Professional Documents
Culture Documents
D1 Merged
D1 Merged
L REQUIREMENTS
EQUIPMENT MATERIAL
TOTAL
No.of Hour/s Hourly Rate Unit Cost Cost
₱ 2,465.52
₱ 3,562.56
₱ 6,860.40
₱ 500.00 ₱ 10,000.00 ₱ 10,000.00
₱ 60.00 ₱ 21,000.00 ₱ 21,000.00
₱ 255.00 ₱ 5,865.00 ₱ 5,865.00
₱ 70.00 ₱ 420.00 ₱ 420.00
₱ 41.00 ₱ 246.00 ₱ 246.00
₱ 250.00 ₱ 5,750.00 ₱ 5,750.00
₱ 1,296.84 ₱ 2,593.68 ₱ 2,593.68
₱ 1,296.84 ₱ 5,187.36 ₱ 5,187.36
₱ 80.00 ₱ 400.00 ₱ 400.00
₱ 15.00 ₱ 3,000.00 ₱ 3,000.00
SUB-TOTAL ₱ 67,350.52
1.4 Performance Bond
1.4a 3% of Contract 1 lot
₱ 120,000.00
₱ 67,200.00
₱ 67,200.00
9.79 1,920.00 ₱ 18,796.80
1.03 1,920.00 ₱ 1,977.60
3.47 1,920.00 ₱ 6,662.40
3.2 FOOTING TIE BEAM & WALL FOOTING, (FTB-1 & WF-1)
(STRUCTURAL CONCRETE, CLASS A-28 DAYS)
TOTAL VOLUME = 5.85 CU.M. OUTPUT PER HOUR = 0.27
3.2a Construction Foreman 1 1.00 ₱ 102.73
3.2b Skilled Laborer 2 1.00 ₱ 74.22
3.2c Unskilled Laborer 4 1.00 ₱ 57.17
3.2d One Bagger Mixer 1 pc
3.2e Minor Tools (10% of Labor Cost)
3.2f Gravel 5.85 cu.m.
3.2g Sand 2.93 cu.m.
3.2h Portland Cement 53.00 bags
de 40
kg TOTAL HOUR/S NEEDED = 5.15
₱ 528.90
₱ 1,146.36
₱ 3,532.07
0.50 ₱ 219.75 ₱ 565.69
0.50 ₱ 351.50 ₱ 904.85
₱ 520.73
₱ 378.72 ₱ 29,540.00 ₱ 29,540.00
₱ 80.000 ₱ 886.20 ₱ 886.20
₱ 1,521.31
SUB-TOTAL ₱ 39,146.12
AYS)
CU.M. TOTAL HOUR/S NEEDED = 26.48
₱ 2,720.44
₱ 764.24
₱ 1,177.36
1.00 ₱ 172.00 ₱ 885.54
466.20
₱ 1,296.84 ₱ 9,272.41 ₱ 9,272.41
₱ 1,296.84 ₱ 4,636.20 ₱ 4,636.20
₱ 250.00 ₱ 16,250.00 ₱ 16,250.00
SUB-TOTAL ₱ 36,172.40
AYS)
CU.M. TOTAL HOUR/S NEEDED = 21.67
₱ 2,225.82
₱ 3,216.20
₱ 4,954.73
1.00 ₱ 172.00 ₱ 3,726.67
1,039.68
₱ 1,296.84 ₱ 7,586.51 ₱ 7,586.51
₱ 1,296.84 ₱ 3,793.26 ₱ 3,793.26
₱ 250.00 ₱ 13,250.00 ₱ 13,250.00
SUB-TOTAL ₱ 39,792.86
de 40
kg TOTAL HOUR/S NEEDED = 5.21
₱ 535.71
₱ 1,161.11
₱ 3,577.51
0.50 ₱ 219.75 ₱ 572.97
0.50 ₱ 351.50 ₱ 916.49
₱ 527.43
₱ 378.72 ₱ 22,344.48 ₱ 22,344.48
₱ 213.12 ₱ 2,131.20 ₱ 2,131.20
₱ 147.84 ₱ 6,948.48 ₱ 6,948.48
₱ 80.000 ₱ 897.60 ₱ 897.60
₱ 1,616.09
SUB-TOTAL ₱ 41,229.06
3.3 COLUMN (BELOW THE NGL, (C1)
(STRUCTURAL CONCRETE, CLASS A-28 DAYS)
TOTAL VOLUME = 0.59 CU.M. OUTPUT PER HOUR = 0.27
3.3a Construction Foreman 1 1.00 ₱ 102.73
3.3b Skilled Laborer 2 1.00 ₱ 74.22
3.3c Unskilled Laborer 4 1.00 ₱ 57.17
3.3d One Bagger Mixer 1 pc
3.3e Minor Tools (10% of Labor Cost)
3.3f Gravel 0.59 cu.m.
