Professional Documents
Culture Documents
PNR 000189 Highlights - EN
PNR 000189 Highlights - EN
PNR 000189 Highlights - EN
Systems – General
1
Rev_00 08.29.22
Summary
Summar
▪ VPS – Elements of the PNR Implementation Process
▪ Scope and Applicability
▪ Bowtie Synthesis
▪ Main Standards and RAGAGEP
▪ Critical Controls
▪ Highlights and Requirements
▪ Examples of Deployment / Application of PNRs
▪ Developers (multipliers)
2
VPS – ELEMENTS OF THE PNR IMPLEMENTATION ASSET
PROCESS MANAGEMENT
EXCLUSIONS
APPLICABILITY
• Monorail hoist;
• Typical Mobile Crane • Lifting platform;
• Railway Mobile Crane; • Fork-lift;
• Truck mounted crane;
• Overhead Crane; • Tower crane;
• Gantry Crane; • Jib crane;
• Temporary construction elevator;
• Industrial Elevator. • Conventional elevators for buildings;
• Underground mine elevator (shafts);
• Cable-way Systems.
Operation
4 Project Supply
Construction and
Commissioning Operation Maintenance Decommissioning
Assembling
ASSET
BOWTIE SYNTHESIS MANAGEMENT
Failure Modes Preventive Barriers Risk Scenarios Mitigating Barriers Consequences
Hoisting
5 system failure
ASSET
BOWTIE SYNTHESIS MANAGEMENT
Failure Modes Preventive Barriers Risk Scenarios Mitigating Barriers Consequences
Asset/Load collision
Overspeed
EN 15011:2020
Overhead and Gantry Cranes
ASME B30.2:2016
ASME A17.1:2019
Industrial Elevators
ISO 8100-1:2019
ASME B30.10:2019
Hooks and below-the-hook accessories
ASME B30.20:2021
ISO 12480-1:1997
Lifting planning and operation
ASME P30.1:2019
RAGAGEP – Benchmarking carried out in Mining, Petrochemical and Oil & Gas industries, whose RAGAGEPs
were 8 used in constructing these standards, which made it possible to apply requirements of relevant
international standards in a practical and efficient way.
ASSET
CRITICAL CONTROLS MANAGEMENT
The Critical Controls below apply to Mobile Cranes and are detailed on “One Pages” in
Appendix II of the standard.
9
ASSET
CRITICAL CONTROLS MANAGEMENT
The Critical Controls below apply to Overhead and Gantry Cranes and are detailed on “One
Pages” in Appendix II of the standard.
10
ASSET
CRITICAL CONTROLS MANAGEMENT
The Critical Controls below apply to Industrial Elevators and are detailed on “One Pages” in
Appendix II of the standard.
11
ASSET
HIGHLIGHTS AND REQUIREMENTS MANAGEMENT
Below are some examples of requirements that can be found in the standard:
Design
For all new cargo handling equipment to be acquired, a technical specification (TS) shall be prepared.
The limiting and/or indicator devices described in subsections 6.2.2.5.1 to 6.2.2.5.5 apply to all mobile
cranes with a rated capacity of 1 000 kg or more, or net lifting moment above 40 000 Nm, due to loading.
These devices shall meet the criteria defined in section 4.2.6 of EN 13000.
Construction, Assembling and Comissioning
In the commissioning phase, performance and safety device tests should be performed in accordance
with the Inspection and Test Plan. The minimum tests during commissioning are listed in sections 6.3.2.1
to 6.3.2.3.
Operation and Maintenance
Motion and performance limiting devices must not be routinely used as an operational control.
For existing assets that do not have manufacturer's maintenance instructions, the activities described in
APPENDIX V – ITPM – Maintenance Activities should be observed as a minimum reference.
Supplies and Services
In addition to the commissioning requirements described in section 6.3.2, all the documentation
necessary for the safe operation of the equipment, its correct maintenance, as well as certificates of
quality,
12 tests and warranties should be provided.
EXAMPLES OF DEPLOYMENT / APPLICATION ASSET
MANAGEMENT
OF PNRS
As part of the PNR, the design, operation and maintenance documents will specify the way (“How”) to implement the following
requirements:
✓ Creation of a technical specification for the acquisition of cargo handling equipment, ensuring that such devices are supplied
and have the required performance.
✓ Use of the information provided by these devices for lifting planning and operation activities;
PNR requirements may have more or less technical detail, whatever is necessary to establish safe
operational conditions. Such requirements will be detailed in project documents, procedures and operation
13 plans for application of the Standard
ASSET
DEVELOPERS (MULTIPLIERS) MANAGEMENT
Check the last Appendix to the standard and find out who are the representatives of your
area.
14
AM
15