Professional Documents
Culture Documents
1996 - ABB Review Article Bremen
1996 - ABB Review Article Bremen
1996 - ABB Review Article Bremen
L d/ 2
1 2 + 3
6
7 8 9
CF Cf
A B
CD
121 kV
112 kV 13 Y 16 2/3 Hz
50 Hz
Y D 5
LF Rf Lf 12 ×
L d/ 2 12
-
11/23 5/13
10
11
Basic circuit diagram of the 100-MW static frequency link of Stadtwerke Bremen 1
them. In recent decades, the increasing Static traction power links built in the past changing electrical energy between a
reliability of power semiconductor devices, have featured converter units with a rating 16 2⁄3-Hz and 50-Hz system; the converter
and particularly the successful introduction no higher than about 15 MVA. ABB recent- was to be built with GTO thyristors in series
of gate turn-off (GTO) thyristors, has ly took a first step towards higher ratings connection and have a transmission rating
made static converter installations the with the 2 × 25-MVA installation for Swiss of up to 100 MW in both directions. The
preferred option. The benefits they offer are Federal Railway’s converter station at Giu- feasibility study showed that further devel-
as follows: biasco, in southern Switzerland. This instal- opment of the GTO thyristors, their series
• An improvement in efficiency of about 5 lation was placed in commercial operation connection and use of an innovative hard
percent over the entire power range [2] in 1994 [1, 3]. driven gate unit [4], would allow an econ-
• Lower first-time costs due to the elimin- omical static frequency link to be built that
ation of the costly foundations for rotat- satisfies these conditions.
ing installations A single converter with high rating The main technical data of the Bremen
• Longer intervals between maintenance, for Bremen frequency link are given in Table 1. The
plus shorter downtimes, resulting in In 1991, Stadtwerke Bremen AG awarded installation consists of a single converter
higher availability ABB Power Generation and ABB Industrie rated at 100 MW/MVA. This tremendous
• Modular design of the components, AG a contract to study the feasibility of leap in power rating was made possible
making the equipment easier to service building a high-power converter for ex- by several innovations in GTO thyristor
16 2⁄3-Hz
system redundancy is integrated in the converter
Nominal operating voltage (100 MVA) 121 kV itself.
Operating voltage range 97 – 123 kV
Operating frequency range 16 2⁄3 Hz ± 2 %
Plan view of the frequency link (ground floor of the converter building) 2
8 L 210
T 12 T 13
12 14 12
6 4 3 1
M P M P
10 7
9
13 5 2
11
L 401 L 433
T 11 T 01
Z 50
1 2 3 4
verter transformers. Also shown in 1 is the equipment are accommodated in a two- Transparency and good access to the
filter and compensation equipment for the floor building. All the capacitor banks are station components was given a high prior-
three-phase AC network and the DC link, also located in this building to protect them ity during the planning. In this respect, the
plus the main overvoltage protection gear from pollution caused by the steelworks installation benefits in full from the inherent
and the equipment for protecting the and from salinity in the air, a consequence advantages of the converter’s modular de-
station in the event of ‘shoot-through’. The of the installation’s site, which is close to sign: ease of maintenance, low service
voltage and frequency of the power system Germany’s North Sea coastline. The trans- costs, short repair times in the event of
operated by Stadtwerke Bremen AG re- formers, compensating coils, smoothing equipment failure, all of which add up to
main practically constant. In the traction reactors and filter coils are installed in front high availability. The room in which the con-
power supply, on the other hand, both the of the building 2 , 3 . verter on the 16 2⁄3-Hz side is installed has
voltage (97–123 kV) and the frequency The layout of the rooms in the 54 m by been dimensioned to ensure good access
(16.3–17.0 Hz) fluctuate considerably in 15 m large building is practically the same to all the components. Half of the converter
normal operation. The nominal voltage and on the ground and upper floors, since the modules and the voltage-limiting modules
nominal current of the DC link are 10 kV main components (both converter units, are on each floor of the building.
