REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


OFFICE OF THE DISTRICT ENGINEER
QUEZON II DISTRICT ENGINEERING OFFICE
DALAHICAN ROAD, LUCENA CITY

OO1: Ensure Safe and Reliable National Road System,


Bridge - Retrofitting/ Strengthening of Permanent
Bridges, Quipot Br. (B02945LZ) along Quezon-
Batangas Rd

( FY 2022 REGULAR INFRA)


Republic of the Philippines
Department of Public Works and Highways
Quezon II District Engineering Office
Lucena City

Date: November 2, 2021

EXECUTIVE SUMMARY

For : THE DISTRICT ENGINEER

Project ID :
Project Name : OO1: Ensure Safe and Reliable National Road System,
Bridge - Retrofitting/ Strengthening of Permanent
Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas
Rd
Location of Project : San Antonio, Quezon
2. Project Category :
3. Source of Fund : GAA 2022
4. Action Recommended : For Approval
5. Implementing Office: DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : ₱ 25,312,000.00
8. ABC : ₱ 24,805,760.00
9. Project Duration : 150 C.D.
10. Mode Implementation
: By Contract

PREPARED BY:

KENNY S. AVELLANO
Engineer II
Planning and Design Section

SUBMITTED BY:

FAUSTINO MARK ANTHONY S. DE LA CRUZ


Chief, Planning and Design Section
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Net Length (a) Road
Quipot Br. (B02945LZ) along Quezon-Batangas Rd (b) Bridge 50.60 m.
Project ID : (c ) Others
Location : San Antonio, Quezon Target Start Date :
Station Limits : K0099+095.00 - K0099+149.60 Total Project Duration : 150 Calendar days
Appropriation : P 25,312,000.00 No. of Pre-determined : 100 Calendar days
Source of Fund : GAA 2022 Unworkable Days : 50 Calendar days

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
PART A: Facilities for the Engineer 1.33% 262,930.20 1.33% 262,930.20
B: Other General Requirements 3.75% 742,346.93 3.75% 742,346.93
C: Earthwork 0.73% 143,585.91 0.73% 143,585.91
D: Subbase and Base Course 0.00% 0.00 0.00% -
E: Surface Courses (PLS. SEE FORM POW-2015-01C-00) 1.91% 377,679.28 1.91% 377,679.28
F: Bridge Construction 92.29% 18,275,834.61 92.29% 18,275,834.61
G: Drainage and Slope Protection Structures 0.00% 0.00 0.00% -
H: Miscellaneous Structures 0.00% 0.00 0.00% -
I: Provisional Sum 0.00% 0.00 0.00% -
J: Daywork 0.00% 0.00 0.00% -

Total 100% 19,802,376.93 100% 19,802,376.93

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 1,353,005.88 1,353,005.88 A. Total Direct Cost 19,802,376.93 19,802,376.93
2. Materials 16,775,284.66 16,775,284.66 B. OCM and Profit 3,822,156.40 3,822,156.40
3. Rental of Equipment 1,674,086.39 1,674,086.39 C. Value Added Tax (5%) 1,181,226.67 1,181,226.67
4. Provisional Sum / Daywork - - D. Total Construction Cost 24,805,760.00 24,805,760.00
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 3,822,156.40 3,822,156.40 E. Eng'g & Administrative Overhead, 2.0% 506,240.00 506,240.00
6. Value Added Tax (5%) 1,181,226.67 1,181,226.67 F. RROW Acquisition - -
7. EAO, 2.0% 506,240.00 506,240.00 G. Physical Reserved (Contingency) - -
8. RROW Acquisition - -
9. Physical Reserved (Contingency) - -
10.TOTAL ESTIMATED COST 25,312,000.00 25,312,000.00 H. TOTAL ESTIMATED COST 25,312,000.00 25,312,000.00

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

KENNY S. AVELLANO FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO WILFREDO L. RACELIS DEL ROSARIO C. NACA
Engineer II Chief, Planning & Design Section Engineer II Officer-in-Charge Officer-in-Charge
Planning and Design Section Planning and Design Section Office of the Assistant District Engineer Office of the District Engineer
Date: November 2, 2021
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART A FACILITIES FOR THE ENGINEER
As Submitted 0.49% 5.00 37,500.00 - 60,000.00 97,500.00 8% 7,800.00 5,265.00 110,565.00
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) month
As Evaluated 0.49% 5.00 37,500.00 - 60,000.00 97,500.00 8% 7,800.00 5,265.00 110,565.00
As Submitted 0.05% 1.00 9,040.00 - - 9,040.00 8% 723.20 488.16 10,251.36
A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer ea.
As Evaluated 0.05% 1.00 9,040.00 - - 9,040.00 8% 723.20 488.16 10,251.36
As Submitted 0.40% 5.00 40,145.00 39,246.00 - 79,391.00 0% - 3,969.55 83,360.55
A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer mo.
As Evaluated 0.40% 5.00 40,145.00 39,246.00 - 79,391.00 0% - 3,969.55 83,360.55
As Submitted 0.37% 5.00 - 72,499.20 - 72,499.20 8% 5,799.94 3,914.96 82,214.10
A.1.3(1) Provision of Field Office Staff for the Assistance to the Engineer mo.
As Evaluated 0.37% 5.00 - 72,499.20 - 72,499.20 8% 5,799.94 3,914.96 82,214.10
As Submitted 0.02% 300.00 4,500.00 - - 4,500.00 8% 360.00 243.00 5,103.00
A.1.4(1) Provision of Progress Photographs each
As Evaluated 0.02% 300.00 4,500.00 - - 4,500.00 8% 360.00 243.00 5,103.00
As Submitted 1.33% 91,185.00 111,745.20 60,000.00 262,930.20 14,683.14 13,880.67 291,494.01
TOTAL OF PART A
As Evaluated 1.33% 91,185.00 111,745.20 60,000.00 262,930.20 14,683.14 13,880.67 291,494.01
PART B OTHER GENERAL REQUIREMENTS
As Submitted 0.06% 2.00 8,100.00 4,112.96 - 12,212.96 20% 2,442.59 732.78 15,388.33
B.5 Project Billboard / Signboard each
As Evaluated 0.06% 2.00 8,100.00 4,112.96 - 12,212.96 20% 2,442.59 732.78 15,388.33
As Submitted 1.13% 1.00 46,825.79 159,000.00 17,148.00 222,973.79 8% 17,837.90 12,040.58 252,852.27
B.7(2) Occupational Safety and Health Program lump sum
As Evaluated 1.13% 1.00 46,825.79 159,000.00 17,148.00 222,973.79 8% 17,837.90 12,040.58 252,852.27
As Submitted 1.75% 1.00 18,276.18 321,084.00 7,800.00 347,160.18 8% 27,772.81 18,746.65 393,679.64
B.8(2) Traffic Management lump sum
As Evaluated 1.75% 1.00 18,276.18 321,084.00 7,800.00 347,160.18 8% 27,772.81 18,746.65 393,679.64
As Submitted 0.81% 1.00 - - 160,000.00 160,000.00 0% - 8,000.00 168,000.00
B.9 Mobilization / Demobilization lump sum
As Evaluated 0.81% 1.00 - - 160,000.00 160,000.00 0% - 8,000.00 168,000.00
As Submitted 3.75% 73,201.97 484,196.96 184,948.00 742,346.93 48,053.30 39,520.01 829,920.24
TOTAL OF PART B
As Evaluated 3.75% 73,201.97 484,196.96 184,948.00 742,346.93 48,053.30 39,520.01 829,920.24
PART C EARTHWORKS
As Submitted 0.59% 1.00 - 17,519.88 100,199.99 117,719.87 20% 23,543.97 7,063.19 148,327.03
101(1) Removal of Structures and Obstructions lump sum
As Evaluated 0.59% 1.00 - 17,519.88 100,199.99 117,719.87 20% 23,543.97 7,063.19 148,327.03
As Submitted 0.13% 193.05 - 924.95 24,941.09 25,866.04 20% 5,173.21 1,551.96 32,591.21
101(3)a3 Removal of Actual Structures/Obstruction (0.23m thick, PCCP) Unreinforced sq.m.
As Evaluated 0.13% 193.05 - 924.95 24,941.09 25,866.04 20% 5,173.21 1,551.96 32,591.21
As Submitted 0.73% - 18,444.83 125,141.08 143,585.91 28,717.18 8,615.15 180,918.24
TOTAL OF PART C
As Evaluated 0.73% - 18,444.83 125,141.08 143,585.91 28,717.18 8,615.15 180,918.24
PART D SUBBASE AND BASE COURSE
As Submitted
TOTAL OF PART D
As Evaluated
PART E SURFACE COURSES
As Submitted 1.91% 193.05 371,511.21 3,448.39 2,719.68 377,679.28 20% 75,535.86 22,660.76 475,875.90
311(1)f1 Portland Cement Concrete Pavement (Unreinforced) - 0.30 m thick, 14 days sq.m.
As Evaluated 1.91% 193.05 371,511.21 3,448.39 2,719.68 377,679.28 20% 75,535.86 22,660.76 475,875.90
As Submitted 1.91% 371,511.21 3,448.39 2,719.68 377,679.28 75,535.86 22,660.76 475,875.90
TOTAL OF PART E
As Evaluated 1.91% 371,511.21 3,448.39 2,719.68 377,679.28 75,535.86 22,660.76 475,875.90
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART F FACILITIES
BRIDGE FOR THE ENGINEER
CONSTRUCTION
As Submitted 2.73% 1.00 235,600.00 152,478.00 152,047.80 540,125.80 20% 108,025.16 32,407.55 680,558.51
414(1) Forms and Falsework lump sum
As Evaluated 2.73% 1.00 235,600.00 152,478.00 152,047.80 540,125.80 20% 108,025.16 32,407.55 680,558.51
As Submitted 26.79% 397.12 4,966,541.57 109,783.03 229,373.34 5,305,697.94 20% 1,061,139.59 318,341.88 6,685,179.41
416(1)a Carbon Fiber (1 Layer) sq.m.
As Evaluated 26.79% 397.12 4,966,541.57 109,783.03 229,373.34 5,305,697.94 20% 1,061,139.59 318,341.88 6,685,179.41
As Submitted 0.28% 565.10 38,275.62 5,954.14 11,932.23 56,161.99 20% 11,232.40 3,369.72 70,764.11
403(4)a1 Structural Steel, Furnished and Fabricated (Grade 36) kg.
As Evaluated 0.28% 565.10 38,275.62 5,954.14 11,932.23 56,161.99 20% 11,232.40 3,369.72 70,764.11
As Submitted 34.00% 36.82 6,208,101.64 169,656.14 354,468.21 6,732,225.99 20% 1,346,445.20 403,933.56 8,482,604.75
416(1)e Carbon Fiber Plate sq.m.
As Evaluated 34.00% 36.82 6,208,101.64 169,656.14 354,468.21 6,732,225.99 20% 1,346,445.20 403,933.56 8,482,604.75
As Submitted 13.51% 1,691.42 2,439,027.64 92,386.77 142,896.80 2,674,311.21 20% 534,862.24 160,458.67 3,369,632.12
628(9) Special Anti Corrosion Paint sq.m.
As Evaluated 13.51% 1,691.42 2,439,027.64 92,386.77 142,896.80 2,674,311.21 20% 534,862.24 160,458.67 3,369,632.12
As Submitted 7.81% 1.00 942,252.50 199,573.20 404,920.92 1,546,746.62 20% 309,349.32 92,804.80 1,948,900.74
628(11) Structural Concrete Injection and Crack Repair lump sum
As Evaluated 7.81% 1.00 942,252.50 199,573.20 404,920.92 1,546,746.62 20% 309,349.32 92,804.80 1,948,900.74
As Submitted 7.17% 610.94 1,409,587.51 5,339.22 5,638.33 1,420,565.06 20% 284,113.01 85,233.90 1,789,911.97
304A(3) Micro-Surfacing sq.m.
As Evaluated 7.17% 610.94 1,409,587.51 5,339.22 5,638.33 1,420,565.06 20% 284,113.01 85,233.90 1,789,911.97
As Submitted 92.29% 16,239,386.48 735,170.50 1,301,277.63 18,275,834.61 3,655,166.92 1,096,550.08 23,027,551.61
TOTAL OF PART F
As Evaluated 92.29% 16,239,386.48 735,170.50 1,301,277.63 18,275,834.61 3,655,166.92 1,096,550.08 23,027,551.61
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
As Submitted
As Evaluated
As Submitted
TOTAL OF PART G
As Evaluated
PART H MISCELLANEOUS STRUCTURES
As Submitted
As Evaluated
As Submitted
TOTAL OF PART H
As Evaluated
PART I PROVISIONAL SUM
As Submitted
As Evaluated
As Submitted
TOTAL OF PART I
As Evaluated
PART J DAYWORK
As Submitted
As Evaluated
As Submitted
TOTAL OF PART J
As Evaluated
As Submitted 100% 16,775,284.66 1,353,005.88 1,674,086.39 19,802,376.93 3,822,156.40 1,181,226.67 24,805,760.00
GRAND TOTAL
As Evaluated 100% 16,775,284.66 1,353,005.88 1,674,086.39 19,802,376.93 3,822,156.40 1,181,226.67 24,805,760.00
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED

