Jadwal Pelaksanaan PLTS

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

JASA PENGADAAN DAN PEMBANGUNAN PLTS 3 MW DI LOKASI PT.

BADAK LNG
Activity ID Activity Name Original Duration Schedule % Start Finish November
Total Float
2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018
Complete
19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26
JASA P EN GADAAN DAN PEMB AN GUNAN P LTS 3 MW D I LOKASI PT. BADAK L NG 180 0% 04-Dec-17 08 01-Jun-18 17 0 01-Jun-18 17, JASA PENGADAAN DAN PEMBANGUNAN PLTS 3 MW DI LOKASI PT. BAD AK LNG
CONTRACT/SPMP 0 0% 04-Dec-17 08 04-Dec-17 08 0 04-Dec-17 08, CONTRACT/SPMP
A1000 Contract/SMPK 0 100% 04-Dec-17 08 0 Contract/SMPK, 04-Dec-17 08
PREPARATION 27 0% 04-Dec-17 08 30-Dec-17 17 153 30-Dec-17 17, PREPARATION
A1010 Project Execution Plan 2 0% 04-Dec-17 08 05-Dec-17 17 8 Project Execution Plan
A1020 Key Personil 2 0% 04-Dec-17 08 05-Dec-17 17 8 Key Personil
A1030 Schedule & PMR 2 0% 04-Dec-17 08 05-Dec-17 17 8 Schedule & PMR
A1035 EDL 2 0% 04-Dec-17 08 05-Dec-17 17 0 EDL
A1040 Kick Off Meeting 1 0% 06-Dec-17 08 06-Dec-17 17 8 Kick Off Meeting
A1050 Site Survey 3 0% 07-Dec-17 08 09-Dec-17 17 167 Site Survey
A1060 Permits 14 0% 07-Dec-17 08 20-Dec-17 17 97 Permits
A1070 IMB 21 0% 07-Dec-17 08 27-Dec-17 17 121 IMB
A1080 Rent of heavy equipmen 7 0% 21-Dec-17 08 27-Dec-17 17 156 Rent of heavy equipmen
A1090 HSE Equipment (APD) 5 0% 07-Dec-17 08 11-D ec-17 17 172 HSE Equipment (APD)
A1620 Mobilization 10 0% 21-Dec-17 08 30-Dec-17 17 97 Mobilization
A1670 Direksi Kit & War ehouse 3 0% 14-Dec-17 08 16-Dec-17 17 167 Direksi Kit & Warehouse
ENGINEERING 135 0% 05-Dec-17 08 18-Apr-18 17 44 18-Apr-18 17, ENGINEERING
A1100 Procedure 30 0% 07-Dec-17 08 05-Jan-18 17 147 Procedure
A1110 Calculation & Data Sheet 30 0% 05-Dec-17 08 03-Jan-18 17 0 Calculation & Data Sheet
A1120 Drawing 21 0% 08-Dec-17 08 28-Dec-17 17 155 Drawing
A1130 As-Built Drawing 21 0% 29-Mar-18 08 18-Apr-18 17 39 As-Built Drawing
PROCUREMENT 65 0% 09-Dec-17 08 11-Feb-18 17 1 11-Feb-18 17, PROCUREMENT
A1680 Main Equipment 65 0% 09-Dec-17 08 11-Feb-18 17 1 Main Equipment
A1690 Accessories 50 0% 09-Dec-17 08 27-Jan-18 17 0 Accessories
CONSTRUCTION 90 0% 29-Dec-17 08 28-Mar-18 17 65 28-Mar-18 17, CONSTRUCTION
A1700 Preparation 21 0% 31-Dec-17 08 20-Jan-18 17 97 Preparation
A1710 Civil 35 0% 21-Jan-18 08 24-Feb-18 17 97 Civil
A1715 Fabrication 45 0% 02-Jan-18 08 15-Feb-18 17 0 Fabrication
A1720 Testing 56 0% 29-Dec-17 08 22-Feb-18 17 99 Testing
A1730 Installation 56 0% 01-Feb-18 08 28-Mar-18 17 0 Installation
DELIVERY 14 0% 02-Feb-18 08 15-Feb-18 17 1 15-Feb-18 17, DELIVERY
A1560 1st PV Modules 7 0% 02-Feb-18 08 08-Feb-18 17 8 1st PV Modules
A1570 2nd PV Modules 7 0% 09-Feb-18 08 15-Feb-18 17 1 2nd PV Modules
A1580 Trafo 7 0% 09-Feb-18 08 15-Feb-18 17 1 Trafo
A1590 Inverter 7 0% 09-Feb-18 08 15-Feb-18 17 1 Inverter
PRE-COMMISSIONING & COMMISSIONING 60 0% 29-Mar-18 08 27-May-18 17 0 27-May-18 17, PRE-COMMISSIONING & COMMISSIONING
A1740 Pre - Commissioning 35 0% 29-Mar-18 08 02-May-18 17 0 Pre - Commissioning
A1750 Commissioning 25 0% 03-May-18 08 27-May-18 17 0 Commissioning
FINISH PROJECT 15 0% 18-May-18 08 01-Jun-18 17 0 01-Jun-18 17, FINISH PROJECT
A1650 Training 5 0% 18-May-18 08 22-May-18 17 5 Training
A1660 Handover Document & Project 5 0% 28-May-18 08 01-Jun-18 17 0 Handover Document & Project
A1760 Finish 0 0% 01-Jun-18 17 0 Finish,

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation