Professional Documents
Culture Documents
LTCC
LTCC
According to PFRS 15, for revenue recognized over time such as construction contracts to build or create an asset f
We measure progress towards the satisfaction of the performance obligation using:
1. Input method such as cost-to-cost method (IF SILENT)
2. Output method such as survey of experts and % floor area completed
2023
85,000,000.00 Costs na nagastos na (past)
85,000,000.00 Total costs at completion of the project
100.000%
2023
100,000,000.00 Changes are accounted for prospectively
(85,000,000.00) Changes are accounted for prospectively
15,000,000.00
100.000%
15,000,000.00
(13,750,000.00)
1,250,000.00
2023
100,000,000.00
100.000%
100,000,000.00
(68,750,000.00)
31,250,000.00
(30,000,000.00)
1,250,000.00
2023
85,000,000.00
15,000,000.00
100,000,000.00
2023
100,000,000.00
100.000%
100,000,000.00
2023
100,000,000.00
(100,000,000.00)
-
ntries: (VIEW 1) Alternative:
Prepaid Contract Costs 35,000,000.00 CIP 35,000,000.00
Cash 35,000,000.00 Cash
To recognize recognition of contract costs as asset
SFP (View 1)
AR from billings (16M - 14M) 2,000,000.00 PFRS 15: Receivable if right to receive the consideration
Contract Asset
CIP 43,750,000.00
PB (16,000,000.00)
Contract Asset 27,750,000.00 PFRS 15: Contract Asset if right to receive the considera
SFP (View 2)
AR from billings (16M - 14M) 2,000,000.00
Additional receivable
CIP 43,750,000.00
PB (16,000,000.00)
Additional receivable 27,750,000.00
Total receivable under view 2 29,750,000.00 Under View 2, no contract asset since technically billing
JUST REMEMBER:
At the end of the contract (100% completion) and the customer has accepted the asset
Close the CIP and PB accounts
Progress Billings 100,000,000.00
CIP 100,000,000.00
AND REMEMBER: AT THE END OF THE CONTRACT: CIP = PB TO DATE = CONTRACT PRICE
If may problem na walang contract price, kunin mo yung PB to date at completion.
35,000,000.00
43,750,000.00
16,000,000.00
ging to customer
14,000,000.00
ght to receive the consideration is unconditional already (since billed already, unconditional)
if right to receive the consideration is still conditional (other than passage of time) [interpretation: conditional on future billing]
According to PFRS 15, for revenue recognized over time such as construction contracts to build or create an asset f
We measure progress towards the satisfaction of the performance obligation using:
1. Input method such as cost-to-cost method (IF SILENT)
2. Output method such as survey of experts and % floor area completed
2021 2022
Revenue (workback) 35,000,000.00 20,000,000.00
Cost (35,000,000.00) (20,000,000.00)
RGP - -
2021 2022
CITD 35,000,000.00 55,000,000.00
CRGP - -
CIP 35,000,000.00 55,000,000.00
PB (16,000,000.00) (44,000,000.00)
Excess of CIP over PB 19,000,000.00 11,000,000.00
2023
85,000,000.00 Costs na nagastos na (past)
- Costs na gagastusin pa para matapos (future)
85,000,000.00
2023
85,000,000.00 Costs na nagastos na (past)
85,000,000.00 Total costs at completion of the project
100.000%
2023
100,000,000.00 Changes are accounted for prospectively
(85,000,000.00) Changes are accounted for prospectively
15,000,000.00
100.000%
15,000,000.00
-
15,000,000.00
2023
45,000,000.00
(30,000,000.00)
15,000,000.00
2023
85,000,000.00
15,000,000.00
100,000,000.00
(100,000,000.00)
-
Costs Data
2021 2022
Costs incurred to date 35,000,000.00 55,000,000.00
Estimated costs to complete 45,000,000.00 25,000,000.00
Estimated total costs at completion 80,000,000.00 80,000,000.00
According to PFRS 15, for revenue recognized over time such as construction contracts to build or create an asset for the cust
We measure progress towards the satisfaction of the performance obligation using:
