Time Schedule Sucofindo

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

TIME SCHEDULE

Construct Additional Office SUCOFINDO

Month
Weight
NO. Description Unit Qty January February March Remarks
5-Mar 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr 30-Apr 7-May 14-May 21-May 28-May
(%) 11-Mar 18-Mar 25-Mar 1-Apr 8-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jun
100
A PEKERJAAN PEMBONGKARAN ls 1.00 9.00 9.00

B PERSIAPAN
- Bowplank m 45.00 0.53 0.53

C PEKERJAAN PONDASI
- Galian tanah m3 2.40 0.01 0.01

- Pondasi Batu Gunung m3 5.40 1.34 1.34 90


- Beton K250 m3 2.40 1.57 1.57

- Timbunan m3 38.00 0.73 0.73

D PEKERJAAN SLOOF, KOLOM DAN BALOK


- Kolom Ulin 100x100 m3 1.20 1.17 1.17

- Sloof Ulin 100x100 m3 0.80 0.78 0.78

- Balok Ulin 100x100 m3 1.20 1.22 1.22

- Balok Ulin 50x100 m3 0.80 0.81 0.81

E PEKERJAAN DINDING 80
- Rangka Dinding Kapur 50x70 m2 434.80 9.95 9.95

- Dinding Nusaboard 6mm m2 869.60 21.24 10.62 10.62

- Dinding KM Keramik 20x25 m2 21.00 1.11 1.11

- Dinding Dapur Keramik 20x25 m2 4.00 0.21 0.21

F PEKERJAAN ATAP DAN PLAFON


- Kuda-kuda Kapur 50x100 m3 1.00 1.05 1.05

- Gording Kapur 50x100 m3 0.80 0.84 0.84


70
- Usuk Kapur 50x70 m3 0.60 0.63 0.63

- Atap Soka m2 132.00 3.02 3.02

- Talang Air m 10.00 0.12 0.12

- Listplank Nusa plank 200x8 m 46.00 0.43 0.43

- Rangka Plafon Kapur 50x70 m2 153.00 4.33 2.16 2.16

- Plafon Nusaboard 3.5mm m2 153.00 2.67 1.34 1.34

- List Plafon m 188.00 0.72 0.72

G PEKERJAAN PINTU JENDELA 60


- Kusen Pintu 1 Plong bh 11.00 1.19 1.19

- Kusen Pintu Dapur bh 1.00 0.16 0.16

- Kusen Jendela 1 lubang bh 1.00 0.08 0.08

- Kusen Jendela 2 lubang bh 4.00 0.48 0.48

- Boven kecil bh 4.00 0.22 0.22

- Boven besar bh 5.00 0.37 0.37

- Daun Pintu, Engsel, Slot set 11.00 2.69 2.69

- Daun Jendela, Engsel, Lamskar set 9.00 1.57 1.57 50


H PEKERJAAN CAT
- Cat Dinding m2 869.60 2.46 2.46

- Cat Plafon m2 153.00 0.59 0.59

- Cat Kusen Pintu 1 Plong bh 11.00 0.15 0.15

- Cat Kusen Pintu Dapur bh 1.00 0.02 0.02

- Cat Kusen Jendela 1 lubang bh 1.00 0.02 0.02

- Cat Kusen Jendela 2 lubang bh 4.00 0.19 0.19


40
- Cat Boven kecil bh 4.00 0.05 0.05

- Cat Boven besar bh 5.00 0.09 0.09

- Cat daun pintu bh 11.00 0.30 0.30

- Cat daun jendela bh 9.00 0.16 0.16

I PEKERJAAN LANTAI
- Rabat Beton m3 8.10 5.31 5.31

- Lantai 1 Keramik 40x40 m2 72.00 4.35 4.35

- Lantai 2 Papan Ulin 20x200 Ketam m3 1.90 2.31 2.31 30


- Lantai KM Keramik 20x20 m2 4.00 0.22 0.22

- Lantai Tempat Wudhu Keramik 20x20 m2 2.30 0.14 0.14

J PEKERJAAN PLUMBING
- Closet Jongkok unit 2.00 0.64 0.64

- Kitchen Zink unit 1.00 0.32 0.32

- Meja Kitchen Zink unit 1.00 0.64 0.64

- Instalasi Pipa Air Bersih 3/4" m 32.00 0.26 0.26

- Instalasi Pipa Air Kotor 3" m 32.00 0.99 0.99 20


- Instalasi Pipa Air Kotor 4" m 16.00 0.60 0.60

- Keran bh 7.00 0.18 0.18

- Septictank Biofill 3000 ltr unit 1.00 5.27 5.27

K PEKERJAAN PARKIR MOTOR


- Kolom Ulin 100x100 m3 0.30 0.29 0.29

- Gording Kapur 50x100 m3 0.30 0.31 0.31

- Usuk Kapur 50x70 m3 0.20 0.21 0.21


10
- Atap Soka m2 40.00 0.92 0.92

- Listplank Nusa plank 200x8 m 18.00 0.17 0.17

- Rabat Beton m3 3.20 2.10 2.10

L PEKERJAAN TANGGA
- Balok Tangga Ulin 50x100 m3 0.10 0.11 0.11

- Anak Tangga Ulin 2x200 m3 0.10 0.12 0.12

- Pagar Tangga Kapur 50x70 m3 0.20 0.21 0.21

- Cat pagar Tangga ls 1.00 0.12 0.12 0


100.00
Progress Plan per Week (%) 9.00 1.88 4.25 16.78 5.98 10.73 11.04 5.35 9.50 6.63 5.34 10.34 3.18
Progress Plan Cummulative (%) 9.00 10.88 15.13 31.91 37.89 48.62 59.67 65.01 74.51 81.14 86.48 96.82 100.00
Actual Progress per Week (%)
Actual Progress Cummulative (%)
Deviation (%)

Approved by Prepared by
PT. SUCOFINDO PT. Wira Keluarga Mandiri