PART A FACILITIES FOR THE ENGINEER

A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) 5.00 5.00 month 97,500.00 97,500.00 19,500.00 19,500.00 22,113.00 22,113.00 0.49% 0.49%

A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer 5.00 5.00 ea. 9,040.00 9,040.00 9,040.00 9,040.00 10,251.36 10,251.36 0.05% 0.05%

A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer 5.00 5.00 mo. 79,391.00 79,391.00 15,878.20 15,878.20 16,672.11 16,672.11 0.40% 0.40%

A.1.3(1) Provision of Field Office Staff for the Assistance to the Engineer 300.00 300.00 mo. 72,499.20 72,499.20 14,499.84 14,499.84 16,442.82 16,442.82 0.37% 0.37%

A.1.4(1) Provision of Progress Photographs 300.00 300.00 each 4,500.00 4,500.00 15.00 15.00 17.01 17.01 0.02% 0.02%

TOTAL OF PART A 262,930.20 262,930.20 1.33% 1.33%

PART B OTHER GENERAL REQUIREMENTS

B.5 Project Billboard / Signboard 2.00 2.00 each 12,212.96 12,212.96 6,106.48 6,106.48 7,694.17 7,694.17 0.06% 0.06%

B.7(2) Occupational Safety and Health Program 1.00 1.00 lump sum 222,973.79 222,973.79 222,973.79 222,973.79 252,852.27 252,852.27 1.13% 1.13%

B.8(2) Traffic Management 1.00 1.00 lump sum 347,160.18 347,160.18 347,160.18 347,160.18 393,679.64 393,679.64 1.75% 1.75%

B.9 Mobilization / Demobilization 1.00 1.00 lump sum 160,000.00 160,000.00 160,000.00 160,000.00 168,000.00 168,000.00 0.81% 0.81%

TOTAL OF PART B 742,346.93 742,346.93 3.75% 3.75%

PART C EARTHWORKS

101(1) Removal of Structures and Obstructions 1.00 1.00 lump sum 117,719.87 117,719.87 117,719.87 117,719.87 148,327.03 148,327.03 0.59% 0.59%

101(3)a3 Removal of Actual Structures/Obstruction (0.23m thick, PCCP) Unreinforced 193.05 193.05 sq.m. 25,866.04 25,866.04 133.99 133.99 168.82 168.82 0.13% 0.13%

TOTAL OF PART C 143,585.91 143,585.91 0.73% 0.73%

PART D SUBBASE AND BASE COURSE

TOTAL OF PART D

PART E SURFACE COURSES

311(1)f1 Portland Cement Concrete Pavement (Unreinforced) - 0.30 m thick, 14 days 193.05 193.05 sq.m. 377,679.28 377,679.28 1,956.38 1,956.38 2,465.04 2,465.04 1.91% 1.91%

TOTAL OF PART E 377,679.28 377,679.28 1.91% 1.91%

PART F BRIDGE CONSTRUCTION

414(1) Forms and Falsework 1.00 1.00 lump sum 540,125.80 540,125.80 540,125.80 540,125.80 680,558.51 680,558.51 2.73% 2.73%

416(1)a Carbon Fiber (1 Layer) 397.12 397.12 sq.m. 5,305,697.94 5,305,697.94 13,360.44 13,360.44 16,834.16 16,834.16 26.79% 26.79%

403(4)a1 Structural Steel, Furnished and Fabricated (Grade 36) 565.10 565.10 kg. 56,161.99 56,161.99 99.38 99.38 125.22 125.22 0.28% 0.28%

416(1)e Carbon Fiber Plate 36.82 36.82 sq.m. 6,732,225.99 6,732,225.99 182,831.62 182,831.62 230,367.84 230,367.84 34.00% 34.00%

628(9) Special Anti Corrosion Paint 1,691.42 1,691.42 sq.m. 2,674,311.21 2,674,311.21 1,581.10 1,581.10 1,992.19 1,992.19 13.51% 13.51%

628(11) Structural Concrete Injection and Crack Repair 1.00 1.00 lump sum 1,546,746.62 1,546,746.62 1,546,746.62 1,546,746.62 1,948,900.74 1,948,900.74 7.81% 7.81%