3.5g Sand 0.29 cu.m.
3.5g Portland Cement 6.00 bags
3.4 FORMWORKS
TOTAL AREA = 395.74 SQ.M. OUTPUT PER HOUR = 4.50
3.4a Construction Foreman (INSTALLATION) 1 1.16 ₱ 102.73
3.4b Skilled Laborer (INSTALLATION) 4 1.16 ₱ 74.22
3.4c Unskilled Laborer 6 1.16 ₱ 57.17
3.4d Construction Foreman (STRIPPING) 1 0.56 ₱ 102.73
3.4e Unskilled Laborer (STRIPPING) 6 0.56 ₱ 57.17
3.4f H-Frame 1.7m x 1.2m 40 set
3.4g Shoring Jack, 3.8m full extension 62 pcs
3.4h Adj. U-Head Jack, 0.60m 80 pcs
3.4i Adj. Base Jack, 0.60m 80 pcs
3.4j 1-1/2"GI Pipe x 6.0m 62 pcs
3.4k 1-1/2"GI Pipe x 3.0m 16 pcs
3.4l 1-1/2"GI Pipe x 4.0m 32 pcs
3.4n 1-1/2"GI Pipe x 1.0m 216 pcs
3.4o Tie Rod x 0.60m 278 pcs
3.4p Round Wing Not 558 pcs
3.4q 1.22m x 2.44m x 19mm thick Penolic Board - 5 uses 34 sheet
3.4r Good Lumber - 4 uses 450 bd ft
3.4s CWN 23 kg
rade 40
kgs TOTAL HOUR/S NEEDED = 9.99
₱ 1,026.00
₱ 2,223.79
₱ 6,851.74
0.50 ₱ 219.75 ₱ 1,097.36
0.50 ₱ 351.50 ₱ 1,755.28
₱ 1,010.15
₱ 591.84 ₱ 49,714.56 ₱ 49,714.56
₱ 147.84 ₱ 7,687.68 ₱ 7,687.68
₱ 80.000 ₱ 1,719.11 ₱ 1,719.11
₱ 2,956.07
SUB-TOTAL ₱ 76,041.75
8 DAYS)
CU.M. TOTAL HOUR/S NEEDED = 19.07
₱ 1,959.48
₱ 2,831.36
₱ 4,361.86
1.00 ₱ 172.00 ₱ 3,280.74
915.27
₱ 1,296.84 ₱ 6,678.73 ₱ 6,678.73
₱ 1,296.84 ₱ 3,339.36 ₱ 3,339.36
₱ 250.00 ₱ 11,500.00 ₱ 11,500.00
SUB-TOTAL ₱ 34,866.79
4.2 SLAB ON FILL, CORRIDOR AND RAMP
REINFORCING STEEL (DEFORMED), Grade 40
TOTAL WEIGHT = 455.02 kgs OUTPUT PER HOUR = 143.44
4.2a Construction Foreman 1 1.00 ₱ 102.73
4.2b Skilled Laborer 3 1.00 ₱ 74.22
4.2c Unskilled Laborer 12 1.00 ₱ 57.17
4.2d Bar Cutter 1 pc
4.2e Bar Bender 1 pc
4.2f Minor Tools (10% of Labor Cost)
4.2g REBAR, Gr 40, 10mm Ø x 6m long 114.00 pcs
4.2h #16 Galvanized Iron Wire 6.83 kg
4.2i Consumables (5% of Materials Cost)
