TERMS OF REFERENCE
2022
OBJECTIVE:
The objective of this project is to provide the residents and small business owners of Brgy.
Cabacungan, Lacastellana additional public market buildings for public use.
PROJECT DESCRIPTION
The project shall cover the design and construction of the new Brgy. Cabacungan Public Market
Commercial Rentable Space Building and Bagsakan Building that will be situated within the premises of
the current Cabacungan Public Market.
The Commercial Building shall have a minimum total floor area of 850m2 with each rentable stall
shall have a minimum total floor area of 24m2.The Bagsakan Building shall have a minimum total floor area
of 240m2. Both buildings shall have at least 1 comfort room each for male and female with compliance to
B.P. 344. The plans and designs shall be in accordance with the La Castellana Municipal Engineer’s Office
approved standards and the Building Design Specifications as prescribed in this Terms of Reference (TOR).
The project shall have an Approved Budget for the Contract (ABC) of Twenty Million Pesos (Php
20,000,000.00).
In accordance with the Fire Code of the Philippines, a fully functioning Fire Suppression System shall
be installed within the building. The structural design shall comply with the requirements of the National
Structural Code of the Philippines. The plumbing lines and fixtures shall be in accordance to the National
Plumbing Code of the Philippines. The Electrical Design should comply with the provisions of the Philippine
Electrical Code. Building Design must comply with the requirements of the National Building Code of the
Philippines and Batas Pambansa Blg. 344.
OVERVIEW OF THE REQUIREMENTS
1. The Municipality of La Castellana shall award the project to a Registered Construction Company
with Duly Licensed Building Designers, that shall meet and comply eligibility requirements
specified in R.A. 9184, Annex G, Section 9.2.ii, paragraph A.
2. Bids and Awards Committee (BAC) through the Technical Working Group (TWG), shall
evaluate the eligibility and technical documents. The Constructor shall be selected according to
the quality of the Technical Proposals submitted, experience with similar projects, and the firm’s
reputation, along with the capability of their professional staff to be assigned to the project.
The minimum requirements of the Contractor on the desired expertise and qualifications of individual
personnel necessary for undertaking the project are specified as follows:
The minimum requirements of the Contractor on the desired expertise and qualifications of individual
personnel necessary for undertaking the project are specified as follows:
A. One (1) Site Civil Engineer with at least five (5) years experience in Building construction
B. One (1) Registered Electrical Engineer
C. One (1) Registered Mechanical Engineer
D. One (1) Master Plumber
For the project, the contractor is required to mobilize at least, but not limited to:
The presentation of the Conceptual Design must include a Conceptual Master Plan and 3D walkthrough of
the structure which includes the following:
The Location
Adjoining roads and buildings.
Access to the site.
Buildings
The height, width, length and orientation of buildings and their relationship to the local context and the human
scale.
Entrances and facades (including the proportion of glazing).
The appearance of the buildings.
Their distribution across the site.
Accessibility to and between them.
Lighting.
DETAILED SCOPE OF WORK FOR DESIGN PHASE
The Contractor shall prepare the required professional architectural and engineering design for the Proposed
Admin Building and Food Courts in a manner and level conforming to the standard practices and design
guidelines prepared by the Municipal Engineer’s Office.