304A(3) Micro-Surfacing 610.94 610.94 sq.m. 1,420,565.06 1,420,565.06 2,325.21 2,325.21 2,929.76 2,929.76 7.17% 7.17%

TOTAL OF PART F 18,275,834.61 18,275,834.61 92.29% 92.29%

PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES

TOTAL OF PART G

PART H MISCELLANEOUS STRUCTURES

TOTAL OF PART H

PART I PROVISIONAL SUM

TOTAL OF PART I

PART J DAYWORK

TOTAL OF PART J

GRAND TOTAL 19,802,376.93 19,802,376.93 100% 100%


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02-00
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
AS SUBMITTED 262,930.20 5.58% 14,683.14 13,880.67 28,563.81 291,494.01
PART A FACILITIES FOR THE ENGINEER
AS EVALUATED 262,930.20 5.58% 14,683.14 13,880.67 28,563.81 291,494.01
AS SUBMITTED 742,346.93 6.47% 48,053.30 39,520.01 87,573.31 829,920.24
PART B OTHER GENERAL REQUIREMENTS
AS EVALUATED 742,346.93 6.47% 48,053.30 39,520.01 87,573.31 829,920.24
AS SUBMITTED 143,585.91 20.00% 28,717.18 8,615.15 37,332.33 180,918.24
PART C EARTHWORKS
AS EVALUATED 143,585.91 20.00% 28,717.18 8,615.15 37,332.33 180,918.24
AS SUBMITTED - 0.00% - - - -
PART D SUBBASE AND BASE COURSE
AS EVALUATED - 0.00% - - - -
AS SUBMITTED 377,679.28 20.00% 75,535.86 22,660.76 98,196.62 475,875.90
PART E SURFACE COURSE
AS EVALUATED 377,679.28 20.00% 75,535.86 22,660.76 98,196.62 475,875.90
AS SUBMITTED 18,275,834.61 20.00% 3,655,166.92 1,096,550.08 4,751,717.00 23,027,551.61
PART F BRIDGE CONSTRUCTION
AS EVALUATED 18,275,834.61 20.00% 3,655,166.92 1,096,550.08 4,751,717.00 23,027,551.61
AS SUBMITTED - 0.00% - - - -
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
AS EVALUATED - 0.00% - - - -
AS SUBMITTED - 0.00% - - - -
PART H MISCELLANEOUS STRUCTURES
AS EVALUATED - 0.00% - - - -
AS SUBMITTED - 0.00% - - - -
PART I PROVISIONAL SUM
AS EVALUATED - 0.00% - - - -
AS SUBMITTED - 0.00% - - - -
PART J DAYWORK
AS EVALUATED - - - - -
AS SUBMITTED 19,802,376.93 3,822,156.40 1,181,226.67 5,003,383.07 24,805,760.00
TOTAL
AS EVALUATED 19,802,376.93 3,822,156.40 1,181,226.67 5,003,383.07 24,805,760.00

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

KENNY S. AVELLANO FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO WILFREDO L. RACELIS DEL ROSARIO C. NACA
Engineer II Chief, Planning & Design Section Engineer II Officer-in-Charge Officer-in-Charge
Planning and Design Section Planning and Design Section Office of the Assistant District Engineer Office of the District Engineer
Date: November 2, 2021
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02A-00
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART A FACILITIES FOR THE ENGINEER
AS SUBMITTED 5.00 month 97,500.00 8% 7,800.00 5,265.00 13,065.00 110,565.00 22,113.00
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis)
AS EVALUATED 5.00 month 97,500.00 8% 7,800.00 5,265.00 13,065.00 110,565.00 22,113.00
Provision of Furnitures/Fixtures, Equipment & Appliances for AS SUBMITTED 1.00 ea. 9,040.00 8% 723.20 488.16 1,211.36 10,251.36 10,251.36
A.1.1(11)
the Field Office for the Engineer AS EVALUATED 1.00 ea. 9,040.00 8% 723.20 488.16 1,211.36 10,251.36 10,251.36
Operation and Maintenance of 4x2 Pick Up Type Service AS SUBMITTED 5.00 mo. 79,391.00 0% - 3,969.55 3,969.55 83,360.55 16,672.11
A.1.2(6)
Vehicle for the Engineer AS EVALUATED 5.00 mo. 79,391.00 0% - 3,969.55 3,969.55 83,360.55 16,672.11
Provision of Field Office Staff for the Assistance to the AS SUBMITTED 5.00 mo. 72,499.20 8% 5,799.94 3,914.96 9,714.90 82,214.10 16,442.82
A.1.3(1)
Engineer AS EVALUATED 5.00 mo. 72,499.20 8% 5,799.94 3,914.96 9,714.90 82,214.10 16,442.82
AS SUBMITTED 300.00 each 4,500.00 8% 360.00 243.00 603.00 5,103.00 17.01
A.1.4(1) Provision of Progress Photographs
AS EVALUATED 300.00 each 4,500.00 8% 360.00 243.00 603.00 5,103.00 17.01
AS SUBMITTED 262,930.20 14,683.14 13,880.67 28,563.81 291,494.01
TOTAL OF PART A
AS EVALUATED 262,930.20 14,683.14 13,880.67 28,563.81 291,494.01
PART B OTHER GENERAL REQUIREMENTS
AS SUBMITTED 2.00 each 12,212.96 20% 2,442.59 732.78 3,175.37 15,388.33 7,694.17
B.5 Project Billboard / Signboard
AS EVALUATED 2.00 each 12,212.96 20% 2,442.59 732.78 3,175.37 15,388.33 7,694.17
AS SUBMITTED 1.00 lump sum 222,973.79 8% 17,837.90 12,040.58 29,878.48 252,852.27 252,852.27
B.7(2) Occupational Safety and Health Program
AS EVALUATED 1.00 lump sum 222,973.79 8% 17,837.90 12,040.58 29,878.48 252,852.27 252,852.27
AS SUBMITTED 1.00 lump sum 347,160.18 8% 27,772.81 18,746.65 46,519.46 393,679.64 393,679.64
B.8(2) Traffic Management
AS EVALUATED 1.00 lump sum 347,160.18 8% 27,772.81 18,746.65 46,519.46 393,679.64 393,679.64
AS SUBMITTED 1.00 lump sum 160,000.00 0% - 8,000.00 8,000.00 168,000.00 168,000.00
B.9 Mobilization / Demobilization
AS EVALUATED 1.00 lump sum 160,000.00 0% - 8,000.00 8,000.00 168,000.00 168,000.00
AS SUBMITTED 742,346.93 48,053.30 39,520.01 87,573.31 829,920.24
TOTAL OF PART B
AS EVALUATED 742,346.93 48,053.30 39,520.01 87,573.31 829,920.24

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

KENNY S. AVELLANO FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO


Engineer II Chief, Planning & Design Section Engineer II
Planning and Design Section Planning and Design Section
Date: November 2, 2021
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02A-00
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST

PART C FACILITIES FOR THE ENGINEER


EARTHWORKS
AS SUBMITTED 1.00 lump sum 117,719.87 20% 23,543.97 7,063.19 30,607.16 148,327.03 148,327.03
101(1) Removal of Structures and Obstructions
AS EVALUATED 1.00 lump sum 117,719.87 20% 23,543.97 7,063.19 30,607.16 148,327.03 148,327.03
Removal of Actual Structures/Obstruction (0.23m thick, AS SUBMITTED 193.05 sq.m. 25,866.04 20% 5,173.21 1,551.96 6,725.17 32,591.21 168.82
101(3)a3
PCCP) Unreinforced AS EVALUATED 193.05 sq.m. 25,866.04 20% 5,173.21 1,551.96 6,725.17 32,591.21 168.82
AS SUBMITTED 143,585.91 28,717.18 8,615.15 37,332.33 180,918.24
TOTAL OF PART C
AS EVALUATED 143,585.91 28,717.18 8,615.15 37,332.33 180,918.24
PART D SUBBASE AND BASE COURSE
AS SUBMITTED

