Group 12 Recla Gantt Chart
Group 12 Recla Gantt Chart
EFIX COMPANY
Project Start Date 1/29/2018 (Monday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead 2/29/2018 (Monday) 29 Jan 2018 5 Feb 2018 12 Feb 2018 19 Feb 2018 26 Feb 2018 5 Mar 2018 12 Mar 2018 19 Mar 2018
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
% WORK
WBS TASK LEAD START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 [Task Category] - -
Conceive - Decision
1.4.1 making of kinematic Team B Fri 2/02/18 Tue 2/13/18 12 50% 8
diagramm of
machine
1.4.2 Team B Sun 2/04/18 Wed 2/21/18 18 50% 13
Layout Configuration
Design, Select and
1.5 sketch machine parts Team A Mon 2/05/18 Thu 2/22/18 18 14% 14
and machine
Implement of Team C
1.6 Sat 2/03/18 Fri 2/09/18 7 30% 5
Machine &D
Documentations and
1.7 Team A Sat 2/10/18 Wed 2/21/18 12 80% 8
Presentation
-
-