The Contractor shall provide and undertake the following:
1. Pre-design Stage
1.1. Site Investigation
1.2. Geodetic Survey
1.3. Consultation with End-user and TWG
1.4. Data Compilation
2. Design Development
2.1. Review of Schematic Design provided by Municipal Engineer’s Office
2.2. Preparation Detailed Architectural and Engineering Plans
2.2.1. Site Development Plan
2.2.1.1. Site Development
2.2.2. Architectural Plan
2.2.2.1. Perspective, Lot Plan, Vicinity Map, Location Plan (2.00 Km. Radius), Table of
Contents
2.2.2.2. Floor Plans (scale 1:100m minimum) including furniture layout
2.2.2.3. Four (4) Elevations (scale 1:100m minimum)
2.2.2.4. Two (2) Sections (scale 1:100m minimum) including spot details when necessary
2.2.2.5. Roof Plan/s showing roof drain (scale 1:100m minimum)
2.2.2.6. Reflected Ceiling Plan/s (scale 1:100m minimum), including details
2.2.2.7. Details of Stairs, fire escapes/exits, accessible ramps, etc. (scale 1:50m), including
details of railings, treads, risers, etc., in the form of plans, elevation/section
2.2.2.8. Details of Toilets (1:50 m) including accessible toilets in the form of plans,
elevation/section
2.2.2.9. Complete Schedule of doors, emergency exits, etc. (scale 1:50 m), including
specifications for materials and hardware
2.2.2.10. Complete Schedule of windows (scale 1:50 m), including specifications for materials
and hardware
2.2.2.11. Complete Schedule of finishes for interior and exterior floors, walls, ceilings
2.2.2.12. Complete Architectural Technical Specifications
2.2.2.13. Complete Architectural Scope of Works
2.2.2.14. Complete Architectural Bill of Quantities
2.2.2.15. Floor Plans showing layout of floor finishes with tile layout plan.(scale 1:100m
minimum)
2.2.2.16. Complete Schedule of Finishes and Details
2.2.3. Structural Plan
2.2.3.1. General Notes and Construction Standards
2.2.3.2. Foundation Plan/s (scale 1:100m minimum)
2.2.3.3. Floor Framing Plan/s (scale 1:100m minimum)
2.2.3.4. Roof Framing Plan (scale 1:100m minimum)
2.2.3.5. Complete Schedule and Detail of Footings, Columns and Shear Walls
2.2.3.6. Complete Schedule and Detail of FTB’s, Girders, Beams, Floor Slabs and other
Structural Components
2.2.3.7. Other Structural Spot Details
2.2.3.8. Complete Structural Analysis and Design
2.2.3.9. Complete Seismic Analysis (May be included in the Structural Analysis)
2.2.3.10. Complete Structural Scope of Works
2.2.3.11. Complete Structural Bill of Quantities
2.2.4. Electrical Plan
2.2.4.1. General Notes and/or Specifications
2.2.4.2. Legends or Symbols
2.2.4.3. Location and Site Plan
2.2.4.4. Complete design/layout of Lightings
2.2.4.5. Complete design/layout of Power (outlets and special outlets)
2.2.4.6. Complete One line diagram from High Voltage to all panel/breakers to every
circuit/branch line (230V)
2.2.4.7. Complete/design for grounding system and lightning protection system
2.2.4.8. Complete Fire Detection and Alarm Circuits Layout (scale 1:100m minimum) and
details including Schedule of Equipment
2.2.4.9. Complete electrical designed analysis and computation of loads for every circuits
2.2.4.10. Complete schedule of loads of every panel
2.2.4.11. Complete design/layout of transformer and service entrance
2.2.4.12. List of complete detailed estimates of materials (includes labor, equipment and other
indirect cost)
2.2.5. Sanitary and Plumbing Plans
2.2.5.1. General Notes and Legends
2.2.5.2. Location and Site Plan
2.2.5.3. Storm Drainage Layout (scale 1:100m minimum) including actual length of tapping
line to Main Drainage Line
2.2.5.4. Water Line Layout (scale 1:100m minimum) including actual length of tapping line
from main source when applicable
2.2.5.5. Sewer line and Vent line layout (scale 1:100m minimum) including actual length of
tapping line to septic tank or existing sewer line
2.2.5.6. Isometric Layout, showing Waterline, Sewer line and Drainage line
2.2.5.7. Detail of connections, catch basins, downspouts, etc.
2.2.5.8. Detail of Septic Tank/Waste Water Treatment Plant
2.2.5.9. Other Sanitary/Plumbing Spot Details
2.2.5.10. Sanitary Scope of Works
2.2.5.11. Sanitary Bill of Quantities
2.3. Preparation of Scope of Work, Detailed Estimates per Scope of Work and Specifications
2.4. Submission of Complete Plans, Scope of Work, Specifications and Estimates to TWG and Provincial
Government Officials
2.5. Signing and Sealing of approved Plans and Estimates
2.6. Application for Construction Permits and Occupancy
3. Design Parameters
The Contractor shall consider the factors hereunder listed for appropriate “Building Design” in order
to be the academic leader in the field of engineering, food technology and environment. Other concern
relevant to the completion of this project is considered but not limited to:
1. The architectural character of the building should appropriately project the image
of Government Institution with mixed occupancies under the National Building
Code of the Philippines.