AS EVALUATED

PART E SURFACE COURSES


Portland Cement Concrete Pavement (Unreinforced) - 0.30 m AS SUBMITTED 193.05 sq.m. 377,679.28 20% 75,535.86 22,660.76 98,196.62 475,875.90 2,465.04
311(1)f1
thick, 14 days AS EVALUATED 193.05 sq.m. 377,679.28 20% 75,535.86 22,660.76 98,196.62 475,875.90 2,465.04
AS SUBMITTED 377,679.28 75,535.86 22,660.76 98,196.62 475,875.90
TOTAL OF PART E
AS EVALUATED 377,679.28 75,535.86 22,660.76 98,196.62 475,875.90
PART F BRIDGE CONSTRUCTION
AS SUBMITTED 1.00 lump sum 540,125.80 20% 108,025.16 32,407.55 140,432.71 680,558.51 680,558.51
414(1) Forms and Falsework
AS EVALUATED 1.00 lump sum 540,125.80 20% 108,025.16 32,407.55 140,432.71 680,558.51 680,558.51
AS SUBMITTED 397.12 sq.m. 5,305,697.94 20% 1,061,139.59 318,341.88 1,379,481.47 6,685,179.41 16,834.16
416(1)a Carbon Fiber (1 Layer)
AS EVALUATED 397.12 sq.m. 5,305,697.94 20% 1,061,139.59 318,341.88 1,379,481.47 6,685,179.41 16,834.16
AS SUBMITTED 565.10 kg. 56,161.99 20% 11,232.40 3,369.72 14,602.12 70,764.11 125.22
403(4)a1 Structural Steel, Furnished and Fabricated (Grade 36)
AS EVALUATED 565.10 kg. 56,161.99 20% 11,232.40 3,369.72 14,602.12 70,764.11 125.22
AS SUBMITTED 36.82 sq.m. 6,732,225.99 20% 1,346,445.20 403,933.56 1,750,378.76 8,482,604.75 230,367.84
416(1)e Carbon Fiber Plate
AS EVALUATED 36.82 sq.m. 6,732,225.99 20% 1,346,445.20 403,933.56 1,750,378.76 8,482,604.75 230,367.84

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

KENNY S. AVELLANO FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO


Engineer II Chief, Planning & Design Section Engineer II
Planning and Design Section Planning and Design Section
Date: November 2, 2021
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02A-00
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
FACILITIES FOR THE ENGINEER AS SUBMITTED 1,691.42 sq.m. 2,674,311.21 20% 534,862.24 160,458.67 695,320.91 3,369,632.12 1,992.19
628(9) Special Anti Corrosion Paint
AS EVALUATED 1,691.42 sq.m. 2,674,311.21 20% 534,862.24 160,458.67 695,320.91 3,369,632.12 1,992.19
AS SUBMITTED 1.00 lump sum 1,546,746.62 20% 309,349.32 92,804.80 402,154.12 1,948,900.74 1,948,900.74
628(11) Structural Concrete Injection and Crack Repair
AS EVALUATED 1.00 lump sum 1,546,746.62 20% 309,349.32 92,804.80 402,154.12 1,948,900.74 1,948,900.74
AS SUBMITTED 610.94 sq.m. 1,420,565.06 20% 284,113.01 85,233.90 369,346.91 1,789,911.97 2,929.76
304A(3) Micro-Surfacing
AS EVALUATED 610.94 sq.m. 1,420,565.06 20% 284,113.01 85,233.90 369,346.91 1,789,911.97 2,929.76
AS SUBMITTED 18,275,834.61 3,655,166.92 1,096,550.08 4,751,717.00 23,027,551.61
TOTAL OF PART F
AS EVALUATED 18,275,834.61 3,655,166.92 1,096,550.08 4,751,717.00 23,027,551.61
PART G DRAINAGE AND SLOPE PROTECTION STRUCUTRES
AS SUBMITTED
AS EVALUATED
AS SUBMITTED
TOTAL OF PART G
AS EVALUATED
PART H MISCELLANEOUS STRUCTURES
AS SUBMITTED
AS EVALUATED
AS SUBMITTED
TOTAL OF PART H
AS EVALUATED
PART I PROVISIONAL SUM
AS SUBMITTED
AS EVALUATED
AS SUBMITTED
TOTAL OF PART I
AS EVALUATED
PART J DAYWORK
AS SUBMITTED
AS EVALUATED
AS SUBMITTED
TOTAL OF PART J
AS EVALUATED
AS SUBMITTED 19,802,376.93 3,822,156.40 1,181,226.67 5,003,383.07 24,805,760.00
GRAND TOTAL
AS EVALUATED 19,802,376.93 3,822,156.40 1,181,226.67 5,003,383.07 24,805,760.00

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

KENNY S. AVELLANO FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO


Engineer II Chief, Planning & Design Section Engineer II
Planning and Design Section Planning and Design Section
Date: November 2, 2021
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon


FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Cargo / Service Truck (9-10 mt, 270 Horsepower) 8 31
2 Scaffold Pipes (rental) 720 32
3 Clamp (Rental) 720 33
4 Generator set (300 kW) 1 34
5 Air Compressor (161-185 cfm) 69 hp 1 35
6 Back Hoe 0.80 cu.m. 1 36
7 Dump Truck 10 cu.m. 1 37
8 Portable Mist- Based Sanitation Tent 1 38
9 Thermal Scanner (Rechargeable) 2 39
10 Power Spray w/ Complete Acc. 1 40
11 Concrete Vibrator 2 41
12 Concrete Screeder (5.5 Hp) 1 42
13 Concrete Saw, Blade Ø 14" (7.5 Hp) 1 43
14 Bar Cutter, Single Phase, 25 mm. 1 44
15 Sealer Joint (Gas/Diesel Driven) 1 45
16 Welding Machine (500 A), Electric Driven 2 46
17 Cutting Outfit 1 47
18 Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 48
19 Pay Loader (1.50 cu.m.), LX80-2C 1 49
20 Dump Truck (10 cu.m.) 1 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL 1468 SUB-TOTAL 0
TOTAL 1468
COMPUTATION OF ESTIMATED PROJECT DURATION AS PER DO 44 SERIES OF 2012

PROJECT : OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges,
Quipot Br. (B02945LZ) along Quezon-Batangas Rd

LOCATION : San Antonio, Quezon

AMOUNT: P 25,312,000.00

PROJECT CATEGORY : Bridge

90 Calendar Days for 20,000,000.00 as per D.O. 44 series of 2012


62 Calendar Days for 5,000,000.00 as per D.O. 44 series of 2012

90 - X 90 - 62
=
20,000,000 -15,000,000 20,000,000 - 5,000,000

X = 99.92
SAY 100.00

WORKING DAYS : 100.00 days


UNWORKABLE DAYS : 50.00 days

PROJECT DURATION : 150.00 Calendar Days

Prepared by:

KENNY S. AVELLANO
Engineer II
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : month
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor

Sub - Total for A.1 - As Submitted 0.00


A.2 Labor

Sub - Total for A.2 - As Evaluated 0.00


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

a. Rental Rate (including water & electricity lot 1 12,000.00 12,000.00


consumption)

Sub - Total for B.1 - As Submitted 12,000.00


B.2 Equipment

a. Rental Rate (including water & electricity lot 1 12,000.00 12,000.00


consumption)

Sub - Total for B.2 - As Evaluated 12,000.00


C.1 Total (A.1 + B.1) - As Submitted 12,000.00
C.2 Total (A.2 + B.2) - As Evaluated 12,000.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 12,000.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 12,000.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Monoblock Chair (2 pieces), lot 1 7,500.00 7,500.00


30x48 Plastic Table (1 Piece),
Log Book, Bond Paper & measuring tape 8m.

Sub - Total for F.1 - As Submitted 7,500.00


F.2 Materials

a. Monoblock Chair (2 pieces), lot 1 7,500.00 7,500.00


30x48 Plastic Table (1 Piece),
Log Book, Bond Paper & measuring tape 8m.

Sub - Total for F.2 - As Evaluated 7,500.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 19,500.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 19,500.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1,560.00
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 1,560.00
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 1,053.00
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 1,053.00
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 22,113.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 22,113.00

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the
Engineer
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor

Sub - Total for A.1 - As Submitted 0.00


A.2 Labor

Sub - Total for A.2 - As Evaluated 0.00


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 0.00
C.2 Total (A.2 + B.2) - As Evaluated 0.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 0.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 0.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Monoblock Table pc. 1.00 1,600.00 1,600.00


b. Monoblock Chair pc. 4.00 450.00 1,800.00
c. Bulletin/Cork Board pc. 2.00 320.00 640.00
d. Miscellaneous Office Supplies (Log Book, Pen, Pencil, Marker, lot 1.00 5,000.00 5,000.00
Bond Paper, Measuring Device, etc.)
Sub - Total for F.1 - As Submitted 9,040.00
F.2 Materials

a. Monoblock Table pc. 1.00 1,600.00 1,600.00


b. Monoblock Chair pc. 4.00 450.00 1,800.00
c. Bulletin/Cork Board pc. 2.00 320.00 640.00
d. Miscellaneous Office Supplies (Log Book, Pen, Pencil, Marker, lot 1.00 5,000.00 5,000.00
Bond Paper, Measuring Device, etc.)
Sub - Total for F.2 - As Evaluated 9,040.00
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 9,040.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 9,040.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 723.20
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 723.20
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 488.16
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 488.16
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 10,251.36
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 10,251.36

