Professional Documents
Culture Documents
TSPCW6 - Part1 Rev0306
TSPCW6 - Part1 Rev0306
SPECIFICATION FOR
OCTOBER 2005
J229 ( Rev 03/06 )
© National Grid Gas plc 2006 - All Rights Reserved
T/SP/CW/6 Part 1
CONTENTS
Page
FOREWORD v
BRIEF HISTORY v
DISCLAIMER v
1. SCOPE 1
2. REFERENCES 1
3. DEFINITIONS 1
4. COATING MATERIALS 1
5. VARIENTS 2
SECTION TWO –
BASIC PROPERTIES AND TESTS FOR POWDERS AND CURED COATING
6.1 General 3
6.5 Density 3
6.8 Stability 3
7.2 Micro-sectioning 4
7.4 Elongation 4
Page
10. COMPLIANCE 6
11.1 General 7
11.3 Viscosity 7
11.8 Stability 7
12.2 Micro-sectioning 8
12.4 Elongation 8
Page
15. COMPLIANCE 10
APPENDICES
A REFERENCES 11
B DEFINITIONS 12
D FLEXIBILITY TEST 22
I STRAIN/POLARIZATION TEST 34
ENDNOTE 37
FOREWORD
This Specification was approved by Phil Brown on 21/10/04 for use by managers, engineers and
supervisors throughout National Grid Gas.
National Grid Gas documents are revised, when necessary, by the issue of new editions. Users should
ensure that they are in possession of the latest edition by referring to the Gas Documents Library
available on infonetUK (company intranet.)
Compliance with this Document does not confer immunity from prosecution for breach of statutory or
other legal obligations.
BRIEF HISTORY
KEY CHANGES (Identify the changes from the previous version of this document)
Section Amendments
DISCLAIMER
This document is provided for use by National Grid Gas and such of its contractors as are obliged by the
terms and conditions of their contracts to comply with this document. Where this document is used by
any other party it is the responsibility of that party to ensure that this document is correctly applied.
Should: indicates best practice and is the preferred option. If an alternative method is used then a
suitable and sufficient risk assessment shall be completed to show that the alternative method
delivers the same, or better, level of protection.
SPECIFICATION FOR
THE EXTERNAL PROTECTION OF STEEL LINE PIPE AND
FITTINGS USING FUSION BONDED POWDER AND OTHER
COATING SYSTEMS:
PART 1 - REQUIREMENTS FOR COATING MATERIALS AND
METHODS OF TEST
Section One of this specification covers general requirements. Section Two covers fusion bonded
powder and Section Three covers multi-component liquid coating materials.
* Hereinafter referred to as 'this specification'.
2. REFERENCES
2.1 This Specification makes references to the documents listed in Appendix A. Unless otherwise
specified, the latest edition of the documents apply, including all amendments.
3. DEFINITIONS
3.1 The requirements and definitions applying to this Specification are listed in Appendix B.
4. COATING MATERIALS
4.1 Acceptable materials
4.1.1 Coating systems
Only coating systems conforming to this specification should be considered for application in accordance
with CW6: Part 2. Coating systems may include the use of a primer or chemical pre-treatment of the
steel surface to enhance adhesion. In such cases, the pre-treatment and coating material should be
clearly specified as a combined system.
Where recycled fusion bonded epoxy (FBE) material is used, the ratio of recycled to virgin material
should be stated. Any FBE made up with a recycled material mix should meet the requirements of this
specification. Fusion bonded powder should also meet the requirements of Part 1 of this specification
without the use of chemical pre-treatment.
then, after economic evaluation, these new values may be adopted as the minimum requirements and
the specification would be up-graded accordingly.
Any change of formulation, or manufacturing supply route, of a material may be proposed for
consideration as a variant by National Grid Gas and supply of the modified material shall not be
implemented until such time as the revised procedure qualification trials have been completed and the
results accepted in writing by National Grid Gas.
Containers and any associated packaging should, where appropriate, be marked in accordance with the
Chemicals (Hazard Information and Packaging for Supply) Regulations 2002.
