Professional Documents
Culture Documents
CT A282944 Fin XX
CT A282944 Fin XX
CT A282944 Fin XX
Sragen
A Indonesia
REV DATE MODIFICATIONS
01 - Cover Sheet 10 - Equipment Dimensions Andreas Persada
02 - Equipment Layout
03 - Structural - Electrical Layout
11 - Delivery
12 - Disclaimer - Site Readiness GE Healthcare -
04 - Floor Structural Details Andreas.persada@ge.com
05 - Radiation Protection Layout
06 - Radiation Protection Details
07 - Power Requirements - Power Distribution
08 - HVAC - Warning Light
REVOLUTION ACT
09 - Environment - Interconnections FINAL STUDY
Drawn by Verified by Concession S.O. (GON) PIM Manual Rev
A mandatory component of this drawing set is the GE Healthcare Pre Installation manual. Failure to reference the Pre Installation manual will result in
incomplete documentation required for site design and preparation.
Pre Installation documents for GE Healthcare products can be accessed on the web at: www.gehealthcare.com/siteplanning 5487127-1EN 8
GE does not take responsibility for any damages resulting from changes on drawings made by others. Errors may occur by not referring to the complete
set of final issue drawing. GE cannot accept responsibility for any damage due to the partial use of GE final issue drawings, however caused. All
Format Scale File Name Sheet
dimensions are in millimeters unless otherwise specified. Do not scale from printed pdf files. GE accepts no responsibility or liability for defective work
due to scaling from these drawings. A3 1:40 CT-A282944-FIN-XX.DWG 01/12
EQUIPMENT LAYOUT
DIMENSIONS LxWxH WEIGHT
ITEM DESCRIPTION (mm) (kg)
2
5799
3172
5 8
7
6
R.OPERATOR
TOILET
Basic system
6 Electrical outlet 10/16A 230V + G
1 2 RJ 45 network socket
System remote control (Y), locked when power OFF "ON" and "OFF" impulse buttons with
1
indicator lamps red=ON / green=OFF located at 1.50m above floor
2 System emergency off (SEO), (recommended height 1.50m-1.85m above floor)
3000
1 System ON light (L) - 24V
1 X-Ray ON lamp (L1) - 24V
Inspector Option
1 Inspector connection point - 3Phases+N+G (Required to prepare in local)
2
5799
1 RJ 45 network socket
785 AW
3172 3 Electrical outlets for AW option: 230V 10/16A +G linked to the hospital UPS or
555
4
through a dedicated UPS of 1 kVA single phase (If available)
1 RJ45 network socket for AW option
R.OPERATOR
TOILET
61 mm
Anchor washer
Max
[29.9 in] Leveling pad Table base
15-17 mm
705
[27.8 in]
thick concrete
Min 102 mm
80 mm
80 mm
95 mm
95 mm
533
[21 in]
479 12 mm
[18.9 in]
3
377 NOTES: NOTES:
[14.8 in] · Torque anchor to 50 Nm · Torque anchor to 50 Nm
3B 150
[5.9 in]
FINISHED FLOOR REQUIREMENTS
· Installation requires a finish floor in the scan and control rooms
[14.7 in]
Gantry · The floor surface in the scan room directly under the gantry and table must be level.
373
[20.5 in]
830 kg · The floor levelness tolerance of the floor surface that the gantry and table will rest on is 6 mm over a 3000 mm distance.
520
639 · Shims should not be used to compensate for a floor that does not meet this requirement.
[10.5 in]
[25.2 in] [1829.8 lbs]
1 · Eight or more floor covering openings that are 102 mm in diameter are made to ensure the table and gantry rest on a solid surface. These
267
[5.8 in]
[37.4 in]
[39.8 in]
· The distance from central line of anchor to edge of concrete basement of Gantry/table should not be less than 155 mm.
· These requirements apply to all installation types.