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer
Unit of Measurement : mo.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Driver 1 120.00 65.41 7,849.20

Sub - Total for A.1 - As Submitted 7,849.20


A.2 Labor
a. Driver 1 120.00 65.41 7,849.20

Sub - Total for A.2 - As Evaluated 7,849.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 7,849.20
C.2 Total (A.2 + B.2) - As Evaluated 7,849.20
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 7,849.20
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 7,849.20
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a.Fuel Diesel (location=distance) ltr 196.00 39.00 7,644.00


b. Diesel Gear Oil ltr 1.00 220.00 220.00
c. Break Fluid ltr 1.00 165.00 165.00

Sub - Total for F.1 - As Submitted 8,029.00


F.2 Materials

a.Fuel Diesel (location=distance) ltr 196.00 39.00 7,644.00


b. Diesel Gear Oil ltr 1.00 220.00 220.00
c. Break Fluid ltr 1.00 165.00 165.00

Sub - Total for F.2 - As Evaluated 8,029.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 15,878.20
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 15,878.20
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 0% of G.1 0.00
I.2 Contractor's Profit (CP) - As Evaluated 0% of G.2 0.00
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 793.91
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 793.91
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 16,672.11
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 16,672.11

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.3(1) Provision of Field Office Staff for the Assistance to the Engineer
Unit of Measurement : mo.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Highly Skilled Labor 1 192.00 75.52 14,499.84
*Note: Number of Hours based on workable days per month
Sub - Total for A.1 - As Submitted 14,499.84
A.2 Labor
a. Highly Skilled Labor 1 192.00 75.52 14,499.84

Sub - Total for A.2 - As Evaluated 14,499.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 14,499.84
C.2 Total (A.2 + B.2) - As Evaluated 14,499.84
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 14,499.84
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 14,499.84
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted 0.00


F.2 Materials

Sub - Total for F.2 - As Evaluated 0.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 14,499.84
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 14,499.84
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1,159.99
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 1,159.99
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 782.99
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 782.99
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 16,442.82
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 16,442.82

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.4(1) Provision of Progress Photographs


Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor

Sub - Total for A.1 - As Submitted 0.00


A.2 Labor

Sub - Total for A.2 - As Evaluated 0.00


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 0.00
C.2 Total (A.2 + B.2) - As Evaluated 0.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 0.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 0.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Developing each 1 15.00 15.00

Sub - Total for F.1 - As Submitted 15.00


F.2 Materials

a. Developing each 1 15.00 15.00

Sub - Total for F.2 - As Evaluated 15.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 15.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 15.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1.20
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 1.20
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 0.81
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 0.81
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 17.01
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 17.01

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.5 Project Billboard / Signboard


Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 8 90.57 724.56
b. Skilled Labor 1 8 65.41 523.28
c. Unskilled Labor 2 8 50.54 808.64

Sub - Total for A.1 - As Submitted 2,056.48


A.2 Labor
a. Foreman 1 8 90.57 724.56
b. Skilled Labor 1 8 65.41 523.28
c. Unskilled Labor 2 8 50.54 808.64

Sub - Total for A.2 - As Evaluated 2,056.48


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 2,056.48
C.2 Total (A.2 + B.2) - As Evaluated 2,056.48
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 2,056.48
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 2,056.48
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. 3/16 x 4 x 8' marine plywood pc. 1 290.00 290.00


b. Good Lumber bd.ft. 48 60.00 2,880.00
c. Project Sign (Tarpaulin) sq.ft. 32 25.00 800.00
d. Assorted Common Nails kg 1 80.00 80.00

Sub - Total for F.1 - As Submitted 4,050.00


F.2 Materials

a. 3/16 x 4 x 8' marine plywood pc. 1 290.00 290.00


b. Good Lumber bd.ft. 48 60.00 2,880.00
c. Project Sign (Tarpaulin) sq.ft. 32 25.00 800.00
d. Assorted Common Nails kg 1 80.00 80.00

Sub - Total for F.2 - As Evaluated 4,050.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,106.48
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,106.48
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 732.78
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 732.78
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 488.52
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 488.52
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 366.39
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 366.39
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 7,694.17
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 7,694.17

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.7(2) Occupational Safety and Health Program


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Safety Practitioner/Officer (Full Time) 1 1200 62.50 75,000.00
b. Health Officer (Full Time) 1 1200 35.00 42,000.00
c. Sanitation Aide (Full Time) 1 1200 35.00 42,000.00

Sub - Total for A.1 - As Submitted 159,000.00


A.2 Labor
a. Safety Practitioner/Officer (Part Time) 1 1200 62.50 75,000.00
b. Health Officer (Full Time) 1 1200 35.00 42,000.00
c. Sanitation Aide (Full Time) 1 1200 35.00 42,000.00

Sub - Total for A.2 - As Evaluated 159,000.00


Name and Capacity No of Unit/s No. of Day/s Daily Rate Amount (Php)
B.1 Equipment
a. Portable Mist- Based Sanitation Tent 1 150.00 78.32 11,748.00
b. Thermal Scanner (Rechargeable) 2 150.00 8.24 1,236.00
c. Power Spray w/ Complete Acc. 1 150.00 27.76 4,164.00

Sub - Total for B.1 - As Submitted 17,148.00


B.2 Equipment
a. Portable Mist- Based Sanitation Tent 1 150.00 78.32 11,748.00
b. Thermal Scanner (Rechargeable) 2 150.00 8.24 1,236.00
c. Power Spray w/ Complete Acc. 1 150.00 27.76 4,164.00

Sub - Total for B.2 - As Evaluated 17,148.00


C.1 Total (A.1 + B.1) - As Submitted 176,148.00
C.2 Total (A.2 + B.2) - As Evaluated 176,148.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 176,148.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 176,148.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Safety Helmet m-day 660.91 0.27 178.45
b. Hand Gloves m-day 660.91 26.67 17,626.47
c. Safety Shoes m-day 660.91 3.29 2,174.39
e. Body Harness m-day 660.91 1.73 1,143.37
g. Facemask m-day 660.91 5.00 3,304.55

Antiseptic and Disinfectant


a. Sanitizing Solution lit 5.00 100.00 500.00
b. Ethyl Alcohol lit 10.00 185.00 1,850.00
c. Disinfectant Spray can 5.00 1,000.00 5,000.00
d. Liquid Hand Soap lit 5.00 200.00 1,000.00

COVID-19 Rapid Antibody Test set 15.00 900.00 13,500.00

Sub - Total for F.1 - As Submitted 46,825.79


F.2 Materials
a. Safety Helmet m-day 660.91 0.27 178.45
b. Hand Gloves m-day 660.91 26.67 17,626.47
c. Safety Shoes m-day 660.91 3.29 2,174.39
e. Body Harness m-day 660.91 1.73 1,143.37
g. Facemask m-day 660.91 5.00 3,304.55

Antiseptic and Disinfectant


a. Sanitizing Solution m-day 5.00 100.00 500.00
b. Ethyl Alcohol m-day 10.00 185.00 1,850.00
c. Disinfectant Spray m-day 5.00 1,000.00 5,000.00
d. Liquid Hand Soap m-day 5.00 200.00 1,000.00

COVID-19 Rapid Antibody Test m-day 15.00 900.00 13,500.00

Sub - Total for F.2 - As Evaluated 46,825.79


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 222,973.79
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 222,973.79
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 17,837.90
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 17,837.90
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 12,040.58
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 12,040.58
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 252,852.27
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 252,852.27

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.8(2) Traffic Management


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Skilled Labor 1 1200 65.41 78,492.00
b. Unskilled Labor 4 1200 50.54 242,592.00

Sub - Total for A.1 - As Submitted 321,084.00


A.2 Labor
a. Skilled Labor 1 1200 65.41 78,492.00
b. Unskilled Labor 4 1200 50.54 242,592.00

Sub - Total for A.2 - As Evaluated 321,084.00


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

a. Barricade Flasher Light (3 Volts, Battery Operated, Amber Color 10 1200 0.65 7,800.00
w/ lifespan consideration of 6 months)

Sub - Total for B.1 - As Submitted 7,800.00


B.2 Equipment

a. Barricade Flasher Light (3 Volts, Battery Operated, Amber Color 10 1200 0.65 7,800.00
w/ lifespan consideration of 6 months)

Sub - Total for B.2 - As Evaluated 7,800.00


C.1 Total (A.1 + B.1) - As Submitted 328,884.00
C.2 Total (A.2 + B.2) - As Evaluated 328,884.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 328,884.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 328,884.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Traffic Cones (@ 3 meters apart) each 38 277.50 10,545.00
b. Bridgework Ahead each 2 1,642.71 3,285.42
b. Lane Status each 2 119.93 239.86
e. Workmen Ahead each 2 51.76 103.52
f. Temporary Hazard Marker (Chervon) sq.ft. 8 61.76 494.08
h. End RoadWork each 2 60.82 121.64
f. Misc. Items (Maintenance & etc.) lot 1 3,486.66 3,486.66