The Contractor shall require the Manufacturer to supply certificates confirming that tests specified in this
specification have been carried out on the batches supplied and that the materials meet the specified
requirements. These certificates shall be made available for examination by National Grid Gas on
request.
Containers and associated packages should be marked with their weights and, where appropriate, be
provided with handling points, e.g. handles or hand holes.
The manufacturer shall also provide information to cover the environmental aspects of the coating
materials to include:
a) Identification of the environmental risks associated with the use of the materials.
b) Identification of suitable control measures to prevent environmental damage.
c) Identification of suitable methods of disposal of waste materials and contaminated items.
5. VARIENTS
A contractor should only propose variants to this specification where the text indicates that variants
would be considered by National Grid Gas.
SECTION TWO – BASIC PROPERTIES AND TESTS FOR POWDERS AND CURED COATING
6. BASIC PROPERTIES OF THE POWDER
6.1 General
The Contractor should obtain from the Manufacturer the specified and qualified ranges of values for all
properties listed in 6.2 to 6.8 inclusive that will ensure an acceptable coating. The frequency of testing
should be in accordance with 9.2.
Particle size range should be quoted in the production data sheet. Each batch should be checked for
conformity with the values originally quoted.
6.5 Density
The density of the powder should be measured for all batches produced, and the values should conform
with the value originally specified.
6.8 Stability
After ageing for 120 days at 25 ±1 °C in a sealed container, the powder should not exhibit any significant
change from the properties identified in 6.2 to 6.7 inclusive.
7.2 Micro-sectioning
A cross-section of the cured film should be examined at a magnification of X100 and should be seen to
be homogeneous and essentially free of voids, foaming or other defects.
7.4 Elongation
When tested in accordance with 7.3, the elongations at 'yield' and 'break' should be quoted by the
Manufacturer.
The tests should be carried out on sections of 6 mm thick laboratory coated standard steel plate, as
appropriate to the test requirement. Prior to coating, the steel surface should be blast cleaned using G34
grit to ISO 8501 Sa 3 quality and surface profile of between 50µm and 100µm peak to trough height. The
coating thickness should be in the range 400µm to 450µm. A destructive film thickness test should be
carried out to verify the accuracy of the coating thickness measurement technique employed.
The values of Tg1 and Tg2 specified by the Manufacturer should be in a range to ensure the coating is
adequately cured to meet subsequent performance tests.
The Contractor should obtain complete results of all thermal analyses from the Manufacturer for record
purposes. National Grid Gas should have the right to examine the results on request.
The coating shall withstand a minimum mean impact value of 1.5 J without resulting in a breakdown or
loss of adhesion of the coating.
The Contractor should be responsible for ensuring that the range of values for any material under
consideration will be capable of providing a finished product in compliance with the relevant Sections of
T/SP/CW/6: Part 2.
All tests should be carried out on coatings properly cured and in the thickness range 400µm to 450µm.
The coating colour and appearance should be uniform and free from runs, sags, blistering, roughness,
foaming and general film defects.
9.2 During the production of each separate batch of powder or twice every 8 h of continuous
production (whichever is the more frequent), the tests specified in 6.2 to 6.7 inclusive should be carried
out.
9.3 At least once every 8 h of continuous production, the tests specified in 8.1.2 to 8.1.9 inclusive
should be carried out.
9.4 The tests specified in 7.2 to 7.7 inclusive, 8.2.2 to 8.2.4 inclusive, 8.2.8 and the requirements
of 6.8 should be carried out once per year.
9.5 Any time a production, source, process or formulation change is made to the coating system,
the tests specified in 7.2 to 7.7 inclusive, 8.2.2 to 8.2.8 inclusive and the requirements of 6.8 should be
carried out.
10. COMPLIANCE
The coating material shall not be dispatched until it has been demonstrated that the Manufacturers
inspection and testing complies with the requirements of this specification.
The Contractor shall obtain, from the Manufacturer, specified and qualified ranges of values for all
properties, listed in 11.2 to 11.8 inclusive, that will ensure an acceptable coating. The frequency of
testing should be in accordance with 14.2.
