Download as pdf
Download as pdf
You are on page 1of 1
= MIS Fida Construction and Earthworks NO:EE/CDD/CKL/2015/42 /11-W Office 27, 3RD Floor, Al Anayat Mall Dated: G11 Markaz Islamabad Subject: REHABILITATION OF IRRIGATION CHANNEL OF KHAI DAM (CONSTRUCTION OF STRUCTURE Il OF SPILLWAY DAM) Substantial Completion Certificate ‘Substantial Completion Certified under clause 40 of General Condition of Contract. Name of Project, REHABILITATION OF IRRIGATION CHANNEL OF KHAT DAM (CONSTRUCTION OF OUTFALL STRUCTURE II OF SPILLWAY OF KHAI DAM) ‘Commencement Date 21" November 2014 Time Duration for Completion 365 days, Effective date of Completion 10® December 2015 Original contract valve 105,038,120/- ‘Contractor Letter of Request for Substantial Letter No, FIDA/SDDC/95 dated January 18, completion certificate 2015 Period of Maintenance Clause 43 01 Year ‘Pursuant to Clause 40 of General Condition of Contract the Engineer In charge consider the above said project as sustainably completed w.e.f 10® December, 2015 and hence the certificate of Substantial completion is hereby issued for the above-mentioned project. ‘The works/defeets mentioned in the punch list must be completed in the shortest possible time. RECOMMENDED BY /) APPROVED BY tk — = Ze 22 22I pe Addl. Chief Engineer /PD - 1 Chief Engineer

You might also like