2. Building form shall be adapted for tropical climatic conditions and the functional
requirements of a public assembly structure.
4. Construction Supervision
4.1. The Contractor shall maintain the field office for easy access.
4.2. For purposes of supervision and monitoring, weekly meeting shall be conducted in the field office.
4.3. The Municipality of La Castellana will have its own Project Inspector with the following functions:
4.3.1. Inspect and monitor the Contractor’s prosecution of the work to ensure full compliance with
the contract provisions.
4.3.2. Prepare a testing schedule and supervise and/or conduct tests necessary to ensure that materials
used and constructions performed are in conformity with the technical specifications.
4.3.3. Inspect construction operations and accomplishments and ascertain that the construction
conforms to the plans and technical specifications.
4.3.4. Check all Contractors’ payment certificates and verify quantities for which payment is made.
4.3.5. Review and or propose any changes in plans deemed necessary to properly fulfill the intent of
the plans and specifications.
4.3.6. Monitor the physical and financial advancement of the works, in comparison with approved
schedules, and order any necessary corrective measures or actions.
4.3.7. Observe and report any adverse effects of construction on the natural environment and instruct
the Contractor to rectify them- issue site instructions if necessary.
4.3.8. Inspect the safety aspects of the construction works and instruct Contractor to correct any
deficiencies therein.
4.3.9. Submit to the MEO the weekly progress reports covering all aspects of construction.
4.3.10. Analyze, evaluate and recommend to the Project Management Team the disposition of claims
for extra work and/or extension of contract time submitted by the Contractor.
4.3.11. When appropriate under the terms of the contract, instruct the Contractor to suspend
construction work.
4.3.12. Analyze and participate in the pre-final and final inspection of the works as provided for in
the general conditions.
4.3.13. Perform any and all other items of work not specifically mentioned which are necessary to
properly supervise the construction activities.
The Contractor shall furnish the Municipal Engineer’s Office, with one (1) set of tracing paper copies of
drawings, all AutoCAD file drawings and MS Word/Excel documents files in CD and seven (7) printed
sets of drawings specifications duly signed and approved for bidding purposes. Extra sets of documents
needed by the contractor are to be charged to the contractor.
All design decisions shall be referred to the appropriate provisions in the latest editions of the National
Building Code, Structural Code, Plumbing Code, Electrical Code, Fire Code of the Philippines,
Accessibility Law and all other pertinent codes and laws.
I. General Requirements
a. Mobilization/Demobilization
The work consists of the mobilization and demobilization of the contractor's forces and
equipment necessary for performing the work required under the contract
b. Construction of Fence Enclosure/Bunkhouse and Office
Utilize 2-Container Van, 1 for Consultants, 1 for the Construction team
Contractor shall furnish, install and maintain temporary facilities required for construction
for the duration of the project, and remove upon completion of the work as specified herein
c. Provision and Consumption of Electricity/Water
The contractor shall provide electricity and water for the entire duration of the project
d. Provision for Safety and Health
The contractor shall ensure the protection and welfare of workers and the general public
within and around the construction site taking into consideration industry practices and
applicable government requirements
e. Application of all necessary Government Permits/Clearances in building construction
VII. Finishes
This covers all works required in connection with surface finished on wood, metal and concrete
surfaces such as plastering, tiling, painting and other finishing applications. Materials specifications
shall be based on the detailed drawings as shown in the plans or a sample of such material shall be
submitted for approval prior to installation or incorporated in the work.
a. Installation of Floor and Wall Finishes (Tiles, Smooth Concrete)
b. Installation of Fiber Cement Board Ceiling
c. Painting Works
Roofing
The work includes construction of concrete and metal structures in accordance with standard
specifications and in conformity with the lines, grades, thickness and typical cross-section. Materials
specifications shall be based on the detailed drawings as shown on plans
d. Fabrication and Installation of Steel Components and Roofing
e. Fabrication and Installation of Steel Components and Tempered Glass Skylight at Roof
f. Installation of hardscapes and landscape.