11.3 Viscosity
The viscosity of each material component as supplied, and that of the mixture when prepared for use in
the correct ratio, should be specified by the Manufacturer, together with the method of test.
11.8 Stability
The separate material components when stored at 20 °C to 25 °C for a period of 6 months should:
The separate material components, when stored in closed containers approximately 75 mm diameter x
75 mm high, two-thirds full at 20 °C to 25 ° for 24 h, shall not show signs of skinning or other
deterioration.
allowed to cure at 20 °C to 25 °C and 60% to 70% relative humidity for a period of seven days to achieve
optimum properties before test. Samples should be of uniform thickness for all tests.
12.2 Micro-sectioning
A cross-section of the cured film should be examined at a magnification of X100 and should be seen to
be homogeneous and essentially free of voids or other defects.
12.4 Elongation
When tested in accordance with 12.3, the elongations at 'yield' and 'break' should be quoted by the
Manufacturer.
The Contractor should ensure that the tests specified in 13.1.2 to 13.1.8 inclusive are carried out in
duplicate by the Manufacturer in accordance with 14.3 and the results of the tests, demonstrating
compliance, made available.
The tests should normally be carried out on standard steel surfaces which have been blast cleaned,
using G34 grit, to ISO 8501, Sa 3 quality to produce a profile of between 50µm and 50µm peak to trough
height. Coating application should normally be by a suitable technique with pre-heating of components,
where necessary. The coating should be applied to give a dry film thickness of not less than 1.5 mm and
allowed to cure at 20 °C to 25 °C and 60% to 70% relative humidity for a period of 24 h to achieve
optimum properties before test.
Testing of applied coatings should be carried out seven days after the coating application.
The coating shall withstand a minimum impact of 5 J without resulting in a breakdown or loss of adhesion
of the coating.
The tests specified in 13.2.5 to 13.2.7 inclusive should be carried out once to provide evidence of
satisfactory long term performance.
14.2 During the production of each separate batch or twice every 8 h of continuous production
(whichever is the more frequent), the tests specified in 11.2, 11.3 and 11.4 should be carried out. The
requirements of 11.5 to 11.7 inclusive shall also be met.
14.3 At least once every 8 h of continuous production, the tests specified in 13.1.2 to 13.1.8
inclusive should be carried out.
14.4 The tests specified in 12.2 to 12.7 inclusive and in 13.2.2, 13.2.3 and 13.2.4 (considered as
type tests) and the requirements of 11.8 should be carried out once per year or at any time a production,
source, process or formulation change is made to the coating system.
15. COMPLIANCE
The coating material shall not be dispatched until it has been demonstrated that the Manufacturers
inspection and testing complies with the requirements of this specification.
APPENDIX A
REFERENCES
This Specification makes reference to the documents listed below.
APPENDIX B
DEFINITIONS
The definitions applying to this specification are given below.
National Grid Gas - National Grid Gas - a part of National Grid plc.
National Grid Gas - The person appointed from time to time by National Grid Gas and notified in
representative writing to the Contractor to act as National Grid Gas representative for the
purposes of the Contract.
Contractor - The person, firm or company with whom National Grid Gas enters into a
contract to which this specification applies, including the Contractor's personal
representatives, successors and permitted assigns.
Manufacturer - The producer of the coating material or his appointed agents or assigns.
APPENDIX C
METHODS FOR THE EVALUATION OF THE THERMAL CHARACTERISTICS OF POWDER AND
CURED COATING
C.1 INTRODUCTION
This appendix details methods by which the thermal characteristics of a powder (see clause C.2) and the
thermal characteristics of cured coating (see clause C.3) can be evaluated.
C.2.2 Apparatus
The apparatus used should be a DSC∗ with sufficient calorimetric sensitivity to respond to the glass
transition temperature of the powder (the thermal analysis curve should be capable of displaying the heat
flow rate at a sensitivity of not less than 400µW/cm). Additionally, the following accessories will be
required:
a) Calibrate the upper temperature scale of the DSC using samples of pure indium, tin and
lead which have melting points of 156.6 °C, 231.9 °C and 327.4 °C respectively.
b) Melt the metal samples in open pans in either static air or under inert gas purge,
depending on the test procedure being followed.
c) Take the melting point as the intersection of the leading edge of the fusion endotherm with
the projected baseline.
The results obtained are influenced by the scan rate, therefore adjust the instrument such that these
values are correct at the scanning rate employed in the test, i.e. 20 °C/min.
In practice, melting points are usually within 2 °C to 3 °C of the accepted values when determined at a 20
°C/min scan rate and this is found to be adequate for Tg measurements of the coating film. If the
measured value differs from the true value by more than 2 °C to 3 °C, recalibrate the temperature axis.
∗
There are a number of DSC machines available and correlation should be demonstrated
dh
= K1 δY
dt
where δY = difference in Y-axis deflection between the sample and empty pan curves at the
temperature of interest, measured in units of length (centimetres, inches, etc.).
a) The signal attenuation setting on the Y-axis, i.e. q s (Y axis range in mW or equivalent).
b) The cell calibration coefficient E (dimensionless).
The cell calibration coefficient E can be determined at any given temperature through the use of a
material of known specific heat (e.g. sapphire (A12O3)) using the following equation:
CpHrm
E= (1)
q sδ Y
Hr = heating rate.
m = sample mass.
Equation (1) is derived from another equation (2), which relates the heat release (or absorption) to the
area of the event on the thermogram, i.e.:
A
H= (B E qs) (2)
M
The heat release is a function of the specific heat of the test material and equal to:
1
H = CpHrAB (3)
δY
Therefore, if this is substituted in equation (2) and transposed, we arrive at the equation for E.
Alternatively, the cell constant may be determined by relating the latent heat fusion of the pure material
(e.g. indium) to the area produced from the melting endotherm.
C.2.3.3.2 Load the sample pan with a weighed sapphire disc for a second run. Heat the pan up to the
initial ambient temperature and hold until equilibrium is obtained. This should be achieved by
setting the starting temperature to ambient temperature and running in isothermal mode.
C.2.3.3.3 Run a second trace using the same final temperature as is used in C.2.3.3.1.
C.2.3.3.4 Measure several values for δ Y, the vertical difference between the traces, to calculate E
values at these points. The average of E over the range of interest should be used.
C.2.4 Sampling
When it is necessary to sample large amounts of powder from the sample batch (e.g. several kilogram
boxes), take representative amounts (approximately 50 g) from each container, mix together and sample
by coning and quartering. Analyse different batches separately.
Take a final sample (approximately 250 g) and store it in an airtight container, at a temperature not
higher than 0 °C, in case subsequent testing is required. When the cold sample is taken from cold
storage, allow at least 30 min in its closed container to reach ambient temperature. Take powder for DSC
tests directly from the 250 g sample.
When amounts of powder less than 1 kg are involved, coning and quartering or riffle sampling is not
necessary.
a) Date.
b) Time.
c) Powder lot number/batch number.
Where applicable, select a baseline slope setting which gives a virtually horizontal line when the
reference and sample pans are loaded identically. This is normally carried out with empty pans.
The glass transition temperature of the cured material is visible on the DSC trace as a baseline shift,
resulting from a marked step-like change in specific heat at Tg, the step usually covering several
degrees. It is conventional to take Tg as the point of intersection of the extrapolated baseline at the low
temperature end and the tangent of the curve at the inflection point (see Figure C.2). For raw powders,
the Tg usually takes the form of a baseline shift with a superimposed endothermic peak (see Figure C.3).
There are several ways of measuring the exothermal area which vary in their accuracy. These are:
One of these, or a similar method, should be selected for use with the DSC.
The points at which the cure exotherm commences and ends are used to calculate the heat release.
They are usually determined by drawing in the baseline to the exotherm using a rule. Care shall be taken
to distinguish between the onset of cure (Toc) and the onset of flow (Tof) and to commence the baseline at
Toc (see Figure C. 3).