MASONRY WORKS
4.3 CHB Non Load Bearing (Inc. Reinforcing Steel ) 150mm thk.
TOTAL AREA = 139.1 SQ.M. OUTPUT PER HOUR = 3.18
4.3a Construction Foreman 1 1.00 ₱ 102.73
4.3b Skilled Laborer 2 1.00 ₱ 74.22
4.3c Unskilled Laborer 3 1.00 ₱ 57.17
4.3d One Bagger Mixer 1 pc
4.3e Minor Tools (10% of Labor Cost)
4.3f 150 mm thk CHB (Non load Bearing) 1808.3 pc
4.3g Sand 5.564 cu.m.
4.3h Portland Cement 208.65 bags
4.3i REBAR, Gr 40, 10mm Ø x 6m long 56 pcs
4.3j #16 Tie wire 6.955 kg
Grade 40
kgs TOTAL HOUR/S NEEDED = 3.17
₱ 325.88
₱ 706.32
₱ 2,176.25
0.50 ₱ 219.75 ₱ 348.55
0.50 ₱ 351.50 ₱ 557.51
₱ 320.85
₱ 147.84 ₱ 16,853.76 ₱ 16,853.76
₱ 80.000 ₱ 546.02 ₱ 546.02
₱ 869.99
SUB-TOTAL ₱ 22,705.13
8 DAYS)
CU.M. TOTAL HOUR/S NEEDED = 26.11
₱ 2,682.39
₱ 3,875.93
₱ 5,971.09
1.00 ₱ 172.00 ₱ 4,491.11
1,252.94
₱ 1,296.84 ₱ 9,142.72 ₱ 9,142.72
₱ 1,296.84 ₱ 4,571.36 ₱ 4,571.36
₱ 250.00 ₱ 16,000.00 ₱ 16,000.00
SUB-TOTAL ₱ 47,987.55
Grade 40
kg TOTAL HOUR/S NEEDED = 14.24
₱ 1,463.09
₱ 3,171.14
₱ 9,770.62
0.50 ₱ 219.75 ₱ 1,564.85
0.50 ₱ 351.50 ₱ 2,503.04
₱ 1,440.48
₱ 591.84 ₱ 65,102.40 ₱ 65,102.40
₱ 378.72 ₱ 1,514.88 ₱ 1,514.88
₱ 147.84 ₱ 15,227.52 ₱ 15,227.52
₱ 80.000 ₱ 2,451.46 ₱ 2,451.46
₱ 883.95
SUB-TOTAL ₱ 105,093.41
8 DAYS)
CU.M. TOTAL HOUR/S NEEDED = 28.22
₱ 2,899.27
₱ 4,189.31
₱ 6,453.86
1.00 ₱ 172.00 ₱ 4,854.22
1,354.24
₱ 1,296.84 ₱ 9,881.92 ₱ 9,881.92
₱ 1,296.84 ₱ 4,940.96 ₱ 4,940.96
₱ 250.00 ₱ 17,145.00 ₱ 17,145.00
SUB-TOTAL ₱ 51,718.78
₱ 573,723.16
Total Material Cost ₱ 431,320.72
Total Equipment Cost ₱ 44,480.31
Total Labor Cost ₱ 97,922.13
DIVISION 5 2ND FLOOR WORKS
ITEM NO. LABOR
DESCRIPTION NO. OF PERSON/S QUANTITY UNIT
No.of Hour/s Hourly Rate
REINFORCING STEEL (DEFORMED), Grade 40
5.1 COLUMN 1 (C1, PC-1, PC-2)
TOTAL WEIGHT = 1,482.20 kg OUTPUT PER HOUR = 143.44
5.1a Construction Foreman 1 1.00 ₱ 102.73
5.1b Skilled Laborer 3 1.00 ₱ 74.22
5.1c Unskilled Laborer 12 1.00 ₱ 57.14
5.1d Bar Cutter 1 pc
5.1e Bar Bender 1 pc
5.1f Minor Tools (10% of Labor Cost)
5.1g REBAR, Gr 40, 20mm Ø x 6m long 72.00 pcs
5.1h REBAR, Gr 40, 16mm Ø x 6m long 21.00 pcs
5.1i REBAR, Gr 40, 10mm Ø x 6m long 59.00 pcs
5.1j #16 Galvanized Iron Wire 22.23 kg
5.1k Consumables (5% of Materials Cost)