The Architectural and Engineering Works shall be in accordance with the following Laws, Codes and
Standards.
1.00 GENERAL
• All drawings shall be computer drafted. Drawings shall be submitted both in printed and electronic
copies.
• Keep the same orientation for all plans. The north orientation shall be indicated in all architectural
plans. The orientation of the architectural plans shall be consistent with all the engineering plans.
• Existing buildings and new` works shall be clearly indicated and labeled in site plans.
• Detailed plans shall have a scale not smaller than 1:50 meters.
• Spot detailed plans, elevations and sections shall have a scale not smaller than 1:20 meters.
• Avoid notes such as “see architectural detail” or “see structural”. Always refer with a callout to the
specific detail drawing and sheet number.
8.00 DETAILS
• Provide spot detail plans, elevations and sections of a scale not smaller than 1:10 meters for special
designs with aesthetic treatment and ornamentation.
• Provide detail plan of a scale not smaller than 1:50 meters for all areas needing tile pattern, e.g., lobby,
corridor, entrance walk, showing the position and pattern of tiles.
• Centerline location of plumbing fixtures shall be indicated in detail plan with lines of reference and
its corresponding dimensions. This is to indicate the exact locations of the plumbing/sanitary
roughing-ins.
C. SITE WORKS
1. Contour and survey of the lot, including bearing and dimensions of the property lines
2. Road network, curbs and gutters, and sidewalks
3. Parking spaces
4. Reference location and footprint of proposed and existing buildings, with the corresponding building
names and dimensions, including distances between adjacent buildings, and distances between
buildings and the nearest property lines
5. Reference location of utilities, e.g., water reservoirs, septic tanks, water treatment plant, powerhouse,
transformers, waste storage area, security outposts
• Covered walkways shall be provided for access and connection to other buildings.
• Ramps shall be provided in all main entrances of the buildings and other access opening to walkways
leading to other buildings:
2.00 WALLS
• Toilet wall dimensions shall be based on the modular sizing of tiles to avoid tile serujo and or
excessive tile wastage.
• Layout and work on wall and floor tiles must be aligned, plumb, level and square.
• Tile color and design shall be approved first before installation.
3.00 FLOORS
• If floor tiles in two adjacent rooms with different material, color or design meet at the door opening,
the cut shall be located middle of the door thickness when in a closed position. Provide details in the
floor pattern designs. Provide metal or aluminum threshold where two different floor materials meet,
when required.
• Floors at the openings of toilets for persons with disability shall be sloping. Indicate in the plans and
sections.
• Layout and work on wall and floor tiles must be aligned, plumb, level and square.
• Tile color and design shall be approved first before installation.
9.00 PAINTING
• Painted ceiling shall be in flat latex finish, while cornices and mouldings shall be in gloss enamel
finish.
• Painted interior wall shall be at least in semi-gloss latex finish for rooms, unless specified to a higher
type of paint.
• Painted exterior wall shall be at least in moisture-resistant/water-repellant paint finish, textured or
smooth, unless otherwise specified.
• Paint color and shade shall be approved first before application.
The Civil/Structural Design shall be in accordance with the following Laws, Codes and Standards.
2.00 STANDARDS
B. SITE WORKS
Based on Master Site Development Plan of the public assembly building, provide where applicable complete
design and details of road (concrete with curb gutter, including drainage) network, walkways parking areas
and fencing.
1. Walkway should be at least 100mm thick with concrete strength of 3000psi. Ramps should be
provided, instead of steps, for any change in elevations.
C. BUILDINGS
1. The buildings should be designed using seismic importance factor of 1.25 for immediate occupancy
category. Buildings should be designed in accordance with NSCP requirements up to magnitude 7
for those near seismic source Type A. Seismic gaps between buildings (old and new) should be
properly observed.
2. The buildings should be designed also using wind importance factor of 1.15 (especially for design of
trusses/roofing system). Concrete gutters and parapet walls should be provided as additional
protection to the roofing system during strong typhoons.
