.15 180,918.24
PART D SUBBASE AND BASE COURSE
As Submitted
TOTAL OF PART D
As Evaluated
PART E SURFACE COURSES
As Submitted 1.91% 193.05 371,511.21 3,448.39 2,719.68 377,679.28 20% 75,535.86 22,660.76 475,875.90
311(1)f1 Portland Cement Concrete Pavement (Unreinforced) - 0.30 m thick, 14 days sq.m.
As Evaluated 1.91% 193.05 371,511.21 3,448.39 2,719.68 377,679.28 20% 75,535.86 22,660.76 475,875.90
As Submitted 1.91% 371,511.21 3,448.39 2,719.68 377,679.28 75,535.86 22,660.76 475,875.90
TOTAL OF PART E
As Evaluated 1.91% 371,511.21 3,448.39 2,719.68 377,679.28 75,535.86 22,660.76 475,875.90
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART F FACILITIES
BRIDGE FOR THE ENGINEER
CONSTRUCTION
As Submitted 2.73% 1.00 235,600.00 152,478.00 152,047.80 540,125.80 20% 108,025.16 32,407.55 680,558.51
414(1) Forms and Falsework lump sum
As Evaluated 2.73% 1.00 235,600.00 152,478.00 152,047.80 540,125.80 20% 108,025.16 32,407.55 680,558.51
As Submitted 26.79% 397.12 4,966,541.57 109,783.03 229,373.34 5,305,697.94 20% 1,061,139.59 318,341.88 6,685,179.41
416(1)a Carbon Fiber (1 Layer) sq.m.
As Evaluated 26.79% 397.12 4,966,541.57 109,783.03 229,373.34 5,305,697.94 20% 1,061,139.59 318,341.88 6,685,179.41
As Submitted 0.28% 565.10 38,275.62 5,954.14 11,932.23 56,161.99 20% 11,232.40 3,369.72 70,764.11
403(4)a1 Structural Steel, Furnished and Fabricated (Grade 36) kg.
As Evaluated 0.28% 565.10 38,275.62 5,954.14 11,932.23 56,161.99 20% 11,232.40 3,369.72 70,764.11
As Submitted 34.00% 36.82 6,208,101.64 169,656.14 354,468.21 6,732,225.99 20% 1,346,445.20 403,933.56 8,482,604.75
416(1)e Carbon Fiber Plate sq.m.
As Evaluated 34.00% 36.82 6,208,101.64 169,656.14 354,468.21 6,732,225.99 20% 1,346,445.20 403,933.56 8,482,604.75
As Submitted 13.51% 1,691.42 2,439,027.64 92,386.77 142,896.80 2,674,311.21 20% 534,862.24 160,458.67 3,369,632.12
628(9) Special Anti Corrosion Paint sq.m.
As Evaluated 13.51% 1,691.42 2,439,027.64 92,386.77 142,896.80 2,674,311.21 20% 534,862.24 160,458.67 3,369,632.12
As Submitted 7.81% 1.00 942,252.50 199,573.20 404,920.92 1,546,746.62 20% 309,349.32 92,804.80 1,948,900.74
628(11) Structural Concrete Injection and Crack Repair lump sum
As Evaluated 7.81% 1.00 942,252.50 199,573.20 404,920.92 1,546,746.62 20% 309,349.32 92,804.80 1,948,900.74
As Submitted 7.17% 610.94 1,409,587.51 5,339.22 5,638.33 1,420,565.06 20% 284,113.01 85,233.90 1,789,911.97
304A(3) Micro-Surfacing sq.m.
As Evaluated 7.17% 610.94 1,409,587.51 5,339.22 5,638.33 1,420,565.06 20% 284,113.01 85,233.90 1,789,911.97
As Submitted 92.29% 16,239,386.48 735,170.50 1,301,277.63 18,275,834.61 3,655,166.92 1,096,550.08 23,027,551.61
TOTAL OF PART F
As Evaluated 92.29% 16,239,386.48 735,170.50 1,301,277.63 18,275,834.61 3,655,166.92 1,096,550.08 23,027,551.61
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
As Submitted
As Evaluated
As Submitted
TOTAL OF PART G
As Evaluated
PART H MISCELLANEOUS STRUCTURES
As Submitted
As Evaluated
As Submitted
TOTAL OF PART H
As Evaluated
PART I PROVISIONAL SUM
As Submitted
As Evaluated
As Submitted
TOTAL OF PART I
As Evaluated
PART J DAYWORK
As Submitted
As Evaluated
As Submitted
TOTAL OF PART J
As Evaluated
As Submitted 100% 16,775,284.66 1,353,005.88 1,674,086.39 19,802,376.93 3,822,156.40 1,181,226.67 24,805,760.00
GRAND TOTAL
As Evaluated 100% 16,775,284.66 1,353,005.88 1,674,086.39 19,802,376.93 3,822,156.40 1,181,226.67 24,805,760.00
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) 5.00 5.00 month 97,500.00 97,500.00 19,500.00 19,500.00 22,113.00 22,113.00 0.49% 0.49%
A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer 5.00 5.00 ea. 9,040.00 9,040.00 9,040.00 9,040.00 10,251.36 10,251.36 0.05% 0.05%
A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer 5.00 5.00 mo. 79,391.00 79,391.00 15,878.20 15,878.20 16,672.11 16,672.11 0.40% 0.40%
A.1.3(1) Provision of Field Office Staff for the Assistance to the Engineer 300.00 300.00 mo. 72,499.20 72,499.20 14,499.84 14,499.84 16,442.82 16,442.82 0.37% 0.37%
A.1.4(1) Provision of Progress Photographs 300.00 300.00 each 4,500.00 4,500.00 15.00 15.00 17.01 17.01 0.02% 0.02%
B.5 Project Billboard / Signboard 2.00 2.00 each 12,212.96 12,212.96 6,106.48 6,106.48 7,694.17 7,694.17 0.06% 0.06%
B.7(2) Occupational Safety and Health Program 1.00 1.00 lump sum 222,973.79 222,973.79 222,973.79 222,973.79 252,852.27 252,852.27 1.13% 1.13%
B.8(2) Traffic Management 1.00 1.00 lump sum 347,160.18 347,160.18 347,160.18 347,160.18 393,679.64 393,679.64 1.75% 1.75%
B.9 Mobilization / Demobilization 1.00 1.00 lump sum 160,000.00 160,000.00 160,000.00 160,000.00 168,000.00 168,000.00 0.81% 0.81%
PART C EARTHWORKS
101(1) Removal of Structures and Obstructions 1.00 1.00 lump sum 117,719.87 117,719.87 117,719.87 117,719.87 148,327.03 148,327.03 0.59% 0.59%
101(3)a3 Removal of Actual Structures/Obstruction (0.23m thick, PCCP) Unreinforced 193.05 193.05 sq.m. 25,866.04 25,866.04 133.99 133.99 168.82 168.82 0.13% 0.13%
TOTAL OF PART D
311(1)f1 Portland Cement Concrete Pavement (Unreinforced) - 0.30 m thick, 14 days 193.05 193.05 sq.m. 377,679.28 377,679.28 1,956.38 1,956.38 2,465.04 2,465.04 1.91% 1.91%
414(1) Forms and Falsework 1.00 1.00 lump sum 540,125.80 540,125.80 540,125.80 540,125.80 680,558.51 680,558.51 2.73% 2.73%
416(1)a Carbon Fiber (1 Layer) 397.12 397.12 sq.m. 5,305,697.94 5,305,697.94 13,360.44 13,360.44 16,834.16 16,834.16 26.79% 26.79%
403(4)a1 Structural Steel, Furnished and Fabricated (Grade 36) 565.10 565.10 kg. 56,161.99 56,161.99 99.38 99.38 125.22 125.22 0.28% 0.28%
416(1)e Carbon Fiber Plate 36.82 36.82 sq.m. 6,732,225.99 6,732,225.99 182,831.62 182,831.62 230,367.84 230,367.84 34.00% 34.00%
628(9) Special Anti Corrosion Paint 1,691.42 1,691.42 sq.m. 2,674,311.21 2,674,311.21 1,581.10 1,581.10 1,992.19 1,992.19 13.51% 13.51%
628(11) Structural Concrete Injection and Crack Repair 1.00 1.00 lump sum 1,546,746.62 1,546,746.62 1,546,746.62 1,546,746.62 1,948,900.74 1,948,900.74 7.81% 7.81%
304A(3) Micro-Surfacing 610.94 610.94 sq.m. 1,420,565.06 1,420,565.06 2,325.21 2,325.21 2,929.76 2,929.76 7.17% 7.17%
TOTAL OF PART G
TOTAL OF PART H
TOTAL OF PART I
PART J DAYWORK
TOTAL OF PART J
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
KENNY S. AVELLANO FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO WILFREDO L. RACELIS DEL ROSARIO C. NACA
Engineer II Chief, Planning & Design Section Engineer II Officer-in-Charge Officer-in-Charge
Planning and Design Section Planning and Design Section Office of the Assistant District Engineer Office of the District Engineer
