stone 976 and 1052 for 10 km stretches along Chellanam Coast in Ernakulam District - Phase 1 for a length of 7/350 km in
between CP 986 and 1026
Bulb groynes 2
T Groynes 4
No of Groynes 6
status
Bulb Groyne Rubble wotk completed 90%
Tetrapod 5T Completed
2T 40%
T groyne 1 Rubble work
toe 60%
Core 80%
Secondary 20%
Tetrapod 5T 10%
2T Nil
2 Rubble work
toe Nil
Core 20%
Secondary Nil
Tetrapod Nil
Due to tipper lorry strike stone supply is very very less & Hence concrete also production almost nil