Sub - Total for F.1 - As Submitted 18,276.18


F.2 Materials
a. Traffic Cones (@ 3 meters apart) each 38 277.50 10,545.00
b. Bridgework Ahead each 2 1,642.71 3,285.42
b. Lane Status each 2 119.93 239.86
e. Workmen Ahead each 2 51.76 103.52
f. Temporary Hazard Marker (Chervon) sq.ft. 8 61.76 494.08
h. End RoadWork each 2 60.82 121.64
f. Misc. Items (Maintenance & etc.) lot 1 3,486.66 3,486.66

Sub - Total for F.2 - As Evaluated 18,276.18


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 347,160.18
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 347,160.18
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 27,772.81
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 27,772.81
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 18,746.65
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 18,746.65
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 393,679.64
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 393,679.64

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.9 Mobilization / Demobilization


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor

Sub - Total for A.1 - As Submitted 0.00


A.2 Labor

Sub - Total for A.2 - As Evaluated 0.00


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

a. Mobilization (Low Bed Trailer) 8 20,000.00 160,000.00


not exceed to 1% of Direct Cost

Sub - Total for B.1 - As Submitted 160,000.00


B.2 Equipment

a. Mobilization (Low Bed Trailer) 8 20,000.00 160,000.00


not exceed to 1% of Direct Cost

Sub - Total for B.2 - As Evaluated 160,000.00


C.1 Total (A.1 + B.1) - As Submitted 160,000.00
C.2 Total (A.2 + B.2) - As Evaluated 160,000.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 160,000.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 160,000.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted 0.00


F.2 Materials

Sub - Total for F.2 - As Evaluated 0.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 160,000.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 160,000.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 0% of G.1 0.00
I.2 Contractor's Profit (CP) - As Evaluated 0% of G.2 0.00
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 8,000.00
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 8,000.00
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 168,000.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 168,000.00

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 101(1) Removal of Structures and Obstructions


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

Designation No. of Person No. of Hour/s Hourly Rate Amount


A.1 Labor

a. Construction Foreman 1 28.00 90.57 2,535.96


b. Skilled Laborers 2 28.00 65.41 3,662.96
c. Laborers 8 28.00 50.54 11,320.96

Sub - Total for A.1 - As Submitted 17,519.88


A.2 Labor

a. Construction Foreman 1 28.00 90.57 2,535.96


b. Skilled Laborers 2 28.00 65.41 3,662.96
c. Laborers 8 28.00 50.54 11,320.96

Sub - Total for A.2 - As Evaluated 17,519.88


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Backhoe (0.80 cu.m.) 1 28.00 2,096.00 58,688.00


b. Dump Truck (10 cu.m.) 1 28.00 1,420.00 39,760.00
Minor Tools (10% of Labor Cost) 1,751.99 1,751.99

Sub - Total for B.1 - As Submitted 100,199.99


B.2 Equipment

a. Backhoe (0.80 cu.m.) 1 28.00 2,096.00 58,688.00


b. Dump Truck (10 cu.m.) 1 28.00 1,420.00 39,760.00
Minor Tools (10% of Labor Cost) 1,751.99 1,751.99

Sub - Total for B.2 - As Submitted 100,199.99


C.1 Total (A.1 + B.1) - As Submitted 117,719.87
C.2 Total (A.2 + B.2) - As Evaluated 117,719.87
D.1 Output per hour - As Submitted = 1 lump sum
D.2 Output per hour - As Evaluated = 1 lump sum
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 117,719.87
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 117,719.87

Name and Specification Unit Quantity Unit Cost Amount

F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 117,719.87
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 117,719.87
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 14,126.38
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 14,126.38
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 9,417.59
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 9,417.59
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 7,063.19
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 7,063.19
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 148,327.03
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 148,327.03

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 101(3)a3 Removal of Actual Structures/Obstruction (0.23m thick, PCCP) Unreinforced
Unit of Measurement : sq.m.
Output per hour - As Submitted : 40.00
Output per hour - As Evaluated : 40.00

Designation No. of Person No. of Hour/s Hourly Rate Amount


A.1 Labor

a. Construction Foreman 1 1.00 90.57 90.57


b. Laborers 2 1.00 50.54 101.08

Sub - Total for A.1 - As Submitted 191.65


A.2 Labor

a. Construction Foreman 1 1.00 90.57 90.57


b. Laborers 2 1.00 50.54 101.08

Sub - Total for A.2 - As Evaluated 191.65


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1.00 2,724.80 2,724.80


b. Pay Loader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 0.50 1,420.00 710.00

Sub - Total for B.1 - As Submitted 5,167.80


B.2 Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1.00 2,724.80 2,724.80


b. Pay Loader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 0.50 1,420.00 710.00

Sub - Total for B.2 - As Submitted 5,167.80


C.1 Total (A.1 + B.1) - As Submitted 5,359.45
C.2 Total (A.2 + B.2) - As Evaluated 5,359.45
D.1 Output per hour - As Submitted = 40 sq.m.
D.2 Output per hour - As Evaluated = 40 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 133.99
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 133.99

Name and Specification Unit Quantity Unit Cost Amount

F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 133.99
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 133.99
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 16.08
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 16.08
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 10.72
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 10.72
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 8.04
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 8.04
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 168.82
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 168.82

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 311(1)f1 Portland Cement Concrete Pavement (Unreinforced) - 0.30 m thick, 14 days
Unit of Measurement : sq.m.
Output per hour - As Submitted : 53.67
Output per hour - As Evaluated : 53.67

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor

a. Foreman 1 1 90.57 90.57


b. Skilled Laborers 4 1 65.41 261.64
c. Unskilled Laborer 12 1 50.54 606.48

Sub - Total for A.1 - As Submitted 958.69


Labor

a. Foreman 1 1 90.57 90.57


A.2 b. Skilled Laborer 4 1 65.41 261.64
c. Unskilled Laborer 12 1 50.54 606.48

Sub - Total for A.2 - As Evaluated 958.69


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

a. Concrete Vibrator 2 1 57.17 114.34


b. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
c. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 32.64 32.64
d. Bar Cutter, Single Phase, 25 mm. 1 0.1 105.47 10.55
e. Sealer Joint (Gas/Diesel Driven w/ cold/hot Spray nozzle) 1 0.1 56.37 5.64
Minor Tools (5% of Labor) 1 1 47.93 47.93

Sub - Total for B.1 - As Submitted 756.10


B.2 Equipment

a. Concrete Vibrator 2 1 57.17 114.34


b. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
c. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 32.64 32.64
d. Bar Cutter, Single Phase, 25 mm. 1 0.1 105.47 10.55
e. Sealer Joint (Gas/Diesel Driven w/ cold/hot Spray nozzle) 1 0.1 56.37 5.64
Minor Tools (5% of Labor) 1 1 47.93 47.93

Sub - Total for B.2 - As Evaluated 756.10


C.1 Total (A.1 + B.1) - As Submitted 1,714.79
C.2 Total (A.2 + B.2) - As Evaluated 1,714.79
D.1 Output per hour - As Submitted 53.67
D.2 Output per hour - As Evaluated 53.67
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 31.95
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 31.95
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Reinforcing Steel Bar (Grade 60) kg. 0.7900 49.00 38.71
b. Curing Compound lit. 0.2900 35.00 10.15
c. Asphalt Sealant lit. 0.1800 44.00 7.92
d. Steel Forms, 300mm width l.m. 0.460 105.00 48.30
g. Readymix concrete (3500 psi @ 14 days concrete) bag 0.3000 6,050.00 1,815.00
h. Concrete Saw (diamond blade 14") pc 0.00015 8,000.00 1.20
i. Grease/Tar lit. 0.0094 225.00 2.12
j. Pipe Sleeve, 2" dia. l.m. 0.0094 110.00 1.03

Sub - Total for F.1 - As Submitted 1,924.43


F.2 Materials
a. Reinforcing Steel Bar (Grade 60) kg. 0.7900 49.00 38.71
b. Curing Compound lit. 0.2900 35.00 10.15
c. Asphalt Sealant lit. 0.1800 44.00 7.92
d. Steel Forms, 300mm width l.m. 0.4600 105.00 48.30
g. Readymix concrete (3500 psi @ 14 days bag 0.3000 6,050.00 1,815.00
h. Concrete Saw (diamond blade 14") pc 0.0002 8,000.00 1.20
i. Grease/Tar lit. 0.0094 225.00 2.12
j. Pipe Sleeve, 2" dia. l.m. 0.0094 110.00 1.03