and 10.5 kA, respectively. the DC link capacitors and the common The control system cubicles are situated
The new installation is located directly turn-off circuits) are evenly divided between on the top floor, in a central position to en-
behind the 110-kV substation of Stadt- the two floors and arranged identically. The sure short cables to the power com-
werke Bremen AG and immediately next to chosen configuration ensures that the con- ponents. Also on the top floor is the MMI
German Railway’s 110-kV substation. The necting buses are kept as short as pos- station for local control.
converter and the control and monitoring sible. The transformers as well as the com-
XT IB Z Bk
+ I B maxX T
GTO
PB
∆U T QB B
_ Ud U Bi UB SB
~
P ∆UT +
QB
C
0
- -
E F A
ust δ
a
U Bi max U Bi U B
Principle of operation of the GTO thyristor converter 4
δ IB
a Equivalent circuit
E DC voltage link
F Traction power supply
Ud DC voltage
UBi Internal converter voltage
XT Short-circuit reactance of 16 2⁄3-Hz transformer PB + -
∆UT Voltage drop across XT
b
UB Traction power supply voltage at connecting point
ZBk Short-circuit impedance of traction power supply
PB , QB , SB Power fed into 16 2⁄3-Hz system
b Simplified vector diagram of GTO thyristor converter
IB Output current of GTO thyristor converter
ust , δ Output variables of control system A, B, C Defined operating points
pensation, filter and smoothing reactors are area). This defines the voltage drop ∆UT The PQ diagram representing the 16 2⁄3-
all located outside of the building, but close and with it the amplitude and phase of the Hz side 5 corresponds to the defined
to their associated power components. current IB. power data (Table 2). The circle for UB =
The availability of reactive power is li- 121 kV includes the three specified oper-
mited by the maximum internal voltage that ating points A, B and C, and corresponds
Principle of operation can be set. This is defined by the direct to the maximum current allowed for the
and equipment layout on the voltage of the DC link and the converter GTO thyristor converter. This also deter-
16 2⁄3-Hz side control procedure described in the follow- mines the maximum power at a lower rail-
The direct voltage of the DC link is kept ing. In connection with this, it should be way network voltage. In the overexcited
constant by the converter on the three- noted that the restrictions on the switching range, the power limit is defined at point B
phase AC side. The GTO thyristor converter time do not allow the full control voltage ust by the maximum possible converter volt-
generates an internal voltage with freely ad- to be utilized (the maximum control voltage age.
justable amplitude and phase and a fre- factor is 0.96). Since an additional antiparallel thyristor
quency which is determined by the inter- The apparent power SB is limited by the converter with the same power rating is in-
connected operation. The reference quan- maximum current IB that can be conducted stalled, the symmetrical operating points
tities for the manipulated variables of the by the GTO converter and the converter A’, B’, C’ are valid for the energy flow from
converter are the voltage and phase relation transformer (small circle in 4b ). Whereas in the 16 2⁄3-Hz side to the 50-Hz side.
at the tie to the traction power supply. the case of the transformer this limit has
The vector diagram in 4b illustrates the only thermal origins, in the case of the con-
principle of operation of the converter verter consideration also has to be given to Control method and output voltage
with GTO thyristors. A key role is played the turn-off capability. In addition, the active The proven PWM (pulse width modulation)
by the short-circuit reactance XT of the power limits (the perpendicular borders of method was chosen for the control, this
single-phase converter transformer 4a . the grey area) depend on the design of the method being used widely today for drive
The internal converter voltage UBi can be infeed circuit (thyristor converter, etc) on systems. The switching commands for the
freely chosen within certain limits (grey the three-phase AC side. individual phase modules (U-modules) are
verter ensures such that this causes no ance was attached to the verification of the several other tests were carried out. These
damage. Besides, the integrated preventive components and subassemblies used in it. included:
measures ensure that protection firing This was carried out by simulation with • Tests to determine what happens in the
occurs on only very rare occasions. highly sophisticated models and by labora- high-frequency range during transient
The GTO thyristor converter has also tory testing of the different parts of the in- faults in the traction power system.