3. The structural designer is encouraged to use fire-resistive and non-toxic materials.
The Electrical Design shall be in accordance with the following Laws, Codes and Standards.
2.00 STANDARDS
• Provide and install adequate normal branch circuits for Lighting Systems to all areas using the
standard Lighting Design Analysis. Utilize the standard illumination requirements per area of concern
using the preferred particular type of luminaires.
• Provide and install adequate normal branch circuits for the Power System.
• Provide and install all electrical panels and protections at every Electrical Rooms (per floor).
• 1.5MVA, 400 V, 60 Hz, 3-Phase Sound Proof Power Generating Set, Outdoor Type (MTU-Detroit
or Cummins )
• Provide and install adequate life safety and critical emergency power connected to the alternate power
source.
• Provide and install adequate life safety and emergency signage going to the emergency egress.
• Install minimum of 30 units Emergency Lights, LED
The Sanitary/Plumbing Design shall be in accordance with the following Laws, Codes and Standards.
• National Building Code of the Philippines and its Latest and Amended IRR
• RA9514 Fire Code of the Philippines and its Latest and Amended IRR
• National Plumbing Code of the Philippines (NPCP)
• Sanitation Code of the Philippines
• Existing Local Codes and Ordinances
2.00 STANDARDS
Based on Master Site Development Plan of the public assembly building, the Site Works shall provide
complete layout of the following:
• The Storm Drainage Network shall accommodate the magnitude of peak rates of surface run-off
including drainage coming from the building/s. The system shall be capable of handling the design
flows routing to the designated outfall;
For rainfall calculation and sizing of drainage pipes, refer to Table-D2, Appendix-D, National Plumbing Code
of the Philippines and current rainfall record from PAG-ASA (250mm/hr.)
• The Sewerage Pipe Network design shall accommodate all sewage coming from all the facilities,
conveyed by gravitational flow leading to the proposed Sewage Treatment Plant.
• The Water Supply Network shall include the provision of Fire Hydrants, accessible Drinking
Fountain that will serve as testing point for safe and potable water supply.
• Provide complete Sewer Line and Vent System from all (domestic) plumbing fixtures and floor
drains, laid by gravity flow leading to the Sewage Treatment Plant (STP);
For Demand Weight of Fixtures in Fixture Units, refer to Appendix-A, Table A-2, NPCP.
• Provide complete cold water supply pipes to all plumbing fixtures from the main water source.
• Provide separate line for water closet.
• Provide complete hot water system with portable water heaters for selected areas as required and or
specified by the Owner.
• Provide complete storm drainage system for all roofs, canopies, concrete ledges and balconies
including condensate drains laid for gravity flow connected to a leader/pipe line leading to the natural
ground level storm drainage network.
ANNEX 1: CHECKLIST OF REQUIREMENTS – DETAILED ARCHITECTURE DESIGNS
Checklist of Drawing Requirements in the preparation/evaluation/approval of Detailed Architectural and
Engineering Plans and other Documents for Infrastructure Project Implementation
Reference: Revised Implementing Rules and Regulations of the National Building Code of the Philippines (PD 1096)
SHEET
REMARKS*
NUMBER SHEET CONTENTS
Evaluated by:
Architect
Reference: Revised Implementing Rules and Regulations of the National Building Code of the Philippines
(PD 1096)
SHEET
SHEET CONTENTS REMARKS*
NUMBER
STRUCTURAL DRAWINGS (as applicable)
S – 1 (a…n) General Notes and Construction Standards
S – 2 (a…n) Foundation Plan/s (scale 1:100m minimum)
S – 3 (a…n) Floor Framing Plan/s (scale 1:100m minimum)
S – 4 (a…n) Roof Framing Plan (scale 1:100m minimum)
S – 5 (a…n) Schedule and Detail of Footings, Columns and Shear Walls
Schedule and Detail of FTB’s, Girders, Beams and Floor
S – 6 (a…n)
Slabs
S – 7 (a…n) Detail of Trusses
S – 8 (a…n) Other Structural Spot details