[59.9 in]
1521
[63.6 in]
4 NOT TO SCALE
1616
Up/Down Table
520 kg [1146 lbs]
including 180 kg TYPICAL CABLE MANAGEMENT
[2.3 in]
212
[8.3 in]
5
Waterproof joint removable cover Dividers as required Removable coverplate
Dividers as required per local code
6 per local code
6946 mAs
CHANGED PARAMETER MULTIPLICATION FACTOR
new mAs/100
80 kV 0.24
100 kV 0.45
120 kV 0.71
140 kV 1.00
1.25 mm aperture 0.09
1.04
5 mm aperture 0.34
1.65
10 mm aperture 0.56
2.62
15 mm aperture
4.15
0.81
6.57
10.4
20 mm aperture 1.00
2
SHIELDING REQUIREMENTS:
10.4
6.57
4.15
2
2.62
Engage a qualified radiological health physicist to review your scan room shielding
1.65
requirements, taking into consideration:
1.04
· Materials used for construction of walls, floors, ceiling, doors, and windows.
· Activities in surrounding scan room areas.
· Equipment in surrounding scan room areas (e.g., film developer, film storage)
· Room size and equipment placement within the room relative to room size.
3172 The Illustrations on this page depict measured radiation levels within the scanning room,
while scanning a 32 cm CTDI phantom and using a large filter, with the technique shown. Use
the mAs, kV and aperture scaling factors in the table shown here to adjust exposure levels to
the scan technique used at the site.
NOTE: Actual measurements can vary. Expected deviations equals ±15%, expect for the 5 mA
and 1 mm techniques, where variations may be greater (up to a factor of 2), due to the
inherent deviation in small values. The maximum deviation anticipated for tube output
equals ±40%.
R.OPERATOR
TOILET
0.26 3
0.52 2.5
2
1.04
1.5 1.5
0.17 0.33 0.66 1.31 2.08
1 1
4.15
4.15 0.5 0.5
6.57
0 0
-0.5 -0.5
-1
-3 -2 -1 0 1 2 3
-2.5 -1.5 -0.5 0.5 1.5 2.5 -1.5
-2
-2.5
-3
Elevation Plan View
1.04 3
2.5
1.65
6.57 2
2.62 10.42
1.5 1.5
1.04 2.62 4.15
1.31 4.15 1 1
10.42
0.5 0.5
0 0
-0.5 -0.5
-1
-3 -2 -1 0 1 2 3
-2.5 -1.5 -0.5 0.5 1.5 2.5 -1.5
-2
-2.5
-3
Elevation Plan View
CABLES Table2:
· Power and cable installation must comply with the distribution diagram. Feeder Table - 40 kVA
· All cables must be isolated and flexible, cable color codes must comply with standards for electrical The information below assumes the use of copper wire, rated 75 C and run in steel conduit. All ampacity is determined in accordance with the
installation. National Electrical Code (NFPA 70), Table 310-16 (2002). The ampacity of the circuit protection device listed above determines the minimum
· The cables from signaling and remote control (Y, SEO, L...) will go to PDB with a pigtail length of 1.5m, and will feeder size, except where total source regulation limits require a larger size.
be connected during installation. Each conductor will be identified and isolated (screw connector). Feeder length from Power Minimum Wire Size, AWG or MCM (mm²)/VAC
Substation to MDP - ft (m) 200 VAC 220 VAC 240 VAC 380 VAC 400 VAC 420 VAC 440 VAC 460 VAC 480 VAC
CABLEWAYS 50 (15) 2 (35) 3 (30) 3 (30) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22)
The general rules for laying cableways should meet the conditions laid down in current standards and regulations, 100 (30) 2/0 (70) 1/0 (55) 1/0 (55) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22)
with regard to:
150 (46) 5/0 (125) 3/0 (85) 3/0 (85) 3 (30) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22)
· Protecting cables against water (cableways should be waterproof).
· Protecting cables against abnormal temperatures (proximity to heating pipes or ducts). 200 (61) 6/0 (170) 5/0 (125) 4/0 (100) 3 (30) 3 (30) 3 (30) 3 (30) 4 (22) 4 (22)
· Protecting cables against temperature shocks. 250 (76) 6/0 (170) 6/0 (170) 5/0 (125) 1 (45) 2 (35) 2 (35) 3 (30) 3 (30) 3 (30)
· Replacing cables (cableways should be large enough for cables to be replaced). 300 (91) 7/0 (215) 6/0 (170) 6/0 (170) 1 (45) 1 (45) 1 (45) 2 (35) 2 (35) 3 (30)
· Metal cableways should be grounded. 350 (107) 8/0 (275) 7/0 (215) 6/0 (170) 1/0 (55) 1/0 (55) 1 (45) 1 (45) 1 (45) 2 (35)
400 (122) 8/0 (275) 8/0 (275) 8/0 (275) 2/0 (70) 1/0 (55) 1/0 (55) 1 (45) 1 (45) 1 (45)
Sub-Feeder length from MDP to
PDU - ft (m)
32 (9.7536) 2 (35) 3 (30) 3 (30) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22) 4 (22)
Grounding
Run a dedicated 1/0 [55 mm²] or larger insulated copper ground wire from the power source to the MDP and from MDP to the PDU. Run the
ground wire in the same raceway with the three-phase wires.