C.3.2 Apparatus
The apparatus used should be a DSC with sufficient calorimetric sensitivity to respond to the glass
transition temperature of the materials under test (the thermal analysis curve should display the heat flow
rate at a sensitivity of 400µW/cm minimum). Additionally, the following accessories will be required:
a) Calibrate the upper temperature scale of the DSC using samples of pure indium, tin and
lead which have melting points of 156.6 °C, 231.9 °C and 327.4 °C respectively.
b) Melt the samples in open pans in either static air or under an inert gas purge, depending
on the test procedure being followed.
c) Take the melting point as the intersection of the leading edge of the fusion endotherm with
the projected baseline.
The results obtained are influenced by the scan rate, therefore adjust the instrument such that these
values are correct at the scanning rate employed in the test, i.e. 20 °C /min.
In practice, melting points are usually within 2 °C to 3 °C of the true values when determined at a
20 °C/min scan rate and this is found to be adequate for Tg measurements of the coating film. When the
temperature deviation is higher than this, it is necessary to adjust the sample thermocouple reference
junction.
If adjustment has been necessary to bring within limits, carry out a further calibration to demonstrate that
the instrument is calibrated accurately.
C.3.4 Sampling
Remove coating film samples from the coated component using a hammer and cold chisel. This
produces furled coating flakes. Care should be taken to remove samples of full film thickness, but at the
same time avoid the inclusion of steel debris.
Sample a component at several points along its length and around its circumference. Take samples from
test panels in a similar manner.
Collect the coating flakes in a plastics bag and identify. Grind the flakes to pieces small enough to pass
through a 2.8 mm aperture sieve in a microhammer mill. Record the following information for each
sample:
a) Date.
b) Time.
c) Component number.
d) Sequence number.
e) Powder lot number/batch number.
f) Location of sample on component.
Where applicable, select a baseline slope setting which gives a virtually horizontal line when the
reference and sample pans are loaded identically. This is normally carried out with empty pans.
a) Use open pans to assist the release of moisture from the sample during pre-treatment.
b) Use an empty aluminium pan for the reference.
c) No purge gas is employed; carry out the test in static air at atmospheric pressure.
d) Appropriate experimental data recording conditions.
e) It will normally be necessary to subject the coating sample to thermal pre-treatment before
assessment of its degree of cure. Pre-treatment is designed to remove any absorbed
moisture from the coating because moisture is known to influence glass transition
temperature measurements. Such pre-treatment should not significantly advance the cure
of the coating sample.
The powder Manufacturer should specify the thermal pre-treatment required for the
product. This will typically require heating the sample in the DSC cell from ambient
temperature
(i.e. 20 °C to 25 °C) to some defined temperature higher than 100 °C, probably in the
range 100 °C to 150 °C. This required temperature will typically be attained within 120 s
and held for a period up to 60 s. Immediately cool the sample to ambient temperature with
liquid nitrogen or a suitable cooling fluid; alternatively, a DSC with a built-in cooling device
is acceptable provided it can cool the sample rapidly at the rate required in the method.
The glass transition temperature is visible on the DSC trace as a baseline shift, resulting from a marked
step-like change in specific heat at Tg, the step usually covering several degrees. It is conventional to
take Tg as the point of intersection of the extrapolated baseline at the low temperature end and the
tangent of the curve at the inflection point (see Figure C.2).
APPENDIX D
FLEXIBILITY TEST
D.1 LABORATORY PREPARED TEST PANELS
D.1.1 Apply the coating to steel plates 50 mm x 300 mm x 6 mm thick and properly cure. Bend (at a
deflection rate of 25 mm/min) over appropriate sized mandrels (see D. 1.2) at two substrate
test temperatures (5 °C and 20 °C). After bending, the coating shall not crack, disbond or
pinhole when holiday tested in accordance with Appendix E. Inspect plates immediately after
bending and again after 24 h at 20 °C.
t(1-S)
D=
S
The arc length of the mandrel should be fixed at 225 ±25 mm.
D.1.3 Set the panel support gap according to the following formula:
Support gap = M + 2t + 4 mm
where M = chord length across the mandrel arc, in mm (see Figure D.1).
Bend the panel until it makes contact with the entire surface area of the mandrel.