Date: November 2, 2021
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02A-00
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon
AS EVALUATED
PROJECT : OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges,
Quipot Br. (B02945LZ) along Quezon-Batangas Rd
AMOUNT: P 25,312,000.00
90 - X 90 - 62
=
20,000,000 -15,000,000 20,000,000 - 5,000,000
X = 99.92
SAY 100.00
Prepared by:
KENNY S. AVELLANO
Engineer II
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
Item no./Description : A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : month
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
Item no./Description : A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the
Engineer
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
Item no./Description : A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer
Unit of Measurement : mo.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Driver 1 120.00 65.41 7,849.20
Item no./Description : A.1.3(1) Provision of Field Office Staff for the Assistance to the Engineer
Unit of Measurement : mo.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Highly Skilled Labor 1 192.00 75.52 14,499.84
*Note: Number of Hours based on workable days per month
Sub - Total for A.1 - As Submitted 14,499.84
A.2 Labor
a. Highly Skilled Labor 1 192.00 75.52 14,499.84
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 8 90.57 724.56
b. Skilled Labor 1 8 65.41 523.28
c. Unskilled Labor 2 8 50.54 808.64
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Safety Practitioner/Officer (Full Time) 1 1200 62.50 75,000.00
b. Health Officer (Full Time) 1 1200 35.00 42,000.00
c. Sanitation Aide (Full Time) 1 1200 35.00 42,000.00
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Skilled Labor 1 1200 65.41 78,492.00
b. Unskilled Labor 4 1200 50.54 242,592.00
a. Barricade Flasher Light (3 Volts, Battery Operated, Amber Color 10 1200 0.65 7,800.00
w/ lifespan consideration of 6 months)
a. Barricade Flasher Light (3 Volts, Battery Operated, Amber Color 10 1200 0.65 7,800.00
w/ lifespan consideration of 6 months)
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
F.1 Materials
Item no./Description : 101(3)a3 Removal of Actual Structures/Obstruction (0.23m thick, PCCP) Unreinforced
Unit of Measurement : sq.m.
Output per hour - As Submitted : 40.00
Output per hour - As Evaluated : 40.00
F.1 Materials
Item no./Description : 311(1)f1 Portland Cement Concrete Pavement (Unreinforced) - 0.30 m thick, 14 days
Unit of Measurement : sq.m.
Output per hour - As Submitted : 53.67
Output per hour - As Evaluated : 53.67
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Injection) 4 1 65.41 261.64
c. Unskilled Labor (Surface Preparation) 6 1 50.54 303.24
F.2 Materials
a. BD-2000 = 209 Liters Resin + 1,280 kg. Bulk kit 0.0029 780,000.00 2,262.00
(330 - 360 sq.m. coverage)
b. Consumables (2% of Materials Cost) 45.24
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 360 90.57 32,605.20
b. Skilled Labor 2 360 65.41 47,095.20
c. Unskilled Labor 4 360 50.54 72,777.60
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Surface Preparation) 1 1 65.41 65.41
c. Skilled Labor (Carbon Fiber Setting) 2 1 65.41 130.82
d. Unskilled Labor (Surface Preparation) 4 1 50.54 202.16
e. Unskilled Labor (Carbon Fiber Setting) 4 1 50.54 202.16
Item no./Description : 403(4)a1 Structural Steel, Furnished and Fabricated (Grade 36)
Unit of Measurement : kg.
Output per hour - As Submitted : 56.00
Output per hour - As Evaluated : 56.00
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor 3 1 65.41 196.23
c. Unskilled Labor 6 1 50.54 303.24
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Surface Preparation) 1 1 65.41 65.41
c. Skilled Labor (Carbon Fiber Plate Setting) 2 1 65.41 130.82
d. Unskilled Labor (Surface Preparation) 4 1 50.54 202.16
e. Unskilled Labor (Carbon Fiber Plate Setting) 4 1 50.54 202.16
No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 360 90.57 32,605.20
b. Skilled Labor (Injection) 4 360 65.41 94,190.40
c. Unskilled Labor (Surface Preparation) 4 360 50.54 72,777.60