METHOD STATEMENT FOR INSTALLATION OF FIRE HOSE CABINETS, HOSE
RACK, HOSE REEL & EXTINGUISHERS
Join for Latest Articles
Enter your email address & Click Join: METHOD STATEMENT FOR INSTALLATION OF FIRE HOSE CABINETS, HOSE RACK, HOSE REEL &
EXTINGUISHERS.
Following tools shall be required for the installation of hose reel cabinets/racks and extinguishers.
JOIN Portable Hand tools
Portable Drill machines
Portable Grinding machine
Gas Cutting set
The Fire Hose Cabinets, Hose Racks, Reels & Extinguishers shall be inspected, handled & stored properly upon receipt
at site.
All materials shall be stored in a place free of water, dust & adequately covered to avoid any kind of damages.
While unloading, shifting and storage, it shall be ensured that there are no transit damages.
Any discrepancies, damage etc., found will be notified and reported to QA/QC engineer & Engineer in charge – Plumbing
for further action.
Popular Categories Materials found not suitable for site use will be removed from site immediately & replaced by appropriate material.
Civil Method Statements (81) INSTALLATION PROCEDURES FOR HOSE REEL CABINETS
Electrical Method Statements (44)
Prior to start of installation it shall be ensured that the shop drawings including coordination drawings of the respective
Fire Fighting Systems (17)
area are approved. The locations of the fire cabinets shall also be shown on the Architectural drawings.
HVAC Method Statements (43)
Occupational Health and Safety (23) It shall be ensured that the area is released to proceed with MEP installations.
Oil & Gas Systems (12)
It shall be ensured that the Fire Hose Cabinets, Hose Reels & extinguishers are as per the approved material submittal &
Plumbing Method Statements (36)
have been inspected & approved.
Technical Guides (31)
Testing & Commissioning (59) INSTALLATION OF SURFACE MOUNTED FIRE HOSE CABINETS
Prior to start of installation it shall be ensured that the wall has been painted & released to proceed with the installation.
Popular Tags The location of the fire hose cabinet shall be marked as per the approved shop drawings.
AV System block work method statement block work
procedure CCTV ceramic floor tiles Clean Agent System The height of installation of the cabinets shall be in line with the civil defense approved drawing.
Commissioning COMMISSIONING PROCEDURE Dampers
Demolition Works Drainage piping Electric Water The Fire hose cabinets shall be installed in place using four 10mm approved anchors & bolts, ensuring the door will open
Heaters excavation safe work Fire Dampers Fire 180 deg without blocking any valves.
Fighting System Fire Suppression System HVAC
Ductwork HVAC Method Statement Installation INSTALLATION OF HOSE RACK FOR SURFACE MOUNTED CABINETS
Installation Method Statement installation Procedure
Lightning Protection System Method Of Statement The Fire Hose rack shall be fixed inside the cabinet through a landing valve supplied with the hose rack.
method statement Method Statement For Testing &
Commissioning Precommissioning Precommissioning &
Commissioning Safe Method of Statement Safe Method The piping connection to the hose rack landing valve shall be as per civil defense approved approved shop drawings,
Statement safe work for excavation safe work method pipe penetrations to be properly sealed.
of statement Safe Work Method Statement Sanitary
Wares SMDB's Specifications swimming pool civil works Labelling & identification shall be provided to the equipment in English & Arabic.
SWMS Testing & Commissioning Testing &
Commissioning Method Statement Testing and INSTALLATION OF HOSE REEL FOR SURFACE MOUNTED CABINETS
Commissioning Tower Crane Foundation UPS System
UPS Testing Procedure Variable Frequency Drives water The Hose reel shall be installed inside the fire cabinet utilizing the existing brackets in the cabinet. Hose reel shall open
supply piping
fully & easily in all directions by just pulling the hose nozzle without even touching the reel.
The piping connection to the hose reel shall be as per civil defense approved shop drawings.
You May Like!
INSTALLATION OF FIRE EXTINGUISHERS FOR SURFACE MOUNTED CABINETS
Two approved fire extinguishers shall be placed inside the fire hose cabinets as per approved shop drawings & material
submittal.
Prior to start of installation it shall be ensured that the wall around the fire cabinet has been painted & released to
proceed with the installation.
Ensure that the block work opening for the fire hose cabinet is as per the approved shop drawings prior to start of
installation.
The height & location of installation of the cabinets shall be in line with the civil defence approved drawings.
The fire cabinet shall be then placed in the opening with the outer flange flush with the wall and shall be fitted to the
Meta block wall using 10mm approved fasteners (8-10nos as per the size of the cabinet). The door of the cabinet shall open
Log in 180 degrees to civil defense approval.
Entries feed
Labeling & identification shall be provided to the equipment in English.
Comments feed
The Hose reel shall be installed inside the fire cabinet utilizing the existing brackets in the cabinet. Hose reel shall open
fully & easily in all directions by just pulling the hose nozzle without even touching the reel.
The piping connection to the hose reel shall be as per civil defense approved shop drawings.
Two approved fire extinguishers shall be placed inside the fire hose cabinets as per approved shop drawings.
AUTHORITY APPROVAL
The civil defence authority will visit the site & shall approve the installations upon completion.
Like t his:
Loading...
PRECOMMISSIONING & COMMISSIONING Testing & Commissioning Of Fire Fighting Project Safety Procedure for Management and
METHOD STATEMENT FOR FIRE HOSE System Hosereel & Sprinkler System Control of Compressed Gas Cylinders
RACKS & FIRE HOSE REEL May 13, 2015 Sep 23, 2021
May 21, 2015 In "Fire Fighting Systems" In "Occupational Health and Safety"
In "Fire Fighting Systems"
Previous Next
All Rights Reserved. Safework Method Of Statement. Serving Construction Industry Since 10 years.