D.1.4 During bending, peaking (point at which a gap occurs between the mandrel and the panel)
may be observed at the centre of the panel. In this case, the area of the panel where the gap
exceeds 0.254 mm (0.010 in.) should be disregarded in evaluating the test results. This area
should not exceed 25% of the mandrel surface area.
1
D1 = -t
S 1
+
t D0 - t
D.2.3 The arc length of the mandrel should be fixed at 225 ± 25 mm.
D.2.4 For specimens from pipes having an outside diameter in the range 406 mm to 1219 mm, set
the panel support gap according to the following formula:
Support gap = M + 2t + 4 mm
where M = chord length across the mandrel arc, in mm (see Figure D.1).
t = plate thickness, in mm.
Bend the specimen until contact is made with 75 ± 10% of the mandrel area.
D.2.5 For specimens from pipes having an outside diameter in the range 305 mm to 405 mm set the
panel support gap according to the following formula:
Bend the specimen until it makes contact with the entire surface area of the mandrel.
Test specimens from pipes having an outside diameter below 305 mm by an appropriate
method.
D.2.6 During bending, peaking (point at which a gap occurs between the mandrel and the panel)
may be observed at the centre of the panel. In this case, the area of the panel where the gap
exceeds 0.254 mm (0.010 in.) should be disregarded in evaluating the test results. This area
should not exceed 25% of the mandrel surface area.
D.3 S VALUES
D.3.1 For coatings intended for use on fittings, the following S values should apply:
D.3.2 For coatings intended for use on line pipe, the following S values should, apply:
D.4 TESTING AT 5 °C
Testing at 5 °C may be carried out by pre-cooling the panel in a refrigerator to a temperature slightly
lower than 5 °C and carrying out the bending operation when the panel temperature reaches 5 ±2 °C.
Alternatively, an environmental chamber that controls the temperature of the bending apparatus may be
used. The test specimens should not be immersed in any liquefied coolant to achieve the test
temperature.
APPENDIX E
HOLIDAY DETECTION OF COATINGS
E.1 EQUIPMENT
Holiday detection should be carried out using dc, non-pulsing holiday detection equipment on surfaces at
temperatures below 90 °C and free from moisture.
The rate of travel of the probe over the surface should not exceed 300 mm/s.
APPENDIX F
EVALUATION OF RESISTANCE TO IMPACT
F.1 GENERAL
The procedures specified in clauses F.2 to F.6 inclusive serve to assess the comparative resistance of
coatings to impact damage.
a) A variable impact tester (ASTM G14-77, paragraph 4.2 or equivalent) with punch hammer
type indentor modified as shown in Figure F.1 to accommodate a 14.3 mm diameter ball
bearing and equipped with a minimum impact mass of 1 kg.
b) A sufficient supply of 14.3 mm diameter ball bearings manufactured from EN31 steel with
a Vickers hardness of 800 to 930.
c) A holiday detector (see Appendix E).
d) A thickness gauge.
e) Repair materials.
F.3.2 Position the impact tester on a holiday free site 300 ± 50 mm from one end of the component.
F.3.3 Drop the impact weight from a height calculated to impart the specified impact energy to the
coating. The impact height may be calculated using the following formula:
J
H =
9.81W
F.3.4 Retest the impact area for holidays using the detector set at the required operating voltage.
F.3.5. Repeat F.3.2, F.3.3 and F.3.4 at four more locations evenly spaced over the surface of the
component.
F.3.8 If a holiday is caused by the impact test, check the coating thickness in the test area using a
thickness gauge.
The additional modifications to the ASTM procedure specified in F.5.2 to F.5.6 inclusive should
apply.
F.5.2 Test impact areas for failure using the holiday detector set at a voltage of 125 V per 25µm of
coating thickness (this relates to coating thickness before impact damage).
F.5.3 The minimum spacing between impacts along the centre line of the specimen should be
25 mm.
F.5.7 There shall be no disbonding at the minimum impact energy. Verify this by testing in
accordance with clause G.6 and report in accordance with clause G.7.
