Project: KIIFB Project - Reformation of Damaged Sunken Sea Wall at Chellanam using Tetrapods and rubble in between CP

stone 976 and 1052 for 10 km stretches along Chellanam Coast in Ernakulam District - Phase 1 for a length of 7/350 km in
between CP 986 and 1026

Agreement Date 12/30/2021 Site Handover 1/3/2022 Duration 16 months

Start Date 1/3/2022 End Date 5/2/2022

Estimate PAC ₹2,266,802,648.00 Contract PAC ₹2,568,967,441.29

As per RE draft on.


Activity Unit Requirement 15.10.2022 Acheived Remaining

2 T Tetrapod Numbers 61090 59320 59830 1260


CASTING

3.5 T Tetrapod Numbers 51246 53053 49521 1725


5 T Tetrapod Numbers 7062 6702 2189 4873
2 T Tetrapod Numbers 61090 59320 52538 8552
PLACING

3.5 T Tetrapod Numbers 51246 53053 48925 2321


5 T Tetrapod Groynes Numbers 7062 6702 225 6837
Core m 2970 2970 0
Reach 1

Secondary m 2970 2970 0


Secondary Backslope m 2970 1470 1500
Toe m 2970 2970 0
Core m 3650 3650 0
Reach 2

Secondary m 3650 3650 0


Secondary Backslope m 3650 1830 1820
Toe m 3650 3650 0
Core m 370 370 0
Bazaar

Secondary m 370 370 0


Toe m 370 370 0

Agreement 535719.482 Tonne


Stone

Total Requirement as per Draft RE on 15.10.2022 705387.3744 Tonne


Total Arrived 681,559.03 Tonne
Remaining 23,828.35 Tonne

Work Done as on 25th December 2022 Expense Planned


9299 1,253,135,850.35 875,313,086.03 615,034,294.71
9299A 1,013,622,349.29 786,082,170.00 941609117.2241
Total 2,266,758,199.64 1,661,395,256.03 1,556,643,411.93
As per agreement As per Draft RE 15.10.22
Dismantling 37980.75 80779.9956
10-50 kg 207593 204976.56
200-400 kg 41863 86833.11
150-200 kg 103854 112916.98
250-350 kg 162996.532 201830.36
350-700 kg 57393.7 92117.99
1-10 kg 6188.69
300 - 500 kg 19098.99
500 - 1000 kg 35951.66
500 - 800 kg 26253.03
Total 535719.482 705387.3744
Reach 1 Reach 2 Groyne Total

87839.4344 58206 18070.461 164115.895


81942.3534 3061.1238 85003.4772
105975.6164 3211.981 109187.597
10693 180644.81 191337.81
90994.8672 90994.8672
4731.8464 4731.8464
7552.729 7552.729
2802.36 2802.36
25832.4462 25832.4462
681559.029
Groynes

Bulb groynes 2
T Groynes 4
No of Groynes 6

status
Bulb Groyne Rubble wotk completed 90%
Tetrapod 5T Completed
2T 40%
T groyne 1 Rubble work
toe 60%
Core 80%
Secondary 20%
Tetrapod 5T 10%
2T Nil
2 Rubble work
toe Nil
Core 20%
Secondary Nil
Tetrapod Nil

Due to tipper lorry strike stone supply is very very less & Hence concrete also production almost nil