Item Description Tag # Items Metric Tons dims weight by drawing radius crane LP N Comment Legend (10.09.2022)
in KG
34
E&I Building (Lifting and Installation of 5 modules, including HVAC room) 6-550-ZP-02A/B 5 60 WEIGHT FOR QUOTATION ONLY
40 14% Caustic Dosing Pumps 6-550-PD-14A/B 2 0.18 To be fitted after tank erection
41 Spent Caustic Transfer Pumps 6-550-PA-16A/B 2 0.82 611 X 610 X 3600 823 To be fitted after tank erection
42 Make-Up Water Pumps 6-550-PA-17A/B 2 0.63 1900 X 800 X 700 0.6 To be fitted after tank erection
43 Back-up Water Pumps 6-550-PA-18A/B 2 0.60 2200X 900X 800 1 To be fitted after tank erection
44 Vent and Surge Vessel 6-550-VA-06 1 1.30 900x 4500x 1600 1.3 Sits on the pipe rack structure
45 Cricket Filter Skid (Part A and Part B) 6-550-CZ-01A/B 2 5.81 For Main Skid lifting and placing
46 Safety Showers 6-550-SD-01, 6-550-SD-02, 6-550-SD-03 3 0.58 To be fitted during pipe installation
47 Quotation as Cost + fee of a
Refractory Brick* N/A 1 N/A specialized sub-contractor.
48 Combustion Air Duct 6-550-025-24"-LTCS (DUCT) 2.79 WEIGH FOR QUOTATION ONLY
49 Cricket Filter Steel Structure (stairs, platform, grating, etc) 6-550-CZ-01A/B 1 3.06 Associated with Cricket Filter Skid