F.6.2 The impact strength should be converted to impact energy in joules and this value should be
reported. (A typical calculation is shown in Figure F.1).
APPENDIX G
EVALUATION OF RESISTANCE TO WATER IMMERSION
G.1 GENERAL
The equipment and procedure detailed in clauses G.2 to G.7 inclusive should be used to assess the
comparative resistance of coatings applied to components (free of holidays) to loss of adhesion due to
water absorption.
G.2 EQUIPMENT
The following equipment will be required:
G.4.2 Drill a 6 mm diameter hole through the test panel within 25 mm of one end.
G.4.3 Protect the bare metal of the panel with internal coating material (see clause G.2 c)).
G.5.2 Using the steel rod fitted through the 6 mm diameter hole, suspend the specimen panel in the
water bath immersing all but the top 50 mm of the panel.
G.5.3 After 7 days, remove the panel from the water bath and allow it to cool to ambient temperature.
No longer than 30 minutes should be allowed between removing the test panel from the bath
and performing the adhesion test.
G.5.7 If, after seven days immersion, the coating is retested and is found to be satisfactory, return
the panel to the water bath and repeat the adhesion test at intervals of seven days up to a total
immersion time of 28 days. If the coating fails the requirements of this specification at any test
interval within the 28 days, it should be removed from test.
G.6.2 For all coated components and coatings on panels equal to or less than 600µm thickness, use
the following procedure:
a) Using a sharp pointed knife (e.g. Stanley knife or similar), make two incisions
approximately 13 mm long through to the metal surface to form a V with an angle of
approximately 30° at the intersection point.
b) Starting at the point of intersection force the coating from the steel substrate using the
sharp pointed knife. Take care to protect the eyes and hands when carrying out this
operation.
G.6.3 For laboratory panels with coatings greater than 600µm thickness use the following procedure:
a) Using a small hacksaw blade (e.g. 'Junior' type or similar) make two incisions through to
the metal surface to form an X with an angle of approximately 30° at the point of
intersection.
b) Draw a sharp knife along the cut lines to ensure that the hacksaw blade has reached the
metal surface.
c) Starting at the point of intersection, force the coating from the steel substrate using the
sharp pointed knife. Take care to protect the eyes and hands when carrying out this
operation.
Cohesive failure, caused by voids leaving a honeycomb structure on the specimen surface, should
constitute a failure.
For the purpose of this test, cohesive failure will be recorded where some coating material remains on
the metal surface and where difficulty in coating removal has been experienced.
The extent of the adhesive failure between the coating and the metal substrate should be recorded.
Adhesive loss greater than 3 mm shall be recorded as a 'Failure'.
APPENDIX H
EVALUATION OF RESISTANCE TO CATHODIC DISBONDING
H.1 GENERAL
The procedures detailed in clauses H.2 to H.7 inclusive serve to assess the comparative resistance of
damaged pipe coatings to disbonding when exposed to cathodic protection in potentially corrosive soils.
H.2.2 Reagent
An electrolyte comprising a sodium chloride (NaCl) solution, (3% W/V). 30 g of NaCl should be dissolved
in distilled water and made up to 1 litre.
H.4.2 Fix two lengths of rigid plastic tube perpendicular to the coated surface using a suitable
elastomeric adhesive (see Figure H.1). Place them with their centres on the centre line of the
panel width and equidistant from the panel ends and each other and leave for a period of 12 h
to allow the adhesive to fully cure.
H.4.3 Drill a 6 mm diameter hole through the coating to the metal surface in the centre of each test
area using the drill specified in H.2.1 g).
H.5.2 Connect a voltmeter and reference electrode to each test rig in turn as shown in Figure H.1 b)
With the tip of the calomel reference electrode positioned approximately 10 mm from the
centre of the hole, adjust the voltmeter reading to read a negative voltage of 1500 mV with
respect to the calomel electrode. Carry this out using the variable resistance shown in Figure
H.1 a).
H.5.3 Record, at intervals of 24 h, the voltmeter indication for each test area and adjust the variable
resistor to correct any drift from the negative voltage setting of 1500 mV. Also record, every 24
h, the current flow by measuring the voltage drop across the 1 Ω fixed resistor.