MASONRY WORKS
5.3 CHB Non Load Bearing (Inc. Reinforcing Steel ) 150mm thk.
TOTAL AREA = 139.1 SQ.M. OUTPUT PER HOUR = 3.18
5.3a Construction Foreman 1 1.00 ₱ 102.73
5.3b Skilled Laborer 2 1.00 ₱ 74.22
5.3c Unskilled Laborer 3 1.00 ₱ 57.17
5.3d One Bagger Mixer 1 pc
5.3e Minor Tools (10% of Labor Cost)
5.3f 150 mm thk CHB (Non load Bearing) 1808.3 pc
5.3g Sand 5.564 cu.m.
5.3h Portland Cement 208.65 bags
5.3i REBAR, Gr 40, 10mm Ø x 6m long 56 pcs
5.3j #16 Tie wire 6.955 kg
5.4 CHB Non Load Bearing (Inc. Reinforcing Steel ) 100mm thk.
TOTAL AREA = 124.09 SQ.M. OUTPUT PER HOUR = 3.18
5.4a Construction Foreman 1 1.00 ₱ 102.73
5.4b Skilled Laborer 2 1.00 ₱ 74.22
5.4c Unskilled Laborer 3 1.00 ₱ 57.17
5.4d One Bagger Mixer 1 pc
5.4e Minor Tools (10% of Labor Cost)
5.4f 100 mm thk CHB (Non load Bearing) 1613.17 pcs
5.4g Sand 4.96 cu.m.
5.4h Portland Cement 186.14 bags
5.4i REBAR, Gr 40, 10mm Ø x 6m long 50.00 pcs
5.4j #16 Tie wire 6.20 kg
ade 40
kg TOTAL HOUR/S NEEDED = 12.19
₱ 1,252.28
₱ 2,714.22
₱ 8,362.81
0.50 ₱ 219.75 ₱ 1,339.37
0.50 ₱ 351.50 ₱ 2,142.39
₱ 1,232.93
₱ 378.72 ₱ 55,671.84 ₱ 55,671.84
₱ 213.12 ₱ 6,819.84 ₱ 6,819.84
₱ 148.84 ₱ 25,302.80 ₱ 25,302.80
₱ 80.000 ₱ 2,098.24 ₱ 2,098.24
₱ 1,370.05
SUB-TOTAL ₱ 108,306.77
DAYS)
CU.M. TOTAL HOUR/S NEEDED = 33.26
₱ 3,416.72
₱ 4,937.00
₱ 7,605.73
1.00 ₱ 172.00 ₱ 5,720.59
1,595.95
₱ 1,296.84 ₱ 11,645.62 ₱ 11,645.62
₱ 1,296.84 ₱ 5,822.81 ₱ 5,822.81
₱ 250.00 ₱ 20,205.00 ₱ 20,205.00
SUB-TOTAL ₱ 60,949.43
₱ 618,414.72
Total Material Cost ₱ 469,592.20
Total Equipment Cost ₱ 50,551.39
Total Labor Cost ₱ 98,289.55
DIVISION 6 STAIRS & RAILINGS
LABOR
ITEM NO. DESCRIPTION NO. OF PERSON/S QUANTITY UNIT
No.of Hour/s Hourly Rate
6.1 STAIRS
REINFORCING STEEL (DEFORMED), Grade 40
TOTAL WEIGHT = 156.59 kg OUTPUT PER HOUR = 143.44
6.1a Construction Foreman 1 1.00 ₱ 102.73
6.1b Skilled Laborer 3 1.00 ₱ 74.22
6.1c Unskilled Laborer 12 1.00 ₱ 57.17
6.1d Bar Cutter 1 pc
6.1e Bar Bender 1 pc
6.1f Minor Tools (10% of Labor Cost)
6.1g REBAR, Gr 40, 16mm Ø x 6m long 5.00 pcs
6.1h REBAR, Gr 40, 12mm Ø x 6m long 5.00 pcs
6.1i REBAR, Gr 40, 10mm Ø x 6m long 5.00 pcs
6.1j #16 Galvanized Iron Wire 2.35 kg
6.1k Consumables (5% of Materials Cost)
6.2 RAILINGS
TOTAL = 1.00 l.s OUTPUT
6.2a Construction Foreman 1 40.00 ₱ 102.73
6.2b Skilled Laborer 2 40.00 ₱ 74.22
6.2c Unskilled Laborer 2 40.00 ₱ 57.17
6.2d Welding Machine 1 pc
6.2e Cutting outfit 1 pc
6.2f Minor Tools (10% of Labor Cost)
6.2g 50 mm Ø G.I. Stainless Pipe 8 pcs
6.2h 1" x 1" x 1.5 StainlessTubular Bar 10 pcs
6.2i 25 mm x 3mm thick flat bar 6m. Long 24 pcs
6.2j 25mm Ø G.I. Stainless Pipe 2 pcs
6.2k Wire mesh 1 ls
6.2l Welding Rod ( Stainless ) 5 kls
6.2m Consumables (5% of material cost)
ade 40
kg TOTAL HOUR/S NEEDED = 1.09
₱ 112.15
₱ 243.07
₱ 748.93
0.50 ₱ 219.75 ₱ 119.95
0.50 ₱ 351.50 ₱ 191.86
₱ 110.42
₱ 378.72 ₱ 1,893.60 ₱ 1,893.60
₱ 213.12 ₱ 1,065.60 ₱ 1,065.60
₱ 148.84 ₱ 744.20 ₱ 744.20
₱ 80.000 ₱ 187.91 ₱ 187.91
₱ 194.57
SUB-TOTAL ₱ 5,612.25
DAYS)
CU.M. TOTAL HOUR/S NEEDED = 7.37
₱ 757.16
₱ 1,094.06
₱ 1,685.46
1.00 ₱ 172.00 ₱ 1,267.70
353.67
₱ 1,296.84 ₱ 2,580.71 ₱ 2,580.71
₱ 1,296.84 ₱ 1,290.36 ₱ 1,290.36
₱ 250.00 ₱ 4,477.50 ₱ 4,477.50
SUB-TOTAL ₱ 13,506.61
7.1 Prepainted Metal Sheets (above 0.427mm) Corrugated Type Long Span
TOTAL AREA = 116.28 SQ.M. OUTPUT PER HOUR =
7.1a Construction Foreman 1 1.00 ₱ 102.73
7.b Skilled Laborer 1 1.00 ₱ 74.22
7.1c Unskilled Laborer 2 1.00 ₱ 57.17
7.1d Minor Tools (10% of Labor Cost)
7.1e Prepainted Metal Sheets ( Long Span,0.5mm thk) 1.05
7.1f J-bolt with washers 20
7.1g Consumables (3% of Materials Cost)
8.3 MOLDINGS
TOTAL AREA = 55 SQ.M. OUTPUT PER HOUR = 7.125
8.3a Construction Foreman 1 1.00 ₱ 102.73
8.3b Skilled Laborer 2 1.00 ₱ 74.22
8.3c Unskilled Laborer 4 1.00 ₱ 57.17
8.3d Minor Tools (10% of Labor Cost)
8.3e Cement 18.15 bag
8.3f Sand 1.485 cu.m.
SUB-TOTAL ₱ 49,064.49
SUB-TOTAL ₱ 15,653.14