been designed to withstand faults in the stallation. • Impulse current tests to verify that no
event of failure of the protection system. Al- The program used for the simulation mechanical damage is caused to the
though all of the semiconductor devices was a new one with improved models of components in the event of all the pro-
(GTO thyristors and diodes) in a defective the power semiconductors. The par- tection stages failing.
phase can be destroyed by the full fault ameters were obtained from special • Further impulse current tests to verify
current flowing through a central fault lo- measurements carried out on the hard- that the characteristic data of the semi-
cation, there will be neither mechanical nor ware. In this way it was possible, for conductor devices do not change even
thermal secondary damage as a result of example, to verify the shoot-through and after as many as 100 instances of pro-
this. No plasma is formed and no com- protection firing within the context of the tection firing.
ponents will explode. overall installation and the power systems. • An endurance test lasting longer than
In addition, the influence of the component 100 h under the following conditions:
Verification tolerances could be clarified and worst- 150 % rated current, 120 % rated volt-
Since the GTO thyristor converter in case tests could be carried out. age, 150 % nominal frequency and zero
Bremen is the first of its kind and features Besides the type-tests, which were per- redundancy [4].
largely new technologies, special import- formed in accordance with the standards,
1.25
a
p.u. u hp
ust
u1
0
u hm
–1.25
1.25 u Bi b
p.u.
ust
–1.25
ΦA
50-Hz-side converter
and compensation equipment
Power is fed into the system from the
t1 v2
Stadtwerke Bremen grid via a line-com-
mutated 12-pulse thyristor converter, this
Hierarchical structure of the supervisory control system 11 A negative reverse current is applied to the
defective inverter valve, which is turned off
A Power plant belonging to Stadtwerke Bremen
B Load dispatching center of Stadtwerke Bremen as a result. Approximately one power sys-
C Frequency link control system tem period is required for the entire turn-off
D Substation belonging to Stadtwerke Bremen
process. After a short time of about 1 s,
E Substation belonging to German Railway
F Filter which is needed to restore the turn-off
function to its original status, transmission
MMI Man-machine interface with DEC workstation based on ALPHA processor
RD Remote diagnostics starts up again automatically. The func-
PSR Programmable high-speed controller (control and protection) tional availability of the common turn-off
VBE Valve base electronics (50-Hz and 16 2/3-Hz sides)
TM, GM Failure monitoring, recording of thyristor and GTO thyristor converter statuses circuit is monitored continuously.
SLK Common turn-off circuit
DC DC voltage link
electronics) into electrical firing pulses. The In the case of the thyristor converter, this be selected as required. The installation
valve base electronics also monitors, with electronics package also controls the com- itself is unattended.
the help of return signals from the thyristor mon turn-off circuit. Return signals enable Control and protection of the frequency
electronics, the redundancy of the series- the controller to quickly identify com- link are based on ABB’s programmable
connected semiconductor devices, pro- mutation failures when the converter is op- high-speed control system, PSR2 [5].
ducing an alarm or trip signal whenever the erating in inverter mode. PSR2 was developed especially for com-
level of redundancy is reduced. Semicon- plex power electronics systems, making it
ductor devices which have failed are ident- the ideal solution for the Bremen link. It
ified and can be replaced the next time rou- Control and monitoring system combines a high processing speed with an
tine maintenance is carried out. The installation is controlled and monitored extremely user-friendly graphic program-
The overvoltage limiter in the DC link by a S.P.I.D.E.R. MicroSCADA system run ming language (FUPLA 2). The combination
of the GTO thyristor converter is also con- on an ALPHA workstation 11 . This system, of these two features ensures a high level
trolled by the valve base electronics. The which also records status changes and dis- of operational flexibility. Both the graphic
same electronics is further responsible turbances, can be operated from a local programming interface of the system and
for high-speed detection (in redundant control room, from the nearby Mittelbüren S.P.I.D.E.R. MicroSCADA can be accessed
mode) of shoot-throughs and for tripping power plant, or from Stadtwerke Bremen’s over a telephone line for diagnostics pur-
the protection firing of the GTO thyristor load dispatching center approximately poses.