H.5.4 Every 24 h check the plastic tube for loss of electrolyte and restore the level with distilled water
as necessary.
H.6.2 Use one or other of the following procedures (H.6.3, H.6.4) as appropriate within 30 minutes of
removing the plastic tube:
H.6.3 For coatings up to and including 600µm use the following procedure:
a) Using a sharp-pointed knife (e.g. Stanley type or similar), make two incisions
approximately 13 mm long through to the metal surface extending radially from the 6 mm
hole and at an angle of approximately 30° to each other to form a truncated V.
b) Starting at the base of the truncated V, force the coating from the steel substrate using the
sharp pointed knife. Take care to protect the eyes and hands when carrying out this
operation.
H.6.4 For all coatings in excess of 600µm thickness use the following method:
a) Using a small hacksaw blade (e.g. 'Junior' type or similar), make two cuts across the 6 mm
hole at an angle of approximately 30° to each other to form a truncated 'X'. Make the cuts
through to the metal surface and to extend radially from the 6 mm hole.
b) To ensure that the hacksaw blade has reached the metal surface, draw the point of the
sharp knife along the cut lines.
c) Starting at the base of the truncated V, force the coating from the steel substrate using the
sharp pointed knife. Take care to protect the eyes and hands when carrying out this
operation.
H.6.5 Repeat the investigation procedure at the second test site after 28 days.
APPENDIX I
STRAIN/POLARIZATION TEST
I.1 Bend the test sections in accordance with the method detailed in Appendix D using a value of
S = 0.02 for line pipe powders and S = 0.005 for fitting powders at a temperature of 20 ±2 °C.
I.2 Fix a length of rigid plastic tube perpendicular to the coated surface as detailed in H.4.2 with its
centre on the centre line of the panel and on the minimum radius of the bend i.e. the region of
maximum strain.
I.3 Drill a 6 mm diameter hole through the coating to the metal surface and polarize the specimen
as detailed in H.5. After 28 days polarization, remove the electrolyte and the plastic tube and
remove excess moisture from the test surface.
I.4 The area of coating exposed to the electrolyte shall not exhibit signs of cracks, disbondment in
excess of 5 mm from the edge of the predamage or pinholes, and shall pass a holiday
detection test as detailed in Appendix E.
APPENDIX J
EVALUATION OF RESISTANCE TO HEAT BLISTERING
J.1 GENERAL
The equipment and procedures detailed in clauses J2 to J5 inclusive should be used to assess the
resistance of FBE coatings to heat blistering.
J.4.2 After each period of exposure remove the specimens from the water bath and immediately
remove excess water.
J.4.3 Drill a 6 mm diameter hole through the coating to expose the metal surface in the centre of the
panel. The thickness of the panel should not be reduced by more than 0.5 mm.
J.4.5 Heat the coated test panel(∗) from the back at a rate of 110 ±10 °C/minute, until the
thermocouple registers a temperature of 240 °C. No longer than 15 minutes should elapse
between removing the test panel from the water bath and commencing heating.
J.4.6 When the test plate attains a temperature of 240 °C quench the panel immediately in cold
water. Quenching will prevent blisters from deflating and will allow the size and blister density
to be recorded.
∗
A 2kW hot air gun has proved to be suitable for this purpose. By adjusting the distance between the gun and the test panel the
heating rate can be varied. Ensure that the heating process is reproducible prior to performing the heat blister tests.
J.6.2 A photographic record of the appearance of the test plate after quenching should be made.
ENDNOTE
Comments
Comments and queries regarding the technical content of this document should be directed to:
Buying documents
Contractors and other users external to National Grid Gas should direct their requests for further copies
of National Grid Gas documents to the department or group responsible for the initial issue of their
contract documentation.
Copyright National Grid Gas plc 2006 ©, all rights reserved. No part of this publication may by reproduced
in any material form (including photocopying and restoring in any medium or electronic means and
whether or not transiently or incidentally) without the written permission of National Grid plc except in
accordance with the provisions of the Copyright, Designs and Patents Act 1988.