Sub - Total for F.2 - As Evaluated 1,924.43


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,956.38
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,956.38
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 234.77
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 234.77
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 156.51
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 156.51
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 117.38
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 117.38
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 2,465.04
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 2,465.04

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 304A(3) Micro-Surfacing


Unit of Measurement : sq.m.
Output per hour - As Submitted : 75.00
Output per hour - As Evaluated : 75.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Injection) 4 1 65.41 261.64
c. Unskilled Labor (Surface Preparation) 6 1 50.54 303.24

Sub - Total for A.1 - As Submitted 655.45


A.2 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Injection) 4 1 65.41 261.64
c. Unskilled Labor (Surface Preparation) 6 1 50.54 303.24

Sub - Total for A.2 - As Evaluated 655.45


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
a.Equipment for Spreading and Compaction (30% of Materials Cost) lot 1 692.17 692.17

Sub - Total for B.1 - As Submitted 692.17


B.2 Equipment
a.Equipment for Spreading and Compaction (30% of Materials Cost) lot 1 692.17 692.17

Sub - Total for B.2 - As Evaluated 692.17


C.1 Total (A.1 + B.1) - As Submitted 1,347.62
C.2 Total (A.2 + B.2) - As Evaluated 1,347.62
D.1 Output per hour - As Submitted 75.00
D.2 Output per hour - As Evaluated 75.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 17.97
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 17.97
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. BD-2000 = 209 Liters Resin + 1,280 kg. Bulk Bag Light Grey Color kit 0.0029 780,000.00 2,262.00
(330 - 360 sq.m. coverage)
b. Consumables (2% of Materials Cost) 45.24

Sub - Total for F.1 - As Submitted 2,307.24

F.2 Materials
a. BD-2000 = 209 Liters Resin + 1,280 kg. Bulk kit 0.0029 780,000.00 2,262.00
(330 - 360 sq.m. coverage)
b. Consumables (2% of Materials Cost) 45.24

Sub - Total for F.2 - As Evaluated 2,307.24


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 2,325.21
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 2,325.21
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 279.03
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 279.03
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 186.02
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 186.02
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 139.51
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 139.51
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 2,929.76
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 2,929.76

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 414(1) Forms and Falsework


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 360 90.57 32,605.20
b. Skilled Labor 2 360 65.41 47,095.20
c. Unskilled Labor 4 360 50.54 72,777.60

Sub - Total for A.1 - As Submitted 152,478.00


A.2 Labor
a. Foreman 1 360 90.57 32,605.20
b. Skilled Labor 2 360 65.41 47,095.20
c. Unskilled Labor 4 360 50.54 72,777.60

Sub - Total for A.2 - As Evaluated 152,478.00


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
a. Scaffold Pipes (rental) pc. 720 150.00 108,000.00
b. Clamp (Rental) pc. 720 40.00 28,800.00
Minor Tools (10% of Labor) lot 1 15,247.80 15,247.80

Sub - Total for B.1 - As Submitted 152,047.80


B.2 Equipment
a. Scaffold Pipes (rental) pc. 720 150.00 108,000.00
b. Clamp (Rental) pc. 720 40.00 28,800.00
Minor Tools (10% of Labor) lot 1 15,247.80 15,247.80

Sub - Total for B.2 - As Evaluated 152,047.80


C.1 Total (A.1 + B.1) - As Submitted 304,525.80
C.2 Total (A.2 + B.2) - As Evaluated 304,525.80
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 304,525.80
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 304,525.80
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Marine Plywood 3/4"x 4'x8' pc. 120 1,380.00 165,600.00
b. Waterproof Tarpaulin Lightweight Blue (6mx12m.) pc. 20 3,500.00 70,000.00

Sub - Total for F.1 - As Submitted 235,600.00


F.2 Materials
a. Marine Plywood 3/4"x 4'x8' pc. 120 1,380.00 165,600.00
b. Waterproof Tarpaulin Lightweight Blue (6mx12m.) pc. 20 3,500.00 70,000.00

Sub - Total for F.2 - As Evaluated 235,600.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 540,125.80
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 540,125.80
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 64,815.10
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 64,815.10
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 43,210.06
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 43,210.06
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 32,407.55
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 32,407.55
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 680,558.51
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 680,558.51

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 416(1)a Carbon Fiber (1 Layer)


Unit of Measurement : sq.m.
Output per hour - As Submitted : 2.50
Output per hour - As Evaluated : 2.50

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Surface Preparation) 1 1 65.41 65.41
c. Skilled Labor (Carbon Fiber Setting) 2 1 65.41 130.82
d. Unskilled Labor (Surface Preparation) 4 1 50.54 202.16
e. Unskilled Labor (Carbon Fiber Setting) 4 1 50.54 202.16

Sub - Total for A.1 - As Submitted 691.12


A.2 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Surface Preparation) 1 1 65.41 65.41
c. Skilled Labor (Carbon Fiber Setting) 2 1 65.41 130.82
d. Unskilled Labor (Surface Preparation) 4 1 50.54 202.16
e. Unskilled Labor (Carbon Fiber Setting) 4 1 50.54 202.16

Sub - Total for A.2 - As Evaluated 691.12


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
a. Generator set (300 kW) 1 1 872.87 872.87
b. Air Compressor (161-185 cfm) 69 hp 1 1 502.00 502.00
c.. Miscellaneous tools (Disc Grinder) 10% of Labor lot 1 69.11 69.11

Sub - Total for B.1 - As Submitted 1,443.98


B.2 Equipment
a. Generator set (300 kW) 1 1 872.87 872.87
b. Air Compressor (161-185 cfm) 69 hp 1 1 502.00 502.00
c.. Miscellaneous tools (Disc Grinder) 10% of Labor lot 1 69.11 69.11

Sub - Total for B.2 - As Evaluated 1,443.98


C.1 Total (A.1 + B.1) - As Submitted 2,135.10
C.2 Total (A.2 + B.2) - As Evaluated 2,135.10
D.1 Output per hour - As Submitted 2.50
D.2 Output per hour - As Evaluated 2.50
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 854.04
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 854.04
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Carbon Fiber Sheet, 300gsm (1 layer) m. 1.05 10,168.00 10,676.40
b. Epoxy Resin Adhesive kg. 0.40 1,950.00 780.00
c. Epoxy Primer kg. 0.30 1,700.00 510.00
d. Epoxy Putty kg. 0.45 1,200.00 540.00

Sub - Total for F.1 - As Submitted 12,506.40


F.2 Materials
a. Carbon Fiber Sheet, 200gsm (1 layer) m. 1.05 7,650.00 8,032.50
b. Epoxy Resin Adhesive kg. 0.40 1,950.00 780.00
c. Epoxy Primer kg. 0.30 1,700.00 510.00
d. Epoxy Putty kg. 0.45 1,200.00 540.00

Sub - Total for F.2 - As Evaluated 9,862.50


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 13,360.44
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 10,716.54
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 1,603.25
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 1,285.98
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1,068.84
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 857.32
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 801.63
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 642.99
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 16,834.16
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 16,834.16

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 403(4)a1 Structural Steel, Furnished and Fabricated (Grade 36)
Unit of Measurement : kg.
Output per hour - As Submitted : 56.00
Output per hour - As Evaluated : 56.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor 3 1 65.41 196.23
c. Unskilled Labor 6 1 50.54 303.24

Sub - Total for A.1 - As Submitted 590.04


A.2 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor 3 1 65.41 196.23
c. Unskilled Labor 6 1 50.54 303.24

Sub - Total for A.2 - As Evaluated 590.04


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
a. Welding Machine (500 A), Electric Driven 2 1.00 539.00 1,078.00
b. Cutting Outfit 1 1.00 45.45 45.45
Minor Tools (Grinding Machine Etc.) 10% of Labor Cost 59.00

Sub - Total for B.1 - As Submitted 1,182.45


B.2 Equipment
a. Welding Machine (500 A), Electric Driven 2 1.00 539.00 1,078.00
b. Cutting Outfit 1 1.00 45.45 45.45
Minor Tools (Grinding Machine Etc.) 10% of Labor Cost 59.00