Structural Analysis and Design
Boring and Land Test Results
Seismic Analysis
Structural Technical Specifications
Structural Scope of Works
Structural Bill of Quantities
* To be marked as either Complying or Non Complying/Complete or Incomplete by the evaluator or
to be filled with supporting comments (use additional sheets if necessary)
Evaluated by:
Structural Engineer
Reference: Revised Implementing Rules and Regulations of the National Building Code of the Philippines
(PD 1096)
SHEET No. SHEET CONTENTS REMARKS*
ELECTRICAL DRAWINGS (as applicable)
General Notes and/or specifications
E – 1 (a…n)
Legends or Symbols
Lighting and Receptacle Outlets Layout (scale 1:100m minimum) and
E – 2 (a…n)
details including Schedule of Lighting Fixtures and Control Devices
Power Layout (scale 1:100m minimum) and details including Schedule
E – 3 (a…n)
of Panels
Electrical designed Analysis and Computation of Loads for every
E – 4 (a…n)
circuits
E – 5 (a…n) Schedule and Detail of Loads of every Panel
E – 6 (a…n) Other Electrical Detail
Electrical Computation
Design Analysis
Electrical Scope of Works
Electrical Bill of Quantities
* To be marked as either Complying or Non Complying/Complete or Incomplete by the evaluator or to
be filled with supporting comments (use additional sheets if necessary)
Evaluated
by:
Registered/Professional Electrical Engineer
ANNEX 4: CHECKLIST OF REQUIREMENTS – SANITARY/PLUMBING DESIGNS
Checklist of Drawing Requirements in the preparation/evaluation/approval of Detailed Architectural and
Engineering Plans and other Documents for Infrastructure Project Implementation
Reference: Revised Implementing Rules and Regulations of the National Building Code of the Philippines
(PD 1096)
SHEET
SHEET CONTENTS REMARKS*
NUMBER
PLUMBING/SANITARY DRAWINGS (as applicable)
P – 1 (a…n) General Notes and Legends
P – 2 (a…n) Location and Site Plan
Storm Drainage Layout (scale 1:100m minimum) including
P – 3 (a…n)
actual length of tapping line to Main Drainage Line
Water Line Layout (scale 1:100m minimum) including actual
P – 4 (a…n)
length of tapping line from main source when applicable
Sewer line and Vent line layout (scale 1:100m minimum)
P – 5 (a…n) including actual length of tapping line to septic tank or
existing sewer line
Isometric Layout, showing Waterline, Sewer line and
P – 6 (a…n)
Drainage line
P – 7 (a…n) Detail of connections, catch basins, downspouts, etc.
P – 8 (a…n) Detail of Cistern: Schedule of Pumps
P – 9 (a…n) Detail of Septic Tank/Sewage Treatment Plant
Design Analysis
Sanitary Technical Specifications
Sanitary Scope of Works
Sanitary Bill of Quantities
Evaluated by:
Sanitary Engineer
TIME FRAME
The Design-and-Build Contractor must adhere to the requirements and parameters set forth in this TOR in
order to realize Redeveloped Provincial Administration Center.
Bidders shall have Fifteen (15) calendar days for pre-design stage, and sixty (60) calendar days to
accomplish the detailed plans, designs and other needed requirements.
CONSTRUCTION STAGE:
The construction has a duration of Three Hundred Sixty (360) calendar days. The Contractor must complete
the works in accordance with the approved plans and specifications.
Hereunder are the Items of Works to be performed in the completion of the project. However, work/s that
may have been overlooked or inadvertently omitted in this TOR but important in the completion and operation
of this project shall be the sole responsibility of the Contractor.
REPORTING REQUIREMENT
A. A report shall be submitted in three (3) sets upon completion of the Architectural Space Program
Study and the Preliminary Architectural and Engineering Study (Phase 1).
B. A report shall be submitted in three (3) sets upon completion of the Indicative Master Plan and
Architectural Schematic Design Study (Phase 2).
C. A report shall be submitted in five (5) sets upon completion of the Contracts Documents Phase (Phase
4A).
D. A report shall be submitted in three (3) sets upon completion of the free-of- charge construction
bidding services.