converter. 20 km away. The operating authority can The control system is responsible for se-
Basic circuit diagram of the control concept adopted for the 100-MW static frequency link 12
+
A B
112 kV 121 kV
50 Hz Y 16 2/3 Hz
ST MGTO
α
Sync Sync
PLL PLL
α δ U st
Id
Control Control UB
Ud
50 Hz 16 2/3 Hz
IB
Commissioning
Cubicles containing the control system for the Bremen static frequency link 13 During commissioning, high priority was
given to step-by-step verification of the
1 Processing and interface units of PSR controller
correct electrical, thermal and mechanical
2 Modulator of converter and I/O units on 16 ⁄3-Hz side
3 Gate control unit of thyristor converter and interface for fiber-optic cables design of all parts of the installation. After
4 Various monitoring and supply units all the standard pre-commissioning tests
5 Local control panel
had been carried out (voltage tests, tests
on the control system and protection, etc),
quential start-up and shut-down of the to measure the traction power system fre- the subsystems were tested in the follow-
installation as well as for ensuring stable quency. ing order:
operation 12 . The protection is designed with two • No-load test, 50-Hz infeed
The main control task on the 50-Hz side channels for full redundancy. If a system The filter and compensation equipment,
is to keep the DC link voltage constant. To fails as the result of a hardware fault, its converter transformer, thyristor con-
optimize the dynamic response and for tripping channels are automatically block- verter and DC link had voltage applied to
protection reasons, a configuration with ed. The installation protection as a whole is them for the first time. Converter control
cascade controller, superimposed voltage not affected by this. The operating staff are system components (eg, the triggering
regulator and subordinate DC current con- informed of the fault and of the defective equipment) were tested by means of a
troller was chosen. Control on this side also equipment involved via the man-machine high-ohm converter load.
includes the switching of the thyristor con- interface. Replacement of the hardware, • Short-circuit test, 50-Hz infeed
verters when the power is reversed. As parameterization and testing of the protec- A continuous test at the maximum direct
with HVDC converter stations, the trigger- tion functions can be carried out for every current of 10.5 kA was carried out to
ing equipment is synchronized by means of protection system with the installation still verify the correct thermal design of all
a phase-locked loop (PLL). in operation. the subsystems, and particularly the 50-
The current (IB) and voltage (UB) Hz cooling plant. Also tested was the
measured on the 16 2⁄3-Hz traction power control, including the supervisory control
side are used to calculate the active and Design and verification system of the thyristor converter.
reactive power. Active power is controlled The Bremen frequency link was designed • No-load test, GTO thyristor converter
according to a load-frequency character- and verified with the help of three tools: The voltage formed by the GTO thyristor
istic, and reactive power on the basis of a • Analytical software converter voltage was tested initially with
voltage/reactive power curve. The pulse- • Simulation software a reduced DC link voltage and with an
width modulator is synchronized by means • ABB simulator (with 50-W scale, for the open circuit-breaker on the 16 2⁄3-Hz
of a phase-locked loop, which is also used physical simulation) side.
A Power transmitted to traction power supply: 121 kV, 30 MW, 20 MVAr underexcited
B Tripping of thyristor converter, automatic switchover to phase-shift mode
C 50-Hz side disconnected: phase-shift mode with 20 MVAr underexcited Authors’ addresses
D Automatic reclosure of 50-Hz side, automatic active power start-up
Rüdiger Boeck
uB Traction power supply voltage Stadtwerke Bremen AG
iB Traction power supply current Theodor-Heuss-Allee 20
ud DC link voltage 10 kV, 1 scale div = 1.3 kV
id DC link current D-28215 Bremen
Germany
Telefax: +49 421 359 2081
Osvin J. Gaupp
uB Peter Dähler
Eugen Bärlocher
Johannes Werninger
ABB Industrie AG
iB CH-5300 Turgi
Switzerland
id
Plinio Zanini
ABB Power Generation Ltd.
100 ms P.O. box
A C A
CH-5401 Baden
B D t Switzerland
Telefax: +41 56 466 6681