3 Weeks Schedule
3 Weeks Schedule
JANUARY FEBRUARY
PROGRESS TARGET
LAST WEEK THIS WEEK NEXT WEEK
NO WORK DESCRIPTION UNIT STATUS
LAST NEXT 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
CUMM
WEEK WEEK Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
CUT OFF
MECHANICAL WORK
3. CONSTRUCTION WORKS
A. MAIN SUBSTATION
A.1 DUCTING INSTALLATION 1523 120.0 120.0 Plan 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0 20.0
m
134 15.0 0.0 Actual 15.0 10.0
A.2 REFRIGERANT & INSULATION PIPE INSTALLATION 426 90.0 90.0 Plan 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0
m
152 152.0 0.0 Actual 28.0 124.0
A.3 DRAIN & INSULATION PIPE INSTALLATION 204 150.0 180.0 Plan 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0 30.0
m
24 24.0 0.0 Actual 24.0
A.4 INSTALLATION UNIT INDOOR AC 12 6.0 6.0 Plan 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Unit
2.0 0.0 Actual 2.0
A.4 INSTALLATION UNIT OUTDOOR AC 12 0.0 6.0 Plan 1.0 1.0 1.0 1.0 1.0 1.0
Unit
0.0 0.0 Actual
B. ANCILLARY SUBSTATION
B.1 INSTALL SLEEVE/DRAIN PIPE 45 0.0 12.0 Plan 2.0 2.0 2.0 2.0 2.0 2.0
m
0.0 0.0 Actual
D. MAIN WORKSHOP
D.1 EXCAVATION WORK 90 0.0 0.0 Plan 20.0 20.0 20.0 20.0 20.0 20.0
0.0 0.0 Actual 10.0 30.0 30.0 20.0
m
SEWER PIPE INSTALLATION 225 0.0 180.0 Plan 30.0 30.0 30.0 30.0 30.0 30.0 50.0 30.0 30.0 30.0 30.0 30.0 30.0
0.0 0.0 Actual 8.0 7.0 80.0