Notes :
(1) Wire size: 2x2mm² [14AWG] and 1x2mm² [14AWG] GND
(2) Wire size: 6x2mm² [14AWG] and 1x2mm² [14AWG] GND
Storage longer than 6 months is not recommended. 11/12 JUMPER, FOR N.O. 11
(1) Non-condensing CONTACT OF DOOR SWITCH
12
12/13 JUMPER, FOR N.C.
CONTACT OF DOOR SWITCH 13
AIR RENEWAL
According to local standards.
HEAT DISSIPATION
OPERATOR CONSOLE:
· Ambient static magnetic fields less than 10 Gauss. Customer supply
AVIMOS
MAXIMUM GANTRY AUDIBLE NOISE LEVEL Console
PDB Table RCK (Option)
(Option)
· The maximum ambient noise level is produced by the gantry during a CT scan acquisition. It is less than Orderable from GE
70dBA when measured at a distance of one meter from the nearest gantry surface, in any direction. AVIMOS
Camera (3x) 25 m
MAXIMUM CONSOLE AUDIBLE NOISE LEVEL (Option) [82']
30 m
· Maximum Console Audible Noise Level The maximum ambient noise levels is less than or equal to 56dBA [98']
when measured 1m up and 1m away from the console at an ambient temperature of 26°C.
CONNECTIVITY REQUIREMENTS
Broadband Connections are necessary during the installation process and going forward to ensure full support
from the Engineering Teams for the customers system. Maximum performance and availability for the customers
system is maintained and closely monitored during the lifetime of the system.
Proactive and reactive maintenance is available utilizing the wide range of digital tools using the connectivity
solutions listed below:
The requirements for these connectivity solutions are explained in the broadband solutions catalogue (separate
document).
[5.9 in]
120 367
150
[5.5 in]
140
Rear Front 389 389
1741
20 [15.3 in] [15.3 in]
[21.7 in]
550
895
[8.7 in]
840
Scan
220
267.2 235
Centerline [9.3 in]
[41.8 in]
1062
520 Anchorage 639 599 Anchorage
[5.1 in]
300 1213 2448
[19.4 in]
350
129
494
[13.8 in]
554
700
[35.4 in]
[27.6 in]
900
Service Area
900
Scan Weight: 10 kg [22 lbs]
Centerline
Center of Gravity
SCALE 1:50 2747 441 Center of Gravity SCALE 1:20 Indicates air flow (Convection)
250
386 [9.85 in]
[15 in]
[33 in]
222 76
850
[29 in]
[3 in]
[24.59 in]
[8.75 in]
740
[22.5 in]
625
572
[20 in]
507.5
[18 in]
445
[11 in]
277.5
[12.25 in]
311
TOP VIEW
650
[26 in]
368 178
[14.5 in] [7.02 in]
[30 in]
1300
750
[33 in]
850
[51 in]
169
Table weight: 40 kg [88 lbs] [7 in] Center of gravity
SCALE 1:20 600
SCALE 1:10
[24 in]
GANTRY DELIVERY
W= 2363
[93 in]
L= 921
[36.3 in]
[74 in]
H= 1881
· The gantry is shipped on a dolly equipped with elevating casters (normal shipping configuration).
NOT TO SCALE
· Suitable radiological protection must be determined by a qualified radiological physicist in conformation with
local regulations. GE does not take responsibility for the specification or provision of radio-protection.
THE UNDERSIGNED, HEREBY CERTIFIES THAT I HAVE READ AND APPROVED THE PLANS IN THIS DOCUMENT.