The formula for the Cost variance is Earned value minus actual costs
Cost variance=20000-25000
Cost variance=-5000
The formula for the Schedule variance is Earned value minus the planned
value
Schedule variance=20000-22000
Schedule variance=-2000
Cost performance index= dividing the Earned value by actual costs