1. Input method such as cost-to-cost method (IF SILENT)
2. Output method such as survey of experts and % floor area completed
2023
85,000,000.00
85,000,000.00
100.000%
2023
100,000,000.00
(85,000,000.00)
15,000,000.00
100.000% ASSUMED based from estimate of engineer
15,000,000.00
(13,000,000.00)
2,000,000.00
2023
100,000,000.00
100.000%
100,000,000.00
2023
100,000,000.00
(100,000,000.00)
-
2022 2023 2021 Prepaid Contract Costs
80,000,000.00 85,000,000.00 Cash
65.000% 100.000% MATCHING PRINCIPLE To recognize recognition of contract cost
52,000,000.00 85,000,000.00
(32,000,000.00) (52,000,000.00) CIP
20,000,000.00 33,000,000.00 Revenue from Contract
To recognize revenue for 2021
55,000,000.00 85,000,000.00
(52,000,000.00) (85,000,000.00) Cost of Contract
3,000,000.00 - Prepaid Contract Costs
To record amortization of contract costs
COSTS ONLY (REVENUE NOT SHOWN ANYMORE)
2022 Prepaid Contract Costs
Cash
Cost of Contract
Prepaid Contract Costs
2023 Prepaid Contract Costs
Cash
Cost of Contract
Prepaid Contract Costs
35,000,000.00
35,000,000.00
ecognition of contract costs as asset
40,000,000.00
40,000,000.00
evenue for 2021
32,000,000.00
32,000,000.00
rtization of contract costs (matching principle)
OT SHOWN ANYMORE)
20,000,000.00
20,000,000.00
20,000,000.00
20,000,000.00
30,000,000.00
30,000,000.00
33,000,000.00
33,000,000.00
Site labor costs
Cost of materials used in construction
Cost of materials not yet used in construction
Depreciation of construction equipment
Depreciation of idle equipment not used in any projects
Cost of design and technical assistance directly related to the project
Insurance costs (75% related to other projects; 25% related to this project)
Research and development costs for which reimbursement is not specified in the contract
General and administrative costs for which reimbursement is specified in the contract
Construction overhead
Site supervision costs
Advance payments to subcontractors (work not yet started)
Selling costs
Question 2: if exclusive
Classification
10,500,000 Contract costs
8,000,000 Contract costs
1,000,000 It depends (PIC Q&A 2020-02)
500,000 Contract costs
50,000 OPEX
300,000 Contract costs
400,000 25% contract costs
60,000
OPEX
90,000
Contract costs
130,000 Contract costs
200,000 Contract costs
1,500,000 Unamortized
80,000 OPEX if silent
19,820,000.00
19,820,000.00
20,820,000.00
Question 1:
Mobilization fee (50M x 10%) 5,000,000.00
Collection from progress billings
06/06/2021 (20% of 50M) 10,000,000.00
10/12/2021 (10% of 50M) 5,000,000.00
12/26/2021 (12/30/2021 acceptance) - Not yet collected in 2021
Total 15,000,000.00
Less 10% retention (1,500,000.00)
Collection from progress billings 13,500,000.00
Total collections in 2021 18,500,000.00
NOTE: Mobilization fee and retention provisions DO NOT affect RGP computation because these are purely balance sheet acc
PB computation 2021
6-Jun-21 20%
12-Oct-21 10%
26-Dec-21 7%
12-Jul-22
23-Dec-22
PB % to date 37%
Contract price 50,000,000.00
PB to date 18,500,000.00
CIP 20,000,000.00
PB to date (18,500,000.00)
Contract Asset (Contract Liability) 1,500,000.00
2022
55,000,000.00
0.90
49,500,000.00
2022
20%
10%
7%
30%
18%
85%
55,000,000.00
46,750,000.00
49,500,000.00
(46,750,000.00)
2,750,000.00 View #1
If the outcome cannot be estimated reliably - use cost recovery method
% of completion is either 0% or 100%
CP 150,000,000.00
TEC (100,000,000.00) Example
TEGP 50,000,000.00
% 0% Cost recovery
RGP -
Revenue 5,000,000.00
Costs (5,000,000.00)
RGP -
If negative TEGP, it means that the construction contract is expected to be completed at a loss
It is considered as an onerous contract (PAS 37)