Sub - Total for B.2 - As Evaluated 1,182.45


C.1 Total (A.1 + B.1) - As Submitted 1,772.49
C.2 Total (A.2 + B.2) - As Evaluated 1,772.49
D.1 Output per hour - As Submitted 56.00
D.2 Output per hour - As Evaluated 56.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 31.65
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 31.65
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Structural Steel MS Plate kg. 0.56 51.00 28.56
b. RSB (grade 40, 16 mm. Dia.) kg. 0.12 49.00 5.88
c. Angle Bar kg. 0.27 60.00 16.20
d. Square Bar kg. 0.06 60.00 3.60
e. Welding Rod kg. 0.05 110.00 5.50
f. Oxy/Acetylene set 0.00050 2,500.00 1.25
g. Cork Expansion Dam Joint Filler pc. 0.00927 655.00 6.07
Miscellaneous (1% of Materials Cost) 0.67
Sub - Total for F.1 - As Submitted 67.73
F.2 Materials
a. Structural Steel MS Plate kg. 0.56 51.00 28.56
b. RSB (grade 40, 16 mm. Dia.) kg. 0.12 49.00 5.88
c. Angle Bar kg. 0.27 60.00 16.20
d. Square Bar kg. 0.06 60.00 3.60
e. Welding Rod kg. 0.05 110.00 5.50
f. Oxy/Acetylene set 0.00050 2,500.00 1.25
g. Cork Expansion Dam Joint Filler pc. 0.00927 655.00 6.07
Miscellaneous (1% of Materials Cost) 0.67
Sub - Total for F.2 - As Evaluated 67.73
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 99.38
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 99.38
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 11.93
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 11.93
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 7.95
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 7.95
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 5.96
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 5.96
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 125.22
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 125.22

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 416(1)e Carbon Fiber Plate


Unit of Measurement : sq.m.
Output per hour - As Submitted : 0.15
Output per hour - As Evaluated : 0.15

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Surface Preparation) 1 1 65.41 65.41
c. Skilled Labor (Carbon Fiber Plate Setting) 2 1 65.41 130.82
d. Unskilled Labor (Surface Preparation) 4 1 50.54 202.16
e. Unskilled Labor (Carbon Fiber Plate Setting) 4 1 50.54 202.16

Sub - Total for A.1 - As Submitted 691.12


A.2 Labor
a. Foreman 1 1 90.57 90.57
b. Skilled Labor (Surface Preparation) 1 1 65.41 65.41
c. Skilled Labor (Carbon Fiber Plate Setting) 2 1 65.41 130.82
d. Unskilled Labor (Surface Preparation) 4 1 50.54 202.16
e. Unskilled Labor (Carbon Fiber Plate Setting) 4 1 50.54 202.16

Sub - Total for A.2 - As Evaluated 691.12


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
a. Generator set (300 kW) 1 1 872.87 872.87
b. Air Compressor (161-185 cfm) 69 hp 1 1 502.00 502.00
c.. Miscellaneous tools (Disc Grinder) 10% of Labor lot 1 69.11 69.11

Sub - Total for B.1 - As Submitted 1,443.98


B.2 Equipment
a. Generator set (300 kW) 1 1 872.87 872.87
b. Air Compressor (161-185 cfm) 69 hp 1 1 502.00 502.00
c.. Miscellaneous tools (Disc Grinder) 10% of Labor lot 1 69.11 69.11

Sub - Total for B.2 - As Evaluated 1,443.98


C.1 Total (A.1 + B.1) - As Submitted 2,135.10
C.2 Total (A.2 + B.2) - As Evaluated 2,135.10
D.1 Output per hour - As Submitted 0.15
D.2 Output per hour - As Evaluated 0.15
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 14,234.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 14,234.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Carbon Fiber Plates, 20m. X 0.05m. sq.m. 1 115,829.00 115,829.00
b. Epoxy Adhesive kg. 11.15 3,970.28 44,268.62
c. Epoxy Primer kg. 5 1,700.00 8,500.00

Sub - Total for F.1 - As Submitted 168,597.62


F.2 Materials
a. Carbon Fiber Plates, 20m. X 0.05m. sq.m. 1 115,829.00 115,829.00
b. Epoxy Adhesive kg. 11.15 3,970.28 44,268.62
c. Epoxy Primer kg. 5 1,700.00 8,500.00

Sub - Total for F.2 - As Evaluated 168,597.62


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 182,831.62
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 182,831.62
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 21,939.79
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 21,939.79
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 14,626.53
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 14,626.53
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 10,969.90
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 10,969.90
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 230,367.84
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 230,367.84

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon


DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 628(9) Special Anti Corrosion Paint


Unit of Measurement : sq.m.
Output per hour - As Submitted : 12.000
Output per hour - As Evaluated : 12.000

Designation No. of Person No. of Hour/s Hourly Rate Amount


A.1 Labor (including excavation)

a. Construction Foreman 1 1.00 90.57 90.57


b. Skilled Laborers 4 1.00 65.41 261.64
c. Laborers 6 1.00 50.54 303.24

Sub - Total for A.1 - As Submitted 655.45


A.2 Labor

a. Construction Foreman 1 1.00 90.57 90.57


b. Skilled Laborers 4 1.00 65.41 261.64
c. Laborers 6 1.00 50.54 303.24

Sub - Total for A.2 - As Evaluated 655.45


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Generator Set (300KW) 1 1.00 872.87 872.87


b. Grinding Machine and Accessories 1 1.00 75.38 75.38
c. Minor Tools (10% of Labor) 1 1.00 65.55 65.55

Sub - Total for B.1 - As Submitted 1,013.80


B.2 Equipment

a. Generator Set (300KW) 1 1.00 872.87 872.87


b. Grinding Machine and Accessories 1 1.00 75.38 75.38
c. Minor Tools (10% of Labor) 1 1.00 65.55 65.55

Sub - Total for B.2 - As Submitted 1,013.80


C.1 Total (A.1 + B.1) - As Submitted 1,669.25
C.2 Total (A.2 + B.2) - As Evaluated 1,669.25
D.1 Output per hour - As Submitted = 12 sq.m.
D.2 Output per hour - As Evaluated = 12 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 139.10
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 139.10
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Special Anti Corrosion Paint (2 Coats) sq.m. 2.06 700.00 1,442.00

Sub - Total for F.1 - As Submitted 1,442.00


F.2 Materials

a. Special Anti Corrosion Paint (2 Coats) sq.m. 2.06 700.00 1,442.00

Sub - Total for F.2 - As Evaluated 1,442.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,581.10
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,581.10
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 189.73
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 189.73
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 126.49
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 126.49
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 94.87
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 94.87
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,992.19
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,992.19

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section
OO1: Ensure Safe and Reliable National Road System, Bridge - Retrofitting/ Strengthening of Permanent Bridges, Quipot Br. (B02945LZ) along Quezon-Batangas Rd

San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 628(11) Structural Concrete Injection and Crack Repair


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 360 90.57 32,605.20
b. Skilled Labor (Injection) 4 360 65.41 94,190.40
c. Unskilled Labor (Surface Preparation) 4 360 50.54 72,777.60

Sub - Total for A.1 - As Submitted 199,573.20


A.2 Labor
a. Foreman 1 360 90.57 32,605.20
b. Skilled Labor (Injection) 4 360 65.41 94,190.40
c. Unskilled Labor (Surface Preparation) 4 360 50.54 72,777.60

Sub - Total for A.2 - As Evaluated 199,573.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
a. Generator set (300 kW) 1 280 872.87 244,403.60
b. Air Compressor (161-185 cfm) 69 hp 1 280 502.00 140,560.00
c.. Miscellaneous tools (Disc Grinder) 10% of Labor lot 1 19,957.32 19,957.32

Sub - Total for B.1 - As Submitted 404,920.92


B.2 Equipment
a. Generator set (300 kW) 1 280 872.87 244,403.60
b. Air Compressor (161-185 cfm) 69 hp 1 280 502.00 140,560.00
c.. Miscellaneous tools (Disc Grinder) 10% of Labor lot 1 19,957.32 19,957.32

Sub - Total for B.2 - As Evaluated 404,920.92


C.1 Total (A.1 + B.1) - As Submitted 604,494.12
C.2 Total (A.2 + B.2) - As Evaluated 604,494.12
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 604,494.12
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 604,494.12
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Epoxy Compound for injection, kg. 138.99 3,350.00 465,616.50
Low Viscosity (.35kg./sq.m.)
b. Epoxy Putty (0.25kg/sq.m.) kg. 99.28 1,200.00 119,136.00
c. Injection Set (ave. spacing 0.50m.) no. 1300 275.00 357,500.00

Sub - Total for F.1 - As Submitted 942,252.50


F.2 Materials
a. Epoxy Compound for injection, kg. 138.99 3,350.00 465,616.50
Low Viscosity (.35kg./sq.m. of slab)
b. Epoxy Putty (0.25kg/sq.m. of slab) kg. 99.28 1,200.00 119,136.00
c. Injection Set (ave. spacing 0.50m.) no. 1300 275.00 357,500.00

Sub - Total for F.2 - As Evaluated 942,252.50


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,546,746.62
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,546,746.62
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 185,609.59
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 185,609.59
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 123,739.73
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 123,739.73
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 92,804.80
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 92,804.80
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,948,900.74
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,948,900.74

Prepared by: Checked/Reviewed by:

KENNY S. AVELLANO CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
Planning and